Anandi Heights

by Marvel Buildcon · Panvel, Raigarh

Possession date of Anandi Heights: 30 November 2024, moved from 31 March 2020 (56 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000003690. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (November 2024) has passed.

What do you want to know about Anandi Heights?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Anandi Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the November 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000003690
Status
Lapsed (registration period ended)
Builder
Marvel Buildcon
Location
Panvel, Raigarh · 410206
Project type
Others
Registered on
6 Aug 2017
Completion date at registration
March 2020
Latest completion date
November 2024
Delay so far
56 months
Homes
69
Sold or booked
100%
Towers
1
Complaints on MahaRERA
5
Court cases listed
0
Appeals at the tribunal
3
Title report on file
Not found

Construction progress of Anandi Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Anandi Heights100%100%100%70%

Commencement certificate (CC), as filed on MahaRERA

  • Anandi Heights: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anandi Heights every month.

Anandi Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: Anandi Heights (13 floors, 80 units)
  • Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 2,999 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Anandi Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Anandi Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Anandi Heights

What is the possession date of Anandi Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Anandi Heights in Panvel, Raigarh is 30 November 2024 — 56 months later than 31 March 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Anandi Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Anandi Heights's builder has filed on MahaRERA, the official one, is 30 November 2024, already 56 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Anandi Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Anandi Heights in Panvel, Raigarh is P52000003690.

Is Anandi Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandi Heights is registered as P52000003690 and its status is "Lapsed (registration period ended)".

What is the construction status of Anandi Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandi Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Anandi Heights is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Anandi Heights have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Anandi Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandi Heights is registered on MahaRERA as P52000003690, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 56 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Anandi Heights's possession date changes?

The latest dates are on Anandi Heights's MahaRERA page (P52000003690). GharKundli's Kundli Watch sends a free WhatsApp update on Anandi Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Anandi Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandi Heights has one building filed: Anandi Heights with 13 floors and 80 units.

How big is the land of Anandi Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandi Heights stands on 2,000 sq m of land (about 0.5 acres), with 2,999 sq m of sanctioned built-up area.

Where can I read reviews of Anandi Heights?

Google Maps has reviews of Anandi Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Anandi Heights?

Anandi Heights by Marvel Buildcon is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000003690, per GharKundli's check of MahaRERA records.

How many homes are in Anandi Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandi Heights has 69 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Anandi Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandi Heights was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Anandi Heights?

No court cases are listed for Anandi Heights on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Anandi Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Marvel Buildcon.

Other projects in pincode 410206

All 2,664 projects in Panvel (410206) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.