EXCELENCIA
by KAMDHENU DEVKRUPA REALTORS LLP · Uran, Raigarh
Possession: EXCELENCIA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000000593. Status: Completed. MahaRERA has issued a regulatory order on this project. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about EXCELENCIA?
How the possession date of EXCELENCIA has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT52000013026)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for an extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for an extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”31 December 2027
Extended at the builder's request (MahaRERA application EXT52000019335)
Reason the builder gave MahaRERA:
“I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project. As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. I have also received the Order for…” Read the full reason
“I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project. As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. I have also received the Order for Extension from MahaRERA”
Source: EXCELENCIA’s extension records on MahaRERA (P52000000593), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EXCELENCIA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000000593
- Status
- Completed
- Builder
- KAMDHENU DEVKRUPA REALTORS LLP
- Location
- Uran, Raigarh · 400702
- Project type
- Others
- Registered on
- 18 Jul 2017
- Completion date at registration
- December 2022
- Latest completion date
- December 2027
- Delay so far
- 60 months
- Homes
- 191
- Towers
- 2
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of EXCELENCIA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 100% |
| WING B | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EXCELENCIA every month.
EXCELENCIA: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (20 floors) · WING B (20 floors)
- Land: 4,039 sq m (about 1.0 acres) · sanctioned built-up 6,058 sq m
The builder’s record and reviews
Devkrupa Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 11 months); 1 still being built, none past the promised date yet. 4 complaints on MahaRERA across 1 project.
Read Google reviews of EXCELENCIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EXCELENCIA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EXCELENCIA
What is the possession date of EXCELENCIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EXCELENCIA in Uran, Raigarh is 31 December 2027 — 60 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for EXCELENCIA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EXCELENCIA's builder has filed on MahaRERA, the official one, is 31 December 2027, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EXCELENCIA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for an extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2027, giving the reason "I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project. As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. I have also received the Order for Extension from MahaRERA".
What is the RERA number of EXCELENCIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EXCELENCIA in Uran, Raigarh is P52000000593.
Is EXCELENCIA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA is registered as P52000000593 and its status is "Completed".
What is the construction status of EXCELENCIA?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does EXCELENCIA have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is EXCELENCIA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA is registered on MahaRERA as P52000000593, its MahaRERA status is "Completed", its completion date has moved 60 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if EXCELENCIA's possession date changes?
The latest dates are on EXCELENCIA's MahaRERA page (P52000000593). GharKundli's Kundli Watch sends a free WhatsApp update on EXCELENCIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EXCELENCIA have?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA has 2 buildings filed: WING A with 20 floors; WING B with 20 floors.
How big is the land of EXCELENCIA?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA stands on 4,039 sq m of land (about 1.0 acres), with 6,058 sq m of sanctioned built-up area.
What is the track record of EXCELENCIA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Devkrupa Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 11 months); 1 still being built, none past the promised date yet. 4 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of EXCELENCIA?
Google Maps has reviews of EXCELENCIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EXCELENCIA?
EXCELENCIA by KAMDHENU DEVKRUPA REALTORS LLP is in Uran, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000000593, per GharKundli's check of MahaRERA records.
How many homes are in EXCELENCIA?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA has 191 homes in 2 towers registered on MahaRERA.
When was EXCELENCIA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EXCELENCIA was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on EXCELENCIA?
No court cases are listed for EXCELENCIA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of EXCELENCIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KAMDHENU DEVKRUPA REALTORS LLP.
Check it yourself on MahaRERA
- How to check the possession date of EXCELENCIA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400702
All 205 projects in Dronagiri (400702) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.