ARIHANT CLAN AALISHAN PHASE I
by ARIHANT VATIKA REALTY PRIVATE LIMITED · Panvel, Raigarh
Possession: ARIHANT CLAN AALISHAN PHASE I is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000006391. Status: Completed. 13 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ARIHANT CLAN AALISHAN PHASE I?
How the possession date of ARIHANT CLAN AALISHAN PHASE I has moved
30 March 2025
Completion date given when the project was registered
31 July 2025
Extended at the builder's request (MahaRERA application EXT52000025903)
Reason the builder gave MahaRERA:
“We are pleased to inform you that the project is now 100% complete, the PART OC OF ONE OF THE 2 BUILDING (TOWER 1 – KAVEH 1) HAS ALREADY BEEN RECEIVED and the full OC application has been submitted. However, there is a high possibility of a…” Read the full reason
“We are pleased to inform you that the project is now 100% complete, the PART OC OF ONE OF THE 2 BUILDING (TOWER 1 – KAVEH 1) HAS ALREADY BEEN RECEIVED and the full OC application has been submitted. However, there is a high possibility of a delay of 3-4 months in obtaining the Full OC due to a backlog in processing applications at the competent authority. We currently expect to receive the OC by June 2025 To ensure sufficient time for completing all formalities, we request an extension until 31/07/2025”30 September 2026
Extended at the builder's request (MahaRERA application EA29062621609)
Reason the builder gave MahaRERA:
“The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 15/10/2024 (Kaveh) and 08/05/2025 (Baraz 1) respective…” Read the full reason
“The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 15/10/2024 (Kaveh) and 08/05/2025 (Baraz 1) respectively and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, permissible built-up area, total parking, sanctioned number of floors and the number of floors for which CC has been issued. In view…”
Source: ARIHANT CLAN AALISHAN PHASE I’s extension records on MahaRERA (P52000006391), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ARIHANT CLAN AALISHAN PHASE I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 13 complaints and 4 court cases, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- ARIHANT CLAN AALISHAN PHASE IIP52000017271 · possession 30 Apr 2028
- MahaRERA registration
- P52000006391
- Status
- Completed
- Builder
- ARIHANT VATIKA REALTY PRIVATE LIMITED
- Location
- Panvel, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2025
- Latest completion date
- September 2026
- Delay so far
- 18 months
- Homes
- 527
- Sold or booked
- 75%
- Towers
- 2
- Complaints on MahaRERA
- 13
- Court cases listed
- 4
- Appeals at the tribunal
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of ARIHANT CLAN AALISHAN PHASE I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BARAZ-1 | 100% | 100% | 100% | 52% |
| KAVEH | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BARAZ-1: covers 55 floors
- KAVEH: covers 38 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT CLAN AALISHAN PHASE I every month.
ARIHANT CLAN AALISHAN PHASE I: buildings, flats and land, as filed on MahaRERA
- Buildings: BARAZ-1 (55 floors, 375 units) · KAVEH (38 floors, 152 units)
- Car parking: 785 covered
- Land: 8,644 sq m (about 2.1 acres) · sanctioned built-up 29,072 sq m · recreational space 1,838 sq m
The builder’s record and reviews
Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects.
Read Google reviews of ARIHANT CLAN AALISHAN PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARIHANT CLAN AALISHAN PHASE I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARIHANT CLAN AALISHAN PHASE I
What is the possession date of ARIHANT CLAN AALISHAN PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT CLAN AALISHAN PHASE I in Panvel, Raigarh is 30 September 2026 — 18 months later than 30 March 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ARIHANT CLAN AALISHAN PHASE I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT CLAN AALISHAN PHASE I's builder has filed on MahaRERA, the official one, is 30 September 2026, already 18 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ARIHANT CLAN AALISHAN PHASE I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2025, giving the reason "We are pleased to inform you that the project is now 100% complete, the PART OC OF ONE OF THE 2 BUILDING (TOWER 1 – KAVEH 1) HAS ALREADY BEEN RECEIVED and the full OC application has been submitted. However, there is a high possibility of a delay of 3-4 months in obtaining the Full OC due to a backlog in processing applications at the competent authority. We currently expect to receive the OC by June 2025 To ensure sufficient time for completing all formalities, we request an extension until 31/07/2025"; to 30 September 2026, giving the reason "The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 15/10/2024 (Kaveh) and 08/05/2025 (Baraz 1) respectively and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, permissible built-up area, total parking, sanctioned number of floors and the number of floors for which CC has been issued. In view…".
What is the RERA number of ARIHANT CLAN AALISHAN PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT CLAN AALISHAN PHASE I in Panvel, Raigarh is P52000006391.
Is ARIHANT CLAN AALISHAN PHASE I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I is registered as P52000006391 and its status is "Completed".
What is the construction status of ARIHANT CLAN AALISHAN PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does ARIHANT CLAN AALISHAN PHASE I have complaints on MahaRERA?
13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ARIHANT CLAN AALISHAN PHASE I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I is registered on MahaRERA as P52000006391, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 13 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does ARIHANT CLAN AALISHAN PHASE I have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ARIHANT CLAN AALISHAN PHASE II (P52000017271, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.
How can I get updates if ARIHANT CLAN AALISHAN PHASE I's possession date changes?
The latest dates are on ARIHANT CLAN AALISHAN PHASE I's MahaRERA page (P52000006391). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT CLAN AALISHAN PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARIHANT CLAN AALISHAN PHASE I have?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I has 2 buildings filed: BARAZ-1 with 55 floors and 375 units; KAVEH with 38 floors and 152 units.
How much parking does ARIHANT CLAN AALISHAN PHASE I have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 785 covered car parking spaces for ARIHANT CLAN AALISHAN PHASE I.
How big is the land of ARIHANT CLAN AALISHAN PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I stands on 8,644 sq m of land (about 2.1 acres), with 29,072 sq m of sanctioned built-up area and 1,838 sq m of recreational open space.
What is the track record of ARIHANT CLAN AALISHAN PHASE I's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ARIHANT CLAN AALISHAN PHASE I?
Google Maps has reviews of ARIHANT CLAN AALISHAN PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARIHANT CLAN AALISHAN PHASE I?
ARIHANT CLAN AALISHAN PHASE I by ARIHANT VATIKA REALTY PRIVATE LIMITED is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000006391, per GharKundli's check of MahaRERA records.
How many homes are in ARIHANT CLAN AALISHAN PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I has 527 homes in 2 towers registered on MahaRERA, and 75% of them are sold or booked.
When was ARIHANT CLAN AALISHAN PHASE I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT CLAN AALISHAN PHASE I was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ARIHANT CLAN AALISHAN PHASE I?
4 court cases are listed for ARIHANT CLAN AALISHAN PHASE I on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ARIHANT CLAN AALISHAN PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT VATIKA REALTY PRIVATE LIMITED, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ARIHANT CLAN AALISHAN PHASE I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410206
- Wise City RZ-01 Plotted Development - Phase 3
- Crystal Co-Operative Housing Society Limited
- SAI SIDDHI MADHUBAN
- Pandurang Heights
- Sai Nilay
- MUKTA RESIDENCY
- Shanmukhi Spanda
- Shivesh Mahavir
Other projects by ARIHANT VATIKA REALTY PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.