Kyron

by Zire Rushi Construction · Andheri East, Mumbai

Registered on MahaRERA under PC1180002600583, and currently active. Its completion date has moved from December 2028 to April 2029, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
PC1180002600583
Status
Registered and active
Builder
Zire Rushi Construction
Location
Andheri East, Mumbai · 400069
Project type
Commercial
Registered on
1 Jun 2026
Completion date at registration
December 2028
Latest completion date
April 2029
Delay so far
4 months
Homes
0
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

GharKundli’s full report on Kyron

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

Kyron: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Kyron

Is Kyron registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kyron is registered as PC1180002600583 and its status is "Registered and active".

Where is Kyron?

Kyron by Zire Rushi Construction is in Andheri East, Mumbai (pincode 400069), Maharashtra, and is registered on MahaRERA as PC1180002600583, per GharKundli's check of MahaRERA records.

When is possession of Kyron due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kyron in Andheri East, Mumbai is 30 April 2029 — 4 months later than 31 December 2028, the date given at registration.

Does Kyron have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Kyron?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Zire Rushi Construction, which has 1 other project registered on MahaRERA.

Other projects in pincode 400069

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.