Onkar Dham

by Subhash Mahadev Waghule · Besides HDFC Bank, Kopari Colony, Thane 400603Also near Naupada, Thane West, Bhaskar Colony

What’s in the report? →

Possession date of Onkar Dham (MahaRERA PM1330002501893): 30 April 2032. It has 20 homes, 19% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1330002501893, and currently active. Its completion date is now April 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1330002501893, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Onkar Dham?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Onkar Dham has moved

  1. 31 December 2031

    Completion date given when the project was registered

  2. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Onkar Dham’s extension records on MahaRERA (PM1330002501893), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Onkar Dham

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1330002501893
Status
Registered and active
Builder
Subhash Mahadev Waghule
Location
Besides HDFC Bank, Kopari Colony, Thane · 400603
Project type
Mixed
Registered on
26 Dec 2025
Completion date at registration
December 2031
Latest completion date
April 2032
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
20
Sold or booked
19%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Onkar Dham, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Onkar Dham10%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Onkar Dham: covers G + 7

Latest CC order on MahaRERA: dated 25/08/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Onkar Dham every 1–2 months.

Onkar Dham: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Onkar Dham →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Onkar Dham: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Onkar Dham

What is the possession date of Onkar Dham?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Onkar Dham in Besides HDFC Bank, Kopari Colony, Thane is 30 April 2032, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Onkar Dham?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Onkar Dham's builder has filed on MahaRERA, the official one, is 30 April 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Onkar Dham?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Onkar Dham in Besides HDFC Bank, Kopari Colony, Thane is PM1330002501893.

Is Onkar Dham registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham is registered as PM1330002501893 and its status is "Registered and active".

What is the current construction status of Onkar Dham? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Onkar Dham is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Onkar Dham have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Onkar Dham safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham is registered on MahaRERA as PM1330002501893, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Onkar Dham?

Onkar Dham is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Onkar Dham?

For a flat in Onkar Dham (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Onkar Dham received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham is still under construction, with 30 April 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Onkar Dham a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham is a redevelopment: 8 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Onkar Dham uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Onkar Dham was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Onkar Dham's possession date changes?

The latest dates are on Onkar Dham's MahaRERA page (PM1330002501893). GharKundli's Kundli Watch sends a free WhatsApp update on Onkar Dham every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Onkar Dham have?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham has one building filed: Onkar Dham with 8 floors and 24 units.

How much parking does Onkar Dham have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 13 covered car parking spaces for Onkar Dham.

How big is the land of Onkar Dham?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham stands on 465 sq m of land (about 0.1 acres), with 1,408 sq m of sanctioned built-up area.

What are the reviews of Onkar Dham?

Google Maps has reviews of Onkar Dham written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Onkar Dham?

Onkar Dham by Subhash Mahadev Waghule is in Besides HDFC Bank, Kopari Colony, Thane, pincode 400603 (near Naupada, Thane West, Bhaskar Colony), Maharashtra, and is registered on MahaRERA as PM1330002501893, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sainath Darshan Society, Sainath Krupa Society. GharKundli lists all 35 MahaRERA projects in Thane East (400603).

How many flats are in Onkar Dham, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham has 20 homes in 1 tower registered on MahaRERA, and 19% of them are sold or booked.

When was Onkar Dham registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Onkar Dham was registered on MahaRERA on 26 December 2025. GharKundli did not find a title report on the land on file there.

Does Onkar Dham have any legal issues or court cases?

1 court case is listed for Onkar Dham on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Onkar Dham?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Subhash Mahadev Waghule.

Other projects in Thane

All 35 projects in Thane East (400603) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.