by BKS galaxy realtors Pvt ltd · Kharghar, RaigarhAlso near Sokhda

Possession: Greenwoods is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000001151. Status: Completed. 62 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Greenwoods?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Greenwoods has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52000010223)

    Reason the builder gave MahaRERA: “Delay in obtaining necessary NOC's from the respective competent authorities due to Covid-19 pandemic, thereby leading to delay in obtaining occupancy certificate.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52000013576)

    Reason the builder gave MahaRERA:
    “We hereby apply for extension of registration of project ‘Greenwoods registered with the regulatory authority vide project registration certificate bearing no. P52000001151. Delay in delivering possession of units to their purchasers is due…” Read the full reason“We hereby apply for extension of registration of project ‘Greenwoods registered with the regulatory authority vide project registration certificate bearing no. P52000001151. Delay in delivering possession of units to their purchasers is due to following reasons: i. Delay by the Aviation Ministry in issuing NOC: a. Aviation Ministry erroneously imposed height restriction in to our Project. After due follow up by Govt. of Maharashtra, Urban Development Minister with the Aviation Minister vide their letter dated 13/04/2022, we have obtained Aviation NOC dated 18/08/2022 from the competent auth…”

Source: Greenwoods’s extension records on MahaRERA (P52000001151), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Greenwoods

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 62 complaints and 1 court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000001151
Status
Completed
Builder
BKS galaxy realtors Pvt ltd
Location
Kharghar, Raigarh · 410210
Project type
Others
Registered on
26 Jul 2017
Completion date at registration
June 2021
Latest completion date
December 2023
Delay so far
30 months
Homes
196
Towers
2
Complaints on MahaRERA
62
Court cases listed
1
Appeals at the tribunal
39
Title report on file
Not found

Construction progress of Greenwoods, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%100%90%
Wing B100%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Greenwoods every month.

Greenwoods: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (34 floors) · Wing B (34 floors)
  • Land: 6,550 sq m (about 1.6 acres) · sanctioned built-up 9,824 sq m · recreational space 3,699 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Greenwoods →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Greenwoods: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Greenwoods

What is the possession date of Greenwoods?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Greenwoods in Kharghar, Raigarh is 31 December 2023 — 30 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Greenwoods?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Greenwoods's builder has filed on MahaRERA, the official one, is 31 December 2023, already 30 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Greenwoods extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "Delay in obtaining necessary NOC's from the respective competent authorities due to Covid-19 pandemic, thereby leading to delay in obtaining occupancy certificate."; to 31 December 2023, giving the reason "We hereby apply for extension of registration of project ‘Greenwoods registered with the regulatory authority vide project registration certificate bearing no. P52000001151. Delay in delivering possession of units to their purchasers is due to following reasons: i. Delay by the Aviation Ministry in issuing NOC: a. Aviation Ministry erroneously imposed height restriction in to our Project. After due follow up by Govt. of Maharashtra, Urban Development Minister with the Aviation Minister vide their letter dated 13/04/2022, we have obtained Aviation NOC dated 18/08/2022 from the competent auth…".

What is the RERA number of Greenwoods?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Greenwoods in Kharghar, Raigarh is P52000001151.

Is Greenwoods registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods is registered as P52000001151 and its status is "Completed".

What is the construction status of Greenwoods?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Greenwoods have complaints on MahaRERA?

62 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Greenwoods safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods is registered on MahaRERA as P52000001151, its MahaRERA status is "Completed", its completion date has moved 30 months since registration and 62 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Greenwoods's possession date changes?

The latest dates are on Greenwoods's MahaRERA page (P52000001151). GharKundli's Kundli Watch sends a free WhatsApp update on Greenwoods every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Greenwoods have?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods has 2 buildings filed: Wing A with 34 floors; Wing B with 34 floors.

How big is the land of Greenwoods?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods stands on 6,550 sq m of land (about 1.6 acres), with 9,824 sq m of sanctioned built-up area and 3,699 sq m of recreational open space.

Where can I read reviews of Greenwoods?

Google Maps has reviews of Greenwoods written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 62 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Greenwoods?

Greenwoods by BKS galaxy realtors Pvt ltd is in Kharghar, Raigarh (pincode 410210), near Sokhda, Maharashtra, and is registered on MahaRERA as P52000001151, per GharKundli's check of MahaRERA records.

How many homes are in Greenwoods?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods has 196 homes in 2 towers registered on MahaRERA.

When was Greenwoods registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Greenwoods was registered on MahaRERA on 26 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Greenwoods?

1 court case is listed for Greenwoods on MahaRERA, and 39 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Greenwoods?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BKS galaxy realtors Pvt ltd.