PRAYAG CITY Phase I
by PRAYAG BUILDERS AND DEVELOPERS · Vihighar, Raigarh
Possession: PRAYAG CITY Phase I is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000004381. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about PRAYAG CITY Phase I?
How the possession date of PRAYAG CITY Phase I has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT52000003783)
Reason the builder gave MahaRERA:
“With due responsibility we intend to complete the work on time. But, due to heavy rain fall in the month of June, July, August, September, October and November in the year 2019 and non availability of construction material, specially sand a…” Read the full reason
“With due responsibility we intend to complete the work on time. But, due to heavy rain fall in the month of June, July, August, September, October and November in the year 2019 and non availability of construction material, specially sand and aggregates, the project is delayed. We regret for the same. We request you to provide extension to our project . We will complete the project before extended completion date 30st Dec 2020.”30 December 2021
Revised completion date on MahaRERA
Source: PRAYAG CITY Phase I’s extension records on MahaRERA (P52000004381), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PRAYAG CITY Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000004381
- Status
- Completed
- Builder
- PRAYAG BUILDERS AND DEVELOPERS
- Location
- Vihighar, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 393
- Towers
- 8
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of PRAYAG CITY Phase I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING 1 WING A B | 100% | 100% | 100% | 100% |
| BUILDING 2 WING C D | 100% | 100% | 100% | 100% |
| BUILDING 3 WING E F | 100% | 100% | 100% | 100% |
| BUILDING 4 WING G H | 100% | 100% | 100% | 100% |
| BUILDING 5 WING I J | 100% | 100% | 100% | 100% |
| BUILDING 6 WING K L | 100% | 100% | 100% | 100% |
| BUILDING 7 WING M N | 100% | 100% | 100% | 100% |
| BUILDING 8 WING O | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRAYAG CITY Phase I every month.
PRAYAG CITY Phase I: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING 1 WING A B (6 floors) · BUILDING 2 WING C D (6 floors) · BUILDING 3 WING E F (6 floors) · BUILDING 4 WING G H (6 floors) · BUILDING 5 WING I J (6 floors) · BUILDING 6 WING K L (6 floors) · BUILDING 7 WING M N (6 floors) · BUILDING 8 WING O (5 floors)
- Land: 10,900 sq m (about 2.7 acres) · sanctioned built-up 13,068 sq m · recreational space 1,378 sq m
The builder’s record and reviews
Prayag Builders AND Developers (a group of 3 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 9 months); 1 still being built, 1 past the promised date (typically 18 months late). 3 complaints on MahaRERA across 2 projects.
Read Google reviews of PRAYAG CITY Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PRAYAG CITY Phase I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PRAYAG CITY Phase I
What is the possession date of PRAYAG CITY Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PRAYAG CITY Phase I in Vihighar, Raigarh is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PRAYAG CITY Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PRAYAG CITY Phase I's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PRAYAG CITY Phase I extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "With due responsibility we intend to complete the work on time. But, due to heavy rain fall in the month of June, July, August, September, October and November in the year 2019 and non availability of construction material, specially sand and aggregates, the project is delayed. We regret for the same. We request you to provide extension to our project . We will complete the project before extended completion date 30st Dec 2020.".
What is the RERA number of PRAYAG CITY Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PRAYAG CITY Phase I in Vihighar, Raigarh is P52000004381.
Is PRAYAG CITY Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I is registered as P52000004381 and its status is "Completed".
What is the construction status of PRAYAG CITY Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does PRAYAG CITY Phase I have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PRAYAG CITY Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I is registered on MahaRERA as P52000004381, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PRAYAG CITY Phase I's possession date changes?
The latest dates are on PRAYAG CITY Phase I's MahaRERA page (P52000004381). GharKundli's Kundli Watch sends a free WhatsApp update on PRAYAG CITY Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PRAYAG CITY Phase I have?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I has 8 buildings filed: BUILDING 1 WING A B with 6 floors; BUILDING 2 WING C D with 6 floors; BUILDING 3 WING E F with 6 floors; BUILDING 4 WING G H with 6 floors; BUILDING 5 WING I J with 6 floors; BUILDING 6 WING K L with 6 floors; and 2 more.
How big is the land of PRAYAG CITY Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I stands on 10,900 sq m of land (about 2.7 acres), with 13,068 sq m of sanctioned built-up area and 1,378 sq m of recreational open space.
What is the track record of PRAYAG CITY Phase I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Prayag Builders AND Developers (a group of 3 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 9 months); 1 still being built, 1 past the promised date (typically 18 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PRAYAG CITY Phase I?
Google Maps has reviews of PRAYAG CITY Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PRAYAG CITY Phase I?
PRAYAG CITY Phase I by PRAYAG BUILDERS AND DEVELOPERS is in Vihighar, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000004381, per GharKundli's check of MahaRERA records.
How many homes are in PRAYAG CITY Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I has 393 homes in 8 towers registered on MahaRERA.
When was PRAYAG CITY Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PRAYAG CITY Phase I was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on PRAYAG CITY Phase I?
No court cases are listed for PRAYAG CITY Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PRAYAG CITY Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRAYAG BUILDERS AND DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PRAYAG CITY Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Panvel
- PARSHWA CITY BUILDING NO.1
- GAURI NANDAN
- Sai Nilay
- PRAKASH TOWER
- Shivesh Mahavir
- SAI SIDDHI MADHUBAN
- Crystal Co-Operative Housing Society Limited
- Indiabulls Park 1
Other projects by PRAYAG BUILDERS AND DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.