by ARION DEVELOPERS & REALTORS PVT. LTD. (Living) · Alibag, Raigarh

Possession: INAARA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000012163. Status: Completed. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about INAARA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of INAARA has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 March 2020

    Extended at the builder's request (MahaRERA application EXT52000001499)

    Reason the builder gave MahaRERA:
    “1) Heavy Monsoon in Raigarh Region during the year 2018: Leading to excessive site flooding and long periods of dangerous working conditions for shuttering, concreting and labour works, periodic unavailability of labour. 2) GST Effect: Dela…” Read the full reason“1) Heavy Monsoon in Raigarh Region during the year 2018: Leading to excessive site flooding and long periods of dangerous working conditions for shuttering, concreting and labour works, periodic unavailability of labour. 2) GST Effect: Delay in procurement of materials and labour. 3) Shortage of raw material, crushed sand required for construction activities.”
  3. 30 April 2023

    Extended at the builder's request (MahaRERA application EXT52000011740)

    Reason the builder gave MahaRERA: “Application For OC Certificate”
  4. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT52000019071)

    Reason the builder gave MahaRERA: “RERA revalidation is required for the sale and registration of unsold inventory to further prospective clients. And in order to facilitate sales of unsold inventory to achieve complete OC for the project.”

Source: INAARA’s extension records on MahaRERA (P52000012163), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on INAARA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the March 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000012163
Status
Completed
Builder
ARION DEVELOPERS & REALTORS PVT. LTD.
Location
Alibag, Raigarh · 402201
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
March 2019
Latest completion date
March 2025
Delay so far
72 months
Homes
88
Towers
3
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found

Construction progress of INAARA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BLOCK A100%0%0%0%
BLOCK B100%50%0%0%
CLUB HOUSE0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on INAARA every month.

INAARA: buildings, flats and land, as filed on MahaRERA

  • Buildings: BLOCK A (5 floors) · BLOCK B (5 floors) · CLUB HOUSE (2 floors)
  • Land: 4,250 sq m (about 1.1 acres) · sanctioned built-up 3,276 sq m · recreational space 425 sq m

The builder’s record and reviews

Living Stone Construction (a group of 7 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 67 months); 3 still being built, 2 past the promised date (typically 12 months late); 3 lapsed. 5 complaints on MahaRERA across 2 projects.

Read Google reviews of INAARA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

INAARA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about INAARA

What is the possession date of INAARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for INAARA in Alibag, Raigarh is 31 March 2025 — 72 months later than 31 March 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for INAARA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date INAARA's builder has filed on MahaRERA, the official one, is 31 March 2025, already 72 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of INAARA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2020, giving the reason "1) Heavy Monsoon in Raigarh Region during the year 2018: Leading to excessive site flooding and long periods of dangerous working conditions for shuttering, concreting and labour works, periodic unavailability of labour. 2) GST Effect: Delay in procurement of materials and labour. 3) Shortage of raw material, crushed sand required for construction activities."; to 30 April 2023, giving the reason "Application For OC Certificate"; to 31 March 2025, giving the reason "RERA revalidation is required for the sale and registration of unsold inventory to further prospective clients. And in order to facilitate sales of unsold inventory to achieve complete OC for the project.".

What is the RERA number of INAARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of INAARA in Alibag, Raigarh is P52000012163.

Is INAARA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA is registered as P52000012163 and its status is "Completed".

What is the construction status of INAARA?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 50% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does INAARA have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is INAARA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA is registered on MahaRERA as P52000012163, its MahaRERA status is "Completed", its completion date has moved 72 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if INAARA's possession date changes?

The latest dates are on INAARA's MahaRERA page (P52000012163). GharKundli's Kundli Watch sends a free WhatsApp update on INAARA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does INAARA have?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA has 3 buildings filed: BLOCK A with 5 floors; BLOCK B with 5 floors; CLUB HOUSE with 2 floors.

How big is the land of INAARA?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA stands on 4,250 sq m of land (about 1.1 acres), with 3,276 sq m of sanctioned built-up area and 425 sq m of recreational open space.

What is the track record of INAARA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Living Stone Construction (a group of 7 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 67 months); 3 still being built, 2 past the promised date (typically 12 months late); 3 lapsed. 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of INAARA?

Google Maps has reviews of INAARA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is INAARA?

INAARA by ARION DEVELOPERS & REALTORS PVT. LTD. (Living) is in Alibag, Raigarh (pincode 402201), Maharashtra, and is registered on MahaRERA as P52000012163, per GharKundli's check of MahaRERA records.

How many homes are in INAARA?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA has 88 homes in 3 towers registered