NEELKANTH VIHAR PHASE I

by NEELKANTH CONSTRUCTIONS · New Panvel, Raigarh

Possession: NEELKANTH VIHAR PHASE I is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000005312. Status: Completed. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about NEELKANTH VIHAR PHASE I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NEELKANTH VIHAR PHASE I has moved

  1. 11 September 2019

    Completion date given when the project was registered

  2. 31 May 2020

    Extended at the builder's request (MahaRERA application EXT52000002616)

    Reason the builder gave MahaRERA:
    “1. WE HAD SUBMITTED THE FILE FOR OC BUT DUE TO CHANGES IN PLANS WE ERE ORDERED TO TAKE THE AMENDED CC FIRST AND THEN GO FOR OC. WE WERE GRANTED THE AMENDED CC VIDE LETTER NO. CIDCO/NAINA/PANVEL/VICHUMBE/BP-392/ACC/2019/1149/SAP/1416 DATED 2…” Read the full reason“1. WE HAD SUBMITTED THE FILE FOR OC BUT DUE TO CHANGES IN PLANS WE ERE ORDERED TO TAKE THE AMENDED CC FIRST AND THEN GO FOR OC. WE WERE GRANTED THE AMENDED CC VIDE LETTER NO. CIDCO/NAINA/PANVEL/VICHUMBE/BP-392/ACC/2019/1149/SAP/1416 DATED 24.10.2019 THE FILE FOR OC IS UNDER PROCESS AT NAINA CIDCO AND WE WILL BE GETTING THE OC VERY SHORTLY. WER ARE UNABLE TO GIVE THE POSSESSION WITHOUT OC AS THERE WILL BE HEAVY PENALTY PAYABLE FOR THE SAME. 2. DUE TO DELAY IN GETTING OC FOR THE PROJECT WE ARE IN HEAVY DEBTS ALRREADY, AND CANT BEAR THE FINANCIAL LOSS AGAIN BY GIVING THE POSSESSION WITHOUT OC.”
  3. 30 November 2020

    Revised completion date on MahaRERA

Source: NEELKANTH VIHAR PHASE I’s extension records on MahaRERA (P52000005312), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NEELKANTH VIHAR PHASE I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the November 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000005312
Status
Completed
Builder
NEELKANTH CONSTRUCTIONS
Location
New Panvel, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
11 Aug 2017
Completion date at registration
September 2019
Latest completion date
November 2020
Delay so far
14 months
Homes
87
Towers
4
Complaints on MahaRERA
4
Court cases listed
0
Appeals at the tribunal
4
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of NEELKANTH VIHAR PHASE I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A TYPE - BUILDING 1 AND 2100%100%17%0%
B TYPE - BUILDING NO 3 AND 4100%100%70%0%
C TYPE - BUILDING NO 5100%100%55%0%
D TYPE - BUILDING NO 6 AND 7100%50%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NEELKANTH VIHAR PHASE I every month.

NEELKANTH VIHAR PHASE I: buildings, flats and land, as filed on MahaRERA

  • Buildings: A TYPE - BUILDING 1 AND 2 (5 floors) · B TYPE - BUILDING NO 3 AND 4 (5 floors) · C TYPE - BUILDING NO 5 (5 floors) · D TYPE - BUILDING NO 6 AND 7 (5 floors)
  • Land: 11,850 sq m (about 2.9 acres) · sanctioned built-up 3,249 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NEELKANTH VIHAR PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NEELKANTH VIHAR PHASE I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NEELKANTH VIHAR PHASE I

What is the possession date of NEELKANTH VIHAR PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NEELKANTH VIHAR PHASE I in New Panvel, Raigarh is 30 November 2020 — 14 months later than 11 September 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NEELKANTH VIHAR PHASE I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NEELKANTH VIHAR PHASE I's builder has filed on MahaRERA, the official one, is 30 November 2020, already 14 months later than the 11 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NEELKANTH VIHAR PHASE I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I's builder applied to MahaRERA to extend the completion date once: to 31 May 2020, giving the reason "1. WE HAD SUBMITTED THE FILE FOR OC BUT DUE TO CHANGES IN PLANS WE ERE ORDERED TO TAKE THE AMENDED CC FIRST AND THEN GO FOR OC. WE WERE GRANTED THE AMENDED CC VIDE LETTER NO. CIDCO/NAINA/PANVEL/VICHUMBE/BP-392/ACC/2019/1149/SAP/1416 DATED 24.10.2019 THE FILE FOR OC IS UNDER PROCESS AT NAINA CIDCO AND WE WILL BE GETTING THE OC VERY SHORTLY. WER ARE UNABLE TO GIVE THE POSSESSION WITHOUT OC AS THERE WILL BE HEAVY PENALTY PAYABLE FOR THE SAME. 2. DUE TO DELAY IN GETTING OC FOR THE PROJECT WE ARE IN HEAVY DEBTS ALRREADY, AND CANT BEAR THE FINANCIAL LOSS AGAIN BY GIVING THE POSSESSION WITHOUT OC.".

What is the RERA number of NEELKANTH VIHAR PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NEELKANTH VIHAR PHASE I in New Panvel, Raigarh is P52000005312.

Is NEELKANTH VIHAR PHASE I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I is registered as P52000005312 and its status is "Completed".

What is the construction status of NEELKANTH VIHAR PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 50% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does NEELKANTH VIHAR PHASE I have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NEELKANTH VIHAR PHASE I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I is registered on MahaRERA as P52000005312, its MahaRERA status is "Completed", its completion date has moved 14 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NEELKANTH VIHAR PHASE I's possession date changes?

The latest dates are on NEELKANTH VIHAR PHASE I's MahaRERA page (P52000005312). GharKundli's Kundli Watch sends a free WhatsApp update on NEELKANTH VIHAR PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NEELKANTH VIHAR PHASE I have?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I has 4 buildings filed: A TYPE - BUILDING 1 AND 2 with 5 floors; B TYPE - BUILDING NO 3 AND 4 with 5 floors; C TYPE - BUILDING NO 5 with 5 floors; D TYPE - BUILDING NO 6 AND 7 with 5 floors.

How big is the land of NEELKANTH VIHAR PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I stands on 11,850 sq m of land (about 2.9 acres), with 3,249 sq m of sanctioned built-up area.

Where can I read reviews of NEELKANTH VIHAR PHASE I?

Google Maps has reviews of NEELKANTH VIHAR PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NEELKANTH VIHAR PHASE I?

NEELKANTH VIHAR PHASE I by NEELKANTH CONSTRUCTIONS is in New Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000005312, per GharKundli's check of MahaRERA records.

How many homes are in NEELKANTH VIHAR PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I has 87 homes in 4 towers registered on MahaRERA.

When was NEELKANTH VIHAR PHASE I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NEELKANTH VIHAR PHASE I was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NEELKANTH VIHAR PHASE I?

No court cases are listed for NEELKANTH VIHAR PHASE I on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of NEELKANTH VIHAR PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NEELKANTH CONSTRUCTIONS, which has 5 other projects registered on MahaRERA.

Other projects in pincode 410206

All 2,664 projects in Panvel (410206) →

Other projects by NEELKANTH CONSTRUCTIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.