CENTURY HEIGHTS

by PRABHU VIRJI PATEL · Kalamboli, RaigarhAlso near Kamothe

Possession date of CENTURY HEIGHTS: 30 September 2027, moved from 30 September 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000053508, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about CENTURY HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CENTURY HEIGHTS has moved

  1. 30 September 2026

    Completion date given when the project was registered

  2. 30 September 2027

    Extended at the builder's request (MahaRERA application EA23072621841)

    Reason the builder gave MahaRERA:
    “Reasons for seeking extension of Proposed Date of Completion (PDOC): The Promoter, M/s. Shubh Realty Prop. Prabhu Virji Patel, is seeking a 12-month extension of the PDOC for the project "Century Heights" (RERA Reg. No. P52000053508) from 3…” Read the full reason“Reasons for seeking extension of Proposed Date of Completion (PDOC): The Promoter, M/s. Shubh Realty Prop. Prabhu Virji Patel, is seeking a 12-month extension of the PDOC for the project "Century Heights" (RERA Reg. No. P52000053508) from 30/09/2026 to 30/09/2027 due to circumstances entirely beyond its control. The project is critically dependent on the sanction of Additional Floor Space Index (FSI) by way of TDR (Transferable Development Rights) by PMC (Panvel Municipal Corporation).”

Source: CENTURY HEIGHTS’s extension records on MahaRERA (P52000053508), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CENTURY HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000053508
Status
Registered and active
Builder
PRABHU VIRJI PATEL
Location
Kalamboli, Raigarh · 410218
Project type
Others
Registered on
8 Nov 2023
Completion date at registration
September 2026
Latest completion date
September 2027
Delay so far
12 months
Homes
78
Sold or booked
61%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of CENTURY HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CENTURY HEIGHTS100%100%33%0%

Commencement certificate (CC), as filed on MahaRERA

  • CENTURY HEIGHTS: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CENTURY HEIGHTS every month.

CENTURY HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: CENTURY HEIGHTS (19 floors, 109 units)
  • Land: 1,549 sq m (about 0.4 acres) · sanctioned built-up 5,258 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of CENTURY HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CENTURY HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CENTURY HEIGHTS

What is the possession date of CENTURY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CENTURY HEIGHTS in Kalamboli, Raigarh is 30 September 2027 — 12 months later than 30 September 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for CENTURY HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CENTURY HEIGHTS's builder has filed on MahaRERA, the official one, is 30 September 2027, already 12 months later than the 30 September 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CENTURY HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 30 September 2027, giving the reason "Reasons for seeking extension of Proposed Date of Completion (PDOC): The Promoter, M/s. Shubh Realty Prop. Prabhu Virji Patel, is seeking a 12-month extension of the PDOC for the project "Century Heights" (RERA Reg. No. P52000053508) from 30/09/2026 to 30/09/2027 due to circumstances entirely beyond its control. The project is critically dependent on the sanction of Additional Floor Space Index (FSI) by way of TDR (Transferable Development Rights) by PMC (Panvel Municipal Corporation).".

What is the RERA number of CENTURY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CENTURY HEIGHTS in Kalamboli, Raigarh is P52000053508.

Is CENTURY HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS is registered as P52000053508 and its status is "Registered and active".

What is the construction status of CENTURY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CENTURY HEIGHTS is 100% done and internal work 33%. GharKundli's full report compares construction progress with the deadline.

Does CENTURY HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is CENTURY HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS is registered on MahaRERA as P52000053508, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CENTURY HEIGHTS's possession date changes?

The latest dates are on CENTURY HEIGHTS's MahaRERA page (P52000053508). GharKundli's Kundli Watch sends a free WhatsApp update on CENTURY HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CENTURY HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS has one building filed: CENTURY HEIGHTS with 19 floors and 109 units.

How big is the land of CENTURY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS stands on 1,549 sq m of land (about 0.4 acres), with 5,258 sq m of sanctioned built-up area.

Where can I read reviews of CENTURY HEIGHTS?

Google Maps has reviews of CENTURY HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CENTURY HEIGHTS?

CENTURY HEIGHTS by PRABHU VIRJI PATEL is in Kalamboli, Raigarh (pincode 410218), near Kamothe, Maharashtra, and is registered on MahaRERA as P52000053508, per GharKundli's check of MahaRERA records.

How many homes are in CENTURY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS has 78 homes in 1 tower registered on MahaRERA, and 61% of them are sold or booked.

When was CENTURY HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CENTURY HEIGHTS was registered on MahaRERA on 8 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on CENTURY HEIGHTS?

No court cases are listed for CENTURY HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of CENTURY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRABHU VIRJI PATEL.

All projects with possession due in 2027 in Raigad →

Other projects in pincode 410218

All 85 projects in Kalamboli (410218) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.