LIVSMART KURLA
by D. K. REALTY (INDIA) PVT. LTD. · Kurla West, MumbaiAlso near Ghatkopar East, Ghatkopar west, Ghatkopar Kirol
Possession date of LIVSMART KURLA: 12 July 2028, moved from 30 December 2021 (75 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800000340, and currently active. Its completion date has moved from December 2021 to July 2028: 75 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 23 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about LIVSMART KURLA?
How the possession date of LIVSMART KURLA has moved
30 December 2021
Completion date given when the project was registered
12 March 2028
Extended at the builder's request (MahaRERA application EA24122518954)
Reason the builder gave MahaRERA:
“D.K. Realty (India) Private Limited (“Promoter”) declares that under a Development Agreement dated 11 December 2015, Housing Development and Infrastructure Limited (HDIL) granted the Promoter exclusive and irrevocable development rights ove…” Read the full reason
“D.K. Realty (India) Private Limited (“Promoter”) declares that under a Development Agreement dated 11 December 2015, Housing Development and Infrastructure Limited (HDIL) granted the Promoter exclusive and irrevocable development rights over 85,000 sq. mtrs. of sale FSI on the property at Kurla, Mumbai, including rights to construct, develop, sell, create third-party interests, and obtain SRA lease rights. Based on this, the Promoter obtained revised approvals from the Slum Rehabilitation Authority (SRA) through an Intimation of Approval dated 1 January 2016 for development of a residential…”12 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: LIVSMART KURLA’s extension records on MahaRERA (P51800000340), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LIVSMART KURLA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 23 complaints and 22 court cases, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800000340
- Status
- Registered and active
- Builder
- D. K. REALTY (INDIA) PVT. LTD.
- Location
- Kurla West, Mumbai · 400070
- Project type
- Mixed
- Registered on
- 15 Jul 2017
- Completion date at registration
- December 2021
- Latest completion date
- July 2028
- Delay so far
- 75 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 1,694
- Sold or booked
- 34%
- Towers
- 28
- Complaints on MahaRERA
- 23
- Court cases listed
- 22
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of LIVSMART KURLA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING 1 | 100% | 100% | 0% | 0% |
| WING 2 | 100% | 100% | 0% | 0% |
| WING 3 | 100% | 0% | 0% | 0% |
| WING 4 | 100% | 0% | 0% | 0% |
| WING 5 | 100% | 0% | 0% | 0% |
| WING 6 | 80% | 0% | 0% | 0% |
| WING 7 | 100% | 0% | 0% | 0% |
| WING 8 | 100% | 0% | 0% | 0% |
| WING 9 | 80% | 0% | 0% | 0% |
| WING 10 | 100% | 0% | 0% | 0% |
| WING 11 | 100% | 0% | 0% | 0% |
| WING 12 | 100% | 0% | 0% | 0% |
| WING 13 | 80% | 0% | 0% | 0% |
| WING 14 | 100% | 0% | 0% | 0% |
| WING 15 | 100% | 0% | 0% | 0% |
| WING 16 | 80% | 0% | 0% | 0% |
| WING 17 | 80% | 0% | 0% | 0% |
| WING 18 | 100% | 0% | 0% | 0% |
| WING 19 | 100% | 0% | 0% | 0% |
| WING 20 | 100% | 0% | 0% | 0% |
| WING 21 | 75% | 0% | 0% | 0% |
| WING 22 | 100% | 0% | 0% | 0% |
| WING 23 | 75% | 0% | 0% | 0% |
| WING 24 | 75% | 0% | 0% | 0% |
| WING 25 | 75% | 0% | 0% | 0% |
| WING 26 | 75% | 0% | 0% | 0% |
| WING 27 | 75% | 0% | 0% | 0% |
| WING 28 | 75% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING 1: covers 13 floors
- WING 2: covers 13 floors
- WING 3: covers 13 floors
- WING 4: covers 13 floors
- WING 5: covers 13 floors
- WING 6: covers 12 floors
- WING 7: covers 13 floors
- WING 8: covers 13 floors
- WING 9: covers 12 floors
- WING 10: covers 13 floors
- WING 11: covers 13 floors
- WING 12: covers 13 floors
- WING 13: covers 12 floors
- WING 14: covers 13 floors
- WING 15: covers 13 floors
- WING 16: covers 12 floors
- WING 17: covers 12 floors
- WING 18: covers 13 floors
- WING 19: covers 13 floors
- WING 20: covers 13 floors
- WING 21: covers 12 floors
- WING 22: covers 13 floors
- WING 23: covers 12 floors
- WING 24: covers 12 floors
- WING 25: covers 12 floors
- WING 26: covers 12 floors
- WING 27: covers 12 floors
- WING 28: covers 12 floors
Latest CC order on MahaRERA: dated 17/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LIVSMART KURLA every month.
LIVSMART KURLA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 382 – 391 | 850 |
| 2 BHK | 386 – 579 | 844 |
| Shops | 1,358 – 2,227 | 5 |
| Office Space | 1,467 – 3,237 | 4 |
- Buildings: WING 1 (17 floors, 59 units) · WING 2 (17 floors, 56 units) · WING 3 (17 floors, 80 units) · WING 4 (17 floors, 56 units) · WING 5 (17 floors, 59 units) · WING 6 (17 floors, 60 units) · WING 7 (17 floors, 56 units) · WING 8 (17 floors, 60 units) · and 20 more
- Car parking: 537 covered
- Land: 18,564 sq m (about 4.6 acres) · sanctioned built-up 85,188 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of LIVSMART KURLA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LIVSMART KURLA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LIVSMART KURLA
What is the possession date of LIVSMART KURLA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LIVSMART KURLA in Kurla West, Mumbai is 12 July 2028 — 75 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for LIVSMART KURLA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LIVSMART KURLA's builder has filed on MahaRERA, the official one, is 12 July 2028, already 75 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LIVSMART KURLA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA's builder applied to MahaRERA to extend the completion date once: to 12 March 2028, giving the reason "D.K. Realty (India) Private Limited (“Promoter”) declares that under a Development Agreement dated 11 December 2015, Housing Development and Infrastructure Limited (HDIL) granted the Promoter exclusive and irrevocable development rights over 85,000 sq. mtrs. of sale FSI on the property at Kurla, Mumbai, including rights to construct, develop, sell, create third-party interests, and obtain SRA lease rights. Based on this, the Promoter obtained revised approvals from the Slum Rehabilitation Authority (SRA) through an Intimation of Approval dated 1 January 2016 for development of a residential…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of LIVSMART KURLA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LIVSMART KURLA in Kurla West, Mumbai is P51800000340.
Is LIVSMART KURLA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA is registered as P51800000340 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of LIVSMART KURLA?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 28 towers. GharKundli's full report compares construction progress with the deadline.
Does LIVSMART KURLA have complaints on MahaRERA?
23 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is LIVSMART KURLA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA is registered on MahaRERA as P51800000340, its completion date has moved 75 months since registration, 23 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LIVSMART KURLA's possession date changes?
The latest dates are on LIVSMART KURLA's MahaRERA page (P51800000340). GharKundli's Kundli Watch sends a free WhatsApp update on LIVSMART KURLA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LIVSMART KURLA have?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA has 28 buildings filed: WING 1 with 17 floors and 59 units; WING 2 with 17 floors and 56 units; WING 3 with 17 floors and 80 units; WING 4 with 17 floors and 56 units; WING 5 with 17 floors and 59 units; WING 6 with 17 floors and 60 units; and 22 more.
What are the flat sizes (carpet area) in LIVSMART KURLA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for LIVSMART KURLA: 1 BHK: 382 to 391 sq ft carpet (850 homes); 2 BHK: 386 to 579 sq ft carpet (844 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does LIVSMART KURLA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 537 covered car parking spaces for LIVSMART KURLA.
How big is the land of LIVSMART KURLA?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA stands on 18,564 sq m of land (about 4.6 acres), with 85,188 sq m of sanctioned built-up area.
Where can I read reviews of LIVSMART KURLA?
Google Maps has reviews of LIVSMART KURLA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 23 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LIVSMART KURLA?
LIVSMART KURLA by D. K. REALTY (INDIA) PVT. LTD. is in Kurla West, Mumbai (pincode 400070), near Ghatkopar East, Ghatkopar west, Ghatkopar Kirol, Maharashtra, and is registered on MahaRERA as P51800000340, per GharKundli's check of MahaRERA records.
How many homes are in LIVSMART KURLA?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA has 1,694 homes in 28 towers registered on MahaRERA, and 34% of them are sold or booked.
When was LIVSMART KURLA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LIVSMART KURLA was registered on MahaRERA on 15 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on LIVSMART KURLA?
22 court cases are listed for LIVSMART KURLA on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of LIVSMART KURLA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is D. K. REALTY (INDIA) PVT. LTD..
Check it yourself on MahaRERA
- How to check the possession date of LIVSMART KURLA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400070
- JAI SHREERAM PRASANNA CHSL
- ANUPAM VILLA CHSL
- SAI CHAMUNDA
- TWIN GALAXY
- Kalyan Kutir Co-operative Housing Society Limited
- DERAIYA LUXURIO
- Taiba Residency
- Dadamiya’s Man'souza Height
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.