UNIQUE VISTAS-BLDG. NO. 3
by MADHU HARSHAD DOSHI · Manpadha, ThaneAlso near Kolshet, brahmand, Chakala, Andheri East
Possession date of UNIQUE VISTAS-BLDG. NO. 3: 31 December 2026, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700004406, and currently active. MahaRERA has issued a regulatory order on this project. 18 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about UNIQUE VISTAS-BLDG. NO. 3?
How the possession date of UNIQUE VISTAS-BLDG. NO. 3 has moved
30 December 2021
Completion date given when the project was registered
30 December 2024
Extended at the builder's request (MahaRERA application EXT51700009599)
Reason the builder gave MahaRERA:
“WE WOULD LIKE TO EXTEND THIS PROJECT AS THIS WAS A SLUM PROJECT SO TILL DATE WE HAVE BEEN FOCUSSING ON COMPLETION OF THE SLUM AND NOW WE WILL BE COMPLETING THE SALE BUILDING. WE HAVE SOLD ONLY FEW FLATS TILL DATE. WE KINDLY REQUEST YOU TO P…” Read the full reason
“WE WOULD LIKE TO EXTEND THIS PROJECT AS THIS WAS A SLUM PROJECT SO TILL DATE WE HAVE BEEN FOCUSSING ON COMPLETION OF THE SLUM AND NOW WE WILL BE COMPLETING THE SALE BUILDING. WE HAVE SOLD ONLY FEW FLATS TILL DATE. WE KINDLY REQUEST YOU TO PLEASE EXTEND THE SAID BUILDING NO. 3 TILL 30TH DECEMBER 2024.”31 December 2025
Extended at the builder's request (MahaRERA application EA20052501192)
Reason the builder gave MahaRERA:
“The construction work of the said building is 95% completed till date. We hereby state that the area under the proposed DP road on the said plot has already been handed over to Thane Municipal Corporation vide indenture for transfer and reg…” Read the full reason
“The construction work of the said building is 95% completed till date. We hereby state that the area under the proposed DP road on the said plot has already been handed over to Thane Municipal Corporation vide indenture for transfer and registered on dated 31.10.2017 with subsequent Deed of rectification dated 07.02.2018. But till date the DP road work has not commenced yet by Thane Municipal Corporation. Further, there was a sudden intimation to us about a Thane-Borivali twin tunnel passing through our layout due to which a huge parcel of land had to be handed over which led to make necess…”31 December 2026
Extended at the builder's request (MahaRERA application EA09072621709)
Reason the builder gave MahaRERA:
“The construction of the said buildings has been completed, and we have obtained the Part Occupation Certificate comprising Lower Levels 1, 2 & 3 + Upper Stilt + 1st to 27th Floors of the said buildings vide Occupation Certificate No. OCC/N/…” Read the full reason
“The construction of the said buildings has been completed, and we have obtained the Part Occupation Certificate comprising Lower Levels 1, 2 & 3 + Upper Stilt + 1st to 27th Floors of the said buildings vide Occupation Certificate No. OCC/N/7003/0016/2026 dated 11/05/2026, issued by the Thane Municipal Corporation. We hereby confirm and declare that we have already applied for the Full Occupation Certificate on 29.06.2026 for the remaining 28th to 29th Floors + 30th Recreational as soon as possible. We further state that, pursuant to the issuance of the aforesaid Part Occupation Certificate,…”
Source: UNIQUE VISTAS-BLDG. NO. 3’s extension records on MahaRERA (P51700004406), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on UNIQUE VISTAS-BLDG. NO. 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 18 complaints and 2 court cases, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- UNIQUE VISTAS-BLDG. NO. 5P51700005345 · possession 31 Dec 2026
- MahaRERA registration
- P51700004406
- Status
- Registered and active
- Builder
- MADHU HARSHAD DOSHI
- Location
- Manpadha, Thane · 400607
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- December 2026
- Delay so far
- 60 months
- Homes
- 222
- Sold or booked
- 97%
- Towers
- 1
- Complaints on MahaRERA
- 18
- Court cases listed
- 2
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of UNIQUE VISTAS-BLDG. NO. 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| UNIQUE VISTAS BLDG NO 3 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- UNIQUE VISTAS BLDG NO 3: covers 33 floors
Latest CC order on MahaRERA: dated 30/06/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on UNIQUE VISTAS-BLDG. NO. 3 every month.
UNIQUE VISTAS-BLDG. NO. 3: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 440 | 164 |
| 2 BHK | 636 | 58 |
- Buildings: UNIQUE VISTAS BLDG NO 3 (33 floors, 222 units)
- Land: 621 sq m (about 0.2 acres) · sanctioned built-up 10,725 sq m · recreational space 5,806 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Madhu Harshad Doshi has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 3 past the promised date (typically 46 months late); 1 lapsed. 73 complaints on MahaRERA across 4 projects.
