SIDDHIVINAYAK HEIGHTS

by LACHHMAN VASDEV BATHIJA · Kalamboli, Raigarh

Possession date of SIDDHIVINAYAK HEIGHTS: 31 July 2018. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000006905. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2018) has passed.

What do you want to know about SIDDHIVINAYAK HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SIDDHIVINAYAK HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the July 2018 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000006905
Status
Lapsed (registration period ended)
Builder
LACHHMAN VASDEV BATHIJA
Location
Kalamboli, Raigarh · 410206
Project type
Others
Registered on
16 Aug 2017
Completion date at registration
July 2018
Homes
61
Towers
1
Complaints on MahaRERA
5
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SIDDHIVINAYAK HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SIDDHIVINAYAK HEIGHTS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIDDHIVINAYAK HEIGHTS every month.

SIDDHIVINAYAK HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: SIDDHIVINAYAK HEIGHTS (18 floors)
  • Land: 1,795 sq m (about 0.4 acres) · sanctioned built-up 2,619 sq m

The builder’s record and reviews

Lachhman Vasdev Bathija has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. 11 complaints on MahaRERA across 2 projects.

Read Google reviews of SIDDHIVINAYAK HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SIDDHIVINAYAK HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SIDDHIVINAYAK HEIGHTS

What is the possession date of SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SIDDHIVINAYAK HEIGHTS in Kalamboli, Raigarh is 31 July 2018. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SIDDHIVINAYAK HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SIDDHIVINAYAK HEIGHTS's builder has filed on MahaRERA, the official one, is 31 July 2018, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SIDDHIVINAYAK HEIGHTS in Kalamboli, Raigarh is P52000006905.

Is SIDDHIVINAYAK HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHIVINAYAK HEIGHTS is registered as P52000006905 and its status is "Lapsed (registration period ended)".

What is the construction status of SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHIVINAYAK HEIGHTS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SIDDHIVINAYAK HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SIDDHIVINAYAK HEIGHTS have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SIDDHIVINAYAK HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHIVINAYAK HEIGHTS is registered on MahaRERA as P52000006905, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SIDDHIVINAYAK HEIGHTS's possession date changes?

The latest dates are on SIDDHIVINAYAK HEIGHTS's MahaRERA page (P52000006905). GharKundli's Kundli Watch sends a free WhatsApp update on SIDDHIVINAYAK HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SIDDHIVINAYAK HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHIVINAYAK HEIGHTS has one building filed: SIDDHIVINAYAK HEIGHTS with 18 floors.

How big is the land of SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHIVINAYAK HEIGHTS stands on 1,795 sq m of land (about 0.4 acres), with 2,619 sq m of sanctioned built-up area.

What is the track record of SIDDHIVINAYAK HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Lachhman Vasdev Bathija has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. 11 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SIDDHIVINAYAK HEIGHTS?

Google Maps has reviews of SIDDHIVINAYAK HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SIDDHIVINAYAK HEIGHTS?

SIDDHIVINAYAK HEIGHTS by LACHHMAN VASDEV BATHIJA is in Kalamboli, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000006905, per GharKundli's check of MahaRERA records.

How many homes are in SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHIVINAYAK HEIGHTS has 61 homes in 1 tower registered on MahaRERA.

When was SIDDHIVINAYAK HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHIVINAYAK HEIGHTS was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SIDDHIVINAYAK HEIGHTS?

No court cases are listed for SIDDHIVINAYAK HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SIDDHIVINAYAK HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LACHHMAN VASDEV BATHIJA, which has 1 other project registered on MahaRERA.

Other projects in Kalamboli

All 2,664 projects in Panvel (410206) →

Other projects by LACHHMAN VASDEV BATHIJA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.