UNIQUE VISTAS MHADA BUILDING NO. 1,2,3

by MADHU HARSHAD DOSHI · Mira Road East, ThaneAlso near One Hiranandani Park, Village Chitalsar, Manpada, Bandra East

Possession date of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3: 30 September 2026, moved from 30 June 2022 (51 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700006925. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51700017004)

    Reason the builder gave MahaRERA:
    “The said project was running very smoothly and in a timely manner upto the hit of the Covid – 19, due to which the project has ran into delay in completion of the project as the availability of the labours and material is not with appropria…” Read the full reason“The said project was running very smoothly and in a timely manner upto the hit of the Covid – 19, due to which the project has ran into delay in completion of the project as the availability of the labours and material is not with appropriate frequency. As of which we are proposing to complete the said project by DECEMBER 2023 completely without any further delays or extensions. The said buildings Construction work has been completed. The said buildings are adjoining to the proposed 40.00 mtrs. D.P. Road, but till date Thane Municipal Corporation has not started the work on the same. Hence,…”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700025237)

    Reason the builder gave MahaRERA:
    “The said buildings Construction work has been completed. Further we inform you to the upcoming Thane – Borivali Twin tunnel is passing through our plot and our 2326.40 sq. mtrs, land is affected on the said twin tunnel. Hence, the infrastru…” Read the full reason“The said buildings Construction work has been completed. Further we inform you to the upcoming Thane – Borivali Twin tunnel is passing through our plot and our 2326.40 sq. mtrs, land is affected on the said twin tunnel. Hence, the infrastructure works like storm water Drain, underground water supply pipe network, electrical cable work is delayed. Now we have started the construction work of the said 40.00 mtrs D.P. Road on our own cost. Also Lift installation, Fire Fighting Alarm system installation and STP work is done but due to non-connectivity of power supply we are unable to test the s…”
  4. 30 September 2026

    Extended at the builder's request (MahaRERA application EA05062621251)

    Reason the builder gave MahaRERA:
    “We have completed the construction work of the said buildings and we have obtained the Full Occupation of the said buildings vide OC NO. OCC/N/7003/0016/2026 dated 11/05/2026 issued by The Thane Municipal Corporation. Therefore, we request…” Read the full reason“We have completed the construction work of the said buildings and we have obtained the Full Occupation of the said buildings vide OC NO. OCC/N/7003/0016/2026 dated 11/05/2026 issued by The Thane Municipal Corporation. Therefore, we request you to kindly grant us the Extension till the date of Occupation Certificate i.e. 11.05.2026.”

Source: UNIQUE VISTAS MHADA BUILDING NO. 1,2,3’s extension records on MahaRERA (P51700006925), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on UNIQUE VISTAS MHADA BUILDING NO. 1,2,3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700006925
Status
Lapsed (registration period ended)
Builder
MADHU HARSHAD DOSHI
Location
Mira Road East, Thane · 400607
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
June 2022
Latest completion date
September 2026
Delay so far
51 months
Homes
499
Sold or booked
0%
Towers
3
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BLDG -1100%100%100%100%
BLDG-2100%100%100%100%
BLDG -3100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BLDG -1: covers 31 floors
  • BLDG-2: covers 31 floors
  • BLDG -3: covers 31 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 every month.

UNIQUE VISTAS MHADA BUILDING NO. 1,2,3: buildings, flats and land, as filed on MahaRERA

  • Buildings: BLDG -1 (31 floors, 178 units) · BLDG-2 (31 floors, 181 units) · BLDG -3 (31 floors, 149 units)
  • Land: 1,069 sq m (about 0.3 acres) · sanctioned built-up 16,325 sq m · recreational space 5,806 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Madhu Harshad Doshi has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 3 past the promised date (typically 46 months late); 1 lapsed. 73 complaints on MahaRERA across 4 projects.

Read Google reviews of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

UNIQUE VISTAS MHADA BUILDING NO. 1,2,3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about UNIQUE VISTAS MHADA BUILDING NO. 1,2,3

What is the possession date of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 in Mira Road East, Thane is 30 September 2026 — 51 months later than 30 June 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date UNIQUE VISTAS MHADA BUILDING NO. 1,2,3's builder has filed on MahaRERA, the official one, is 30 September 2026, already 51 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2023, giving the reason "The said project was running very smoothly and in a timely manner upto the hit of the Covid – 19, due to which the project has ran into delay in completion of the project as the availability of the labours and material is not with appropriate frequency. As of which we are proposing to complete the said project by DECEMBER 2023 completely without any further delays or extensions. The said buildings Construction work has been completed. The said buildings are adjoining to the proposed 40.00 mtrs. D.P. Road, but till date Thane Municipal Corporation has not started the work on the same. Hence,…"; to 31 December 2025, giving the reason "The said buildings Construction work has been completed. Further we inform you to the upcoming Thane – Borivali Twin tunnel is passing through our plot and our 2326.40 sq. mtrs, land is affected on the said twin tunnel. Hence, the infrastructure works like storm water Drain, underground water supply pipe network, electrical cable work is delayed. Now we have started the construction work of the said 40.00 mtrs D.P. Road on our own cost. Also Lift installation, Fire Fighting Alarm system installation and STP work is done but due to non-connectivity of power supply we are unable to test the s…"; to 30 September 2026, giving the reason "We have completed the construction work of the said buildings and we have obtained the Full Occupation of the said buildings vide OC NO. OCC/N/7003/0016/2026 dated 11/05/2026 issued by The Thane Municipal Corporation. Therefore, we request you to kindly grant us the Extension till the date of Occupation Certificate i.e. 11.05.2026.".

What is the RERA number of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 in Mira Road East, Thane is P51700006925.

Is UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 is registered as P51700006925 and its status is "Lapsed (registration period ended)".

What is the construction status of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 is registered on MahaRERA as P51700006925, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 51 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if UNIQUE VISTAS MHADA BUILDING NO. 1,2,3's possession date changes?

The latest dates are on UNIQUE VISTAS MHADA BUILDING NO. 1,2,3's MahaRERA page (P51700006925). GharKundli's Kundli Watch sends a free WhatsApp update on UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 has 3 buildings filed: BLDG -1 with 31 floors and 178 units; BLDG-2 with 31 floors and 181 units; BLDG -3 with 31 floors and 149 units.

How big is the land of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 stands on 1,069 sq m of land (about 0.3 acres), with 16,325 sq m of sanctioned built-up area and 5,806 sq m of recreational open space.

What is the track record of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Madhu Harshad Doshi has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 3 past the promised date (typically 46 months late); 1 lapsed. 73 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

Google Maps has reviews of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 by MADHU HARSHAD DOSHI is in Mira Road East, Thane (pincode 400607), near One Hiranandani Park, Village Chitalsar, Manpada, Bandra East, Maharashtra, and is registered on MahaRERA as P51700006925, per GharKundli's check of MahaRERA records.

How many homes are in UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 has 499 homes in 3 towers registered on MahaRERA, and 0% of them are sold or booked.

When was UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

2 court cases are listed for UNIQUE VISTAS MHADA BUILDING NO. 1,2,3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of UNIQUE VISTAS MHADA BUILDING NO. 1,2,3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MADHU HARSHAD DOSHI, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Mira Road East

All 218 projects in Sandozbaugh (400607) →

Other projects by MADHU HARSHAD DOSHI

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.