Read Google reviews of UNIQUE VISTAS-BLDG. NO. 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
UNIQUE VISTAS-BLDG. NO. 3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about UNIQUE VISTAS-BLDG. NO. 3
What is the possession date of UNIQUE VISTAS-BLDG. NO. 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for UNIQUE VISTAS-BLDG. NO. 3 in Manpadha, Thane is 31 December 2026 — 60 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for UNIQUE VISTAS-BLDG. NO. 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date UNIQUE VISTAS-BLDG. NO. 3's builder has filed on MahaRERA, the official one, is 31 December 2026, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of UNIQUE VISTAS-BLDG. NO. 3 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2024, giving the reason "WE WOULD LIKE TO EXTEND THIS PROJECT AS THIS WAS A SLUM PROJECT SO TILL DATE WE HAVE BEEN FOCUSSING ON COMPLETION OF THE SLUM AND NOW WE WILL BE COMPLETING THE SALE BUILDING. WE HAVE SOLD ONLY FEW FLATS TILL DATE. WE KINDLY REQUEST YOU TO PLEASE EXTEND THE SAID BUILDING NO. 3 TILL 30TH DECEMBER 2024."; to 31 December 2025, giving the reason "The construction work of the said building is 95% completed till date. We hereby state that the area under the proposed DP road on the said plot has already been handed over to Thane Municipal Corporation vide indenture for transfer and registered on dated 31.10.2017 with subsequent Deed of rectification dated 07.02.2018. But till date the DP road work has not commenced yet by Thane Municipal Corporation. Further, there was a sudden intimation to us about a Thane-Borivali twin tunnel passing through our layout due to which a huge parcel of land had to be handed over which led to make necess…"; to 31 December 2026, giving the reason "The construction of the said buildings has been completed, and we have obtained the Part Occupation Certificate comprising Lower Levels 1, 2 & 3 + Upper Stilt + 1st to 27th Floors of the said buildings vide Occupation Certificate No. OCC/N/7003/0016/2026 dated 11/05/2026, issued by the Thane Municipal Corporation. We hereby confirm and declare that we have already applied for the Full Occupation Certificate on 29.06.2026 for the remaining 28th to 29th Floors + 30th Recreational as soon as possible. We further state that, pursuant to the issuance of the aforesaid Part Occupation Certificate,…".
What is the RERA number of UNIQUE VISTAS-BLDG. NO. 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of UNIQUE VISTAS-BLDG. NO. 3 in Manpadha, Thane is P51700004406.
Is UNIQUE VISTAS-BLDG. NO. 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3 is registered as P51700004406 and its status is "Registered and active".
What is the construction status of UNIQUE VISTAS-BLDG. NO. 3?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on UNIQUE VISTAS BLDG NO 3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does UNIQUE VISTAS-BLDG. NO. 3 have complaints on MahaRERA?
18 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is UNIQUE VISTAS-BLDG. NO. 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3 is registered on MahaRERA as P51700004406, its completion date has moved 60 months since registration and 18 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does UNIQUE VISTAS-BLDG. NO. 3 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: UNIQUE VISTAS-BLDG. NO. 5 (P51700005345, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.
How can I get updates if UNIQUE VISTAS-BLDG. NO. 3's possession date changes?
The latest dates are on UNIQUE VISTAS-BLDG. NO. 3's MahaRERA page (P51700004406). GharKundli's Kundli Watch sends a free WhatsApp update on UNIQUE VISTAS-BLDG. NO. 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does UNIQUE VISTAS-BLDG. NO. 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3 has one building filed: UNIQUE VISTAS BLDG NO 3 with 33 floors and 222 units.
What are the flat sizes (carpet area) in UNIQUE VISTAS-BLDG. NO. 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for UNIQUE VISTAS-BLDG. NO. 3: 1 BHK: 440 sq ft carpet (164 homes); 2 BHK: 636 sq ft carpet (58 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of UNIQUE VISTAS-BLDG. NO. 3?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3 stands on 621 sq m of land (about 0.2 acres), with 10,725 sq m of sanctioned built-up area and 5,806 sq m of recreational open space.
What is the track record of UNIQUE VISTAS-BLDG. NO. 3's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhu Harshad Doshi has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 3 past the promised date (typically 46 months late); 1 lapsed. 73 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of UNIQUE VISTAS-BLDG. NO. 3?
Google Maps has reviews of UNIQUE VISTAS-BLDG. NO. 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 18 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is UNIQUE VISTAS-BLDG. NO. 3?
UNIQUE VISTAS-BLDG. NO. 3 by MADHU HARSHAD DOSHI is in Manpadha, Thane (pincode 400607), near Kolshet, brahmand, Chakala, Andheri East, Maharashtra, and is registered on MahaRERA as P51700004406, per GharKundli's check of MahaRERA records.
How many homes are in UNIQUE VISTAS-BLDG. NO. 3?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3 has 222 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.
When was UNIQUE VISTAS-BLDG. NO. 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS-BLDG. NO. 3 was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on UNIQUE VISTAS-BLDG. NO. 3?
2 court cases are listed for UNIQUE VISTAS-BLDG. NO. 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of UNIQUE VISTAS-BLDG. NO. 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MADHU HARSHAD DOSHI, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of UNIQUE VISTAS-BLDG. NO. 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Thane
- UNIQUE VISTAS-BLDG. NO. 5
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- GURUKRUPA NITYAM
- MAULI KRUPA
- LOTUS
- ASAVARI CO OP HSG SOC LTD
- Panache
Other projects by MADHU HARSHAD DOSHI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.