SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS
by SHAH GROUP BUILDERS LTD · kHARGHAR, RaigarhAlso near Sokhda
Possession date of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000011435, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
How the possession date of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS has moved
30 December 2023
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT52000024547)
Reason the builder gave MahaRERA:
“The project under consideration has been stressed and stalled owing to various debts and mounting interest of secured nature. The company was subject to insolvency proceedings under IBC 2016 for two times. However, management was hopeful of…” Read the full reason
“The project under consideration has been stressed and stalled owing to various debts and mounting interest of secured nature. The company was subject to insolvency proceedings under IBC 2016 for two times. However, management was hopeful of completion of the project and therefore negotiated with the financial institution and the society of home buyers from time to time. The secured creditors has shown inclination for settlement through OTS and hence management could carve out the company from insolvency law and at present company is out of insolvency proceedings. Management has devised plan…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS’s extension records on MahaRERA (P52000011435), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints and 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000011435
- Status
- Registered and active
- Builder
- SHAH GROUP BUILDERS LTD
- Location
- kHARGHAR, Raigarh · 410210
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2028
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 48
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 4
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHAH KINGDOM PHASE III SHOPI C WING SHOPS AND PODIUMS | 100% | 100% | 87% | 0% |
| RESIDENTIAL | 100% | 100% | 87% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHAH KINGDOM PHASE III SHOPI C WING SHOPS AND PODIUMS: covers 1 floors
- RESIDENTIAL: covers 27 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS every month.
SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS: buildings, flats and land, as filed on MahaRERA
- Buildings: SHAH KINGDOM PHASE III SHOPI C WING SHOPS AND PODIUMS (1 floors, 71 units) · RESIDENTIAL (31 floors, 48 units)
- Car parking: 50 open
- Land: 3,721 sq m (about 0.9 acres) · sanctioned built-up 5,198 sq m
The builder’s record and reviews
Shah Group Builders has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 still being built, 5 past the promised date (typically 18 months late). 12 complaints on MahaRERA across 5 projects.
Read Google reviews of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS
What is the possession date of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS in kHARGHAR, Raigarh is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The project under consideration has been stressed and stalled owing to various debts and mounting interest of secured nature. The company was subject to insolvency proceedings under IBC 2016 for two times. However, management was hopeful of completion of the project and therefore negotiated with the financial institution and the society of home buyers from time to time. The secured creditors has shown inclination for settlement through OTS and hence management could carve out the company from insolvency law and at present company is out of insolvency proceedings. Management has devised plan…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS in kHARGHAR, Raigarh is P52000011435.
Is SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS is registered as P52000011435 and its status is "Registered and active".
What is the construction status of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS is registered on MahaRERA as P52000011435, its completion date has moved 48 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS's possession date changes?
The latest dates are on SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS's MahaRERA page (P52000011435). GharKundli's Kundli Watch sends a free WhatsApp update on SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS has 2 buildings filed: SHAH KINGDOM PHASE III SHOPI C WING SHOPS AND PODIUMS with 1 floors and 71 units; RESIDENTIAL with 31 floors and 48 units.
How much parking does SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 50 open car parking spaces for SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS.
How big is the land of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS stands on 3,721 sq m of land (about 0.9 acres), with 5,198 sq m of sanctioned built-up area.
What is the track record of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shah Group Builders has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 still being built, 5 past the promised date (typically 18 months late). 12 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
Google Maps has reviews of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS by SHAH GROUP BUILDERS LTD is in kHARGHAR, Raigarh (pincode 410210), near Sokhda, Maharashtra, and is registered on MahaRERA as P52000011435, per GharKundli's check of MahaRERA records.
How many homes are in SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS has 48 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
1 court case is listed for SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHAH GROUP BUILDERS LTD, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHAH KINGDOM PHASE III C WING SHOPS AND PODIUMS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in pincode 410210
- SATYAM VALENCIA
- Nisarg Aura
- Utsav Residency Building No. 1 A and B
- Raya
- THE CRYSTAL PALACE
- Bhagwati Gami Altair
- Gami Bhagwati Orelia
- MADHURAAJ KEDARNATH
Other projects by SHAH GROUP BUILDERS LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.