PRAYAG GHARKUL
by PRAYAG BUILDERS AND DEVELOPERS · Panvel, Raigarh
Possession date of PRAYAG GHARKUL: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000022086, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PRAYAG GHARKUL?
How the possession date of PRAYAG GHARKUL has moved
30 December 2023
Completion date given when the project was registered
30 December 2026
Extended at the builder's request (MahaRERA application EXT52000013437)
Reason the builder gave MahaRERA:
“Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making applicat…” Read the full reason
“Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making application for the registration of ‘PRAYAG GHARKUL’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30th DECEMBER 2023 as the project completion date, we will not able to complete the project due to various unavoidable reasons. Such as 1. In 2020 due to the Pandemic situation of COVID-19 and lock…”31 December 2027
Extended at the builder's request (MahaRERA application EA08092502532)
Reason the builder gave MahaRERA:
“The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely im…” Read the full reason
“The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of personal assets. This decisive action…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PRAYAG GHARKUL’s extension records on MahaRERA (P52000022086), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PRAYAG GHARKUL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000022086
- Status
- Registered and active
- Builder
- PRAYAG BUILDERS AND DEVELOPERS
- Location
- Panvel, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2019
- Completion date at registration
- December 2023
- Latest completion date
- April 2028
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 266
- Sold or booked
- 30%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of PRAYAG GHARKUL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUIDING 3 WING H | 100% | 100% | 20% | 0% |
| BUILDING 1 WING A B C D E | 100% | 100% | 100% | 0% |
| BULDING 2 WING F G | 100% | 100% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUIDING 3 WING H: covers 8 floors
- BUILDING 1 WING A B C D E: covers 6 floors
- BULDING 2 WING F G: covers 8 floors
Latest CC order on MahaRERA: dated 14/08/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRAYAG GHARKUL every month.
PRAYAG GHARKUL: buildings, flats and land, as filed on MahaRERA
- Buildings: BUIDING 3 WING H (8 floors, 61 units) · BUILDING 1 WING A B C D E (6 floors, 135 units) · BULDING 2 WING F G (8 floors, 82 units)
- Car parking: 83 covered, 27 open
- Land: 7,586 sq m (about 1.9 acres) · sanctioned built-up 11,708 sq m · recreational space 816 sq m
The builder’s record and reviews
Prayag Builders AND Developers (a group of 3 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 9 months); 1 still being built, 1 past the promised date (typically 18 months late). 3 complaints on MahaRERA across 2 projects.
Read Google reviews of PRAYAG GHARKUL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PRAYAG GHARKUL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PRAYAG GHARKUL
What is the possession date of PRAYAG GHARKUL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PRAYAG GHARKUL in Panvel, Raigarh is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PRAYAG GHARKUL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PRAYAG GHARKUL's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PRAYAG GHARKUL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2026, giving the reason "Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making application for the registration of ‘PRAYAG GHARKUL’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30th DECEMBER 2023 as the project completion date, we will not able to complete the project due to various unavoidable reasons. Such as 1. In 2020 due to the Pandemic situation of COVID-19 and lock…"; to 31 December 2027, giving the reason "The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of personal assets. This decisive action…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PRAYAG GHARKUL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PRAYAG GHARKUL in Panvel, Raigarh is P52000022086.
Is PRAYAG GHARKUL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL is registered as P52000022086 and its status is "Registered and active".
What is the construction status of PRAYAG GHARKUL?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does PRAYAG GHARKUL have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PRAYAG GHARKUL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL is registered on MahaRERA as P52000022086, its completion date has moved 48 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PRAYAG GHARKUL's possession date changes?
The latest dates are on PRAYAG GHARKUL's MahaRERA page (P52000022086). GharKundli's Kundli Watch sends a free WhatsApp update on PRAYAG GHARKUL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PRAYAG GHARKUL have?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL has 3 buildings filed: BUIDING 3 WING H with 8 floors and 61 units; BUILDING 1 WING A B C D E with 6 floors and 135 units; BULDING 2 WING F G with 8 floors and 82 units.
How much parking does PRAYAG GHARKUL have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 83 covered and 27 open car parking spaces for PRAYAG GHARKUL.
How big is the land of PRAYAG GHARKUL?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL stands on 7,586 sq m of land (about 1.9 acres), with 11,708 sq m of sanctioned built-up area and 816 sq m of recreational open space.
What is the track record of PRAYAG GHARKUL's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Prayag Builders AND Developers (a group of 3 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 9 months); 1 still being built, 1 past the promised date (typically 18 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PRAYAG GHARKUL?
Google Maps has reviews of PRAYAG GHARKUL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PRAYAG GHARKUL?
PRAYAG GHARKUL by PRAYAG BUILDERS AND DEVELOPERS is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000022086, per GharKundli's check of MahaRERA records.
How many homes are in PRAYAG GHARKUL?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL has 266 homes in 3 towers registered on MahaRERA, and 30% of them are sold or booked.
When was PRAYAG GHARKUL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRAYAG GHARKUL was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on PRAYAG GHARKUL?
No court cases are listed for PRAYAG GHARKUL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PRAYAG GHARKUL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRAYAG BUILDERS AND DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PRAYAG GHARKUL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in pincode 410206
- Wise City RZ-01 Plotted Development - Phase 3
- Crystal Co-Operative Housing Society Limited
- SAI SIDDHI MADHUBAN
- Pandurang Heights
- Sai Nilay
- MUKTA RESIDENCY
- Shanmukhi Spanda
- Shivesh Mahavir
Other projects by PRAYAG BUILDERS AND DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.