THE KOLLAGE

by ZIRE RUSHI CONSTRUCTION · Andheri East, MumbaiAlso near Vile Parle east, Andheri West, Vile Parle West

Possession date of THE KOLLAGE: 15 August 2026, moved from 30 December 2022 (44 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800012084. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (August 2026) has passed.

What do you want to know about THE KOLLAGE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of THE KOLLAGE has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013087)

    Reason the builder gave MahaRERA:
    “The present project comprising of Phase-I having Basement, Ground Plus 12 floors including 2 podium and Phase-II having additional four residential upper floors above 12 floors. Part Occupancy Permissions for Phase – I is received on 26th M…” Read the full reason“The present project comprising of Phase-I having Basement, Ground Plus 12 floors including 2 podium and Phase-II having additional four residential upper floors above 12 floors. Part Occupancy Permissions for Phase – I is received on 26th March 2021 and and balance oc upto 12th floor on 19th October 2022. The balance of Phase-II is under construction and delayed due to reasons beyond our control as under: 1. Originally although the concessions for the present project was approved till 16 upper floors, due to subsequent restrictions by the Aviation Authorities on account of directions of the…”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019125)

    Reason the builder gave MahaRERA:
    “The Promoter is developing a project with as on date, two wings i.e. wing A & B having common Basement (for stack parking) + 3rd to 13 th upper floors for both wings as per plans and permissions approved by the MCGM from time to time. T…” Read the full reason“The Promoter is developing a project with as on date, two wings i.e. wing A & B having common Basement (for stack parking) + 3rd to 13 th upper floors for both wings as per plans and permissions approved by the MCGM from time to time. The Promoter have already obtained Part Occupancy Permissions for the two wings till 12 th Upper Floors and handed over possession to all the Allottees of the Project Occupation certificate of one upper floor at 13 th Floor level is pending The construction of the balance one upper floor i.e. 13 th Floor and overhead water tank, is at the advanced stage an…”
  4. 12 June 2025

    Extended at the builder's request (MahaRERA application EXT51800026076)

    Reason the builder gave MahaRERA:
    “we, M/s. Zire Rushi Construction, hereby declare the following with respect to the project The Kollage bearing registration number. P51800012084 registered under MahaRERA. The delay in the completion of the real estate project has been prim…” Read the full reason“we, M/s. Zire Rushi Construction, hereby declare the following with respect to the project The Kollage bearing registration number. P51800012084 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 12/06/2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring ti…”
  5. 15 August 2026

    Extended at the builder's request (MahaRERA application EA18052621002)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 12/06/2025 and we have also initiated the process for…” Read the full reason“The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 12/06/2025 and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, sanctioned number of floors and the total number of parking. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provi…”

Source: THE KOLLAGE’s extension records on MahaRERA (P51800012084), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on THE KOLLAGE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints and 3 court cases, and how it ended
  • Construction pace against the August 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800012084
Status
Lapsed (registration period ended)
Builder
ZIRE RUSHI CONSTRUCTION
Location
Andheri East, Mumbai · 400069
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
December 2022
Latest completion date
August 2026
Delay so far
44 months
Homes
72
Sold or booked
78%
Towers
1
Complaints on MahaRERA
3
Court cases listed
3
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of THE KOLLAGE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
THE KOLLAGE100%100%99%100%

Commencement certificate (CC), as filed on MahaRERA

  • THE KOLLAGE: covers 15 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE KOLLAGE every month.

THE KOLLAGE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK1,129 – 1,45225
2 BHK939 – 1,01620
1 BHK611 – 81818
Other223 – 2709
Office Space5,1471

The builder’s record and reviews

Zire Rushi Construction has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 29 months); 1 still being built, none past the promised date yet. 3 complaints on MahaRERA across 1 project.

Read Google reviews of THE KOLLAGE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

THE KOLLAGE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about THE KOLLAGE

What is the possession date of THE KOLLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE KOLLAGE in Andheri East, Mumbai is 15 August 2026 — 44 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for THE KOLLAGE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date THE KOLLAGE's builder has filed on MahaRERA, the official one, is 15 August 2026, already 44 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of THE KOLLAGE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2023, giving the reason "The present project comprising of Phase-I having Basement, Ground Plus 12 floors including 2 podium and Phase-II having additional four residential upper floors above 12 floors. Part Occupancy Permissions for Phase – I is received on 26th March 2021 and and balance oc upto 12th floor on 19th October 2022. The balance of Phase-II is under construction and delayed due to reasons beyond our control as under: 1. Originally although the concessions for the present project was approved till 16 upper floors, due to subsequent restrictions by the Aviation Authorities on account of directions of the…"; to 30 December 2024, giving the reason "The Promoter is developing a project with as on date, two wings i.e. wing A & B having common Basement (for stack parking) + 3rd to 13 th upper floors for both wings as per plans and permissions approved by the MCGM from time to time. The Promoter have already obtained Part Occupancy Permissions for the two wings till 12 th Upper Floors and handed over possession to all the Allottees of the Project Occupation certificate of one upper floor at 13 th Floor level is pending The construction of the balance one upper floor i.e. 13 th Floor and overhead water tank, is at the advanced stage an…"; to 12 June 2025, giving the reason "we, M/s. Zire Rushi Construction, hereby declare the following with respect to the project The Kollage bearing registration number. P51800012084 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 12/06/2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring ti…"; to 15 August 2026, giving the reason "The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 12/06/2025 and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, sanctioned number of floors and the total number of parking. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provi…".

What is the RERA number of THE KOLLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE KOLLAGE in Andheri East, Mumbai is P51800012084.

Is THE KOLLAGE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE is registered as P51800012084 and its status is "Lapsed (registration period ended)".

What is the construction status of THE KOLLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on THE KOLLAGE is 100% done and internal work 99%. GharKundli's full report compares construction progress with the deadline.

Does THE KOLLAGE have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is THE KOLLAGE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE is registered on MahaRERA as P51800012084, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 44 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if THE KOLLAGE's possession date changes?

The latest dates are on THE KOLLAGE's MahaRERA page (P51800012084). GharKundli's Kundli Watch sends a free WhatsApp update on THE KOLLAGE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does THE KOLLAGE have?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE has one building filed: THE KOLLAGE with 18 floors and 73 units.

What are the flat sizes (carpet area) in THE KOLLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for THE KOLLAGE: 3 BHK: 1129 to 1452 sq ft carpet (25 homes); 2 BHK: 939 to 1016 sq ft carpet (20 homes); 1 BHK: 611 to 818 sq ft carpet (18 homes); Other: 223 to 270 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of THE KOLLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE stands on 2,869 sq m of land (about 0.7 acres), with 5,420 sq m of sanctioned built-up area.

What is the track record of THE KOLLAGE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Zire Rushi Construction has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 29 months); 1 still being built, none past the promised date yet. 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of THE KOLLAGE?

Google Maps has reviews of THE KOLLAGE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is THE KOLLAGE?

THE KOLLAGE by ZIRE RUSHI CONSTRUCTION is in Andheri East, Mumbai (pincode 400069), near Vile Parle east, Andheri West, Vile Parle West, Maharashtra, and is registered on MahaRERA as P51800012084, per GharKundli's check of MahaRERA records. Its boundaries filed there include 36MT WIDE NS PHADKE MARG.

How many homes are in THE KOLLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE has 72 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.

When was THE KOLLAGE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE KOLLAGE was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on THE KOLLAGE?

3 court cases are listed for THE KOLLAGE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of THE KOLLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ZIRE RUSHI CONSTRUCTION, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400069

All 96 projects in Andheri East (400069) →

Other projects by ZIRE RUSHI CONSTRUCTION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.