by VIJAY KAMDAR · east, MumbaiAlso near Andheri West, Marol, D.N.Nagar

Possession: 10 Square is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800004094. Status: Completed. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about 10 Square?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 10 Square has moved

  1. 30 June 2018

    Completion date given when the project was registered

  2. 30 June 2019

    Extended at the builder's request (MahaRERA application EXT51800000576)

    Reason the builder gave MahaRERA:
    “We are eligible for additional FSI based on the width of the road. To consume this additional FSI we need additional height of the building. For this height we have approached Civil Aviation of India Delhi to grant us that additional height…” Read the full reason“We are eligible for additional FSI based on the width of the road. To consume this additional FSI we need additional height of the building. For this height we have approached Civil Aviation of India Delhi to grant us that additional height based on our eligibility.”
  3. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT51800006197)

    Reason the builder gave MahaRERA:
    “To The Real Estate Regulatory Authority 'A' Wing, SRA Building Anant Kanekar Road Bandra (East), Mumbai 400 051 Sir, Sub : APPLICATION FOR EXTENSION OF REGISTRATION OF PROJECT [Under Rule 7(1)] I hereby apply for renewal of registration cer…” Read the full reason“To The Real Estate Regulatory Authority 'A' Wing, SRA Building Anant Kanekar Road Bandra (East), Mumbai 400 051 Sir, Sub : APPLICATION FOR EXTENSION OF REGISTRATION OF PROJECT [Under Rule 7(1)] I hereby apply for renewal of registration certificate of the following project: 10 Square, Plot Bearing / CTS / Survey / Final Plot No.: 1 00/1/2 at Andheri, Andheri, Mumbai Suburban, 400069. Registered with the Authority vide Project Registration Certificate bearing No. P51800004094, which expires on 31/03/2019. The part occupation certificate (O.C) i.e. upto 10th floor has been issued by M.C.G.M.…”
  4. 30 June 2022

    Revised completion date on MahaRERA

Source: 10 Square’s extension records on MahaRERA (P51800004094), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 10 Square

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004094
Status
Completed
Builder
VIJAY KAMDAR
Location
east, Mumbai · 400069
Project type
Residential / Group Housing
Registered on
7 Aug 2017
Completion date at registration
June 2018
Latest completion date
June 2022
Delay so far
48 months
Homes
30
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found

Construction progress of 10 Square, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
10 Square100%100%90%70%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 10 Square every month.

10 Square: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of 10 Square →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

10 Square: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 10 Square

What is the possession date of 10 Square?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 10 Square in east, Mumbai is 30 June 2022 — 48 months later than 30 June 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for 10 Square?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 10 Square's builder has filed on MahaRERA, the official one, is 30 June 2022, already 48 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 10 Square extended?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2019, giving the reason "We are eligible for additional FSI based on the width of the road. To consume this additional FSI we need additional height of the building. For this height we have approached Civil Aviation of India Delhi to grant us that additional height based on our eligibility."; to 31 December 2021, giving the reason "To The Real Estate Regulatory Authority 'A' Wing, SRA Building Anant Kanekar Road Bandra (East), Mumbai 400 051 Sir, Sub : APPLICATION FOR EXTENSION OF REGISTRATION OF PROJECT [Under Rule 7(1)] I hereby apply for renewal of registration certificate of the following project: 10 Square, Plot Bearing / CTS / Survey / Final Plot No.: 1 00/1/2 at Andheri, Andheri, Mumbai Suburban, 400069. Registered with the Authority vide Project Registration Certificate bearing No. P51800004094, which expires on 31/03/2019. The part occupation certificate (O.C) i.e. upto 10th floor has been issued by M.C.G.M.…".

What is the RERA number of 10 Square?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 10 Square in east, Mumbai is P51800004094.

Is 10 Square registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square is registered as P51800004094 and its status is "Completed".

What is the construction status of 10 Square?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square's status on MahaRERA is "Completed". As filed by the builder, slab work on 10 Square is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does 10 Square have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 10 Square safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square is registered on MahaRERA as P51800004094, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 10 Square's possession date changes?

The latest dates are on 10 Square's MahaRERA page (P51800004094). GharKundli's Kundli Watch sends a free WhatsApp update on 10 Square every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 10 Square have?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square has one building filed: 10 Square with 13 floors.

How big is the land of 10 Square?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square stands on 891 sq m of land (about 0.2 acres), with 2,328 sq m of sanctioned built-up area.

Where can I read reviews of 10 Square?

Google Maps has reviews of 10 Square written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 10 Square?

10 Square by VIJAY KAMDAR is in east, Mumbai (pincode 400069), near Andheri West, Marol, D.N.Nagar, Maharashtra, and is registered on MahaRERA as P51800004094, per GharKundli's check of MahaRERA records. Its boundaries filed there include JIVA MAHALE ROAD.

How many homes are in 10 Square?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square has 30 homes in 1 tower registered on MahaRERA.

When was 10 Square registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 10 Square was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on 10 Square?

No court cases are listed for 10 Square on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of 10 Square?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIJAY KAMDAR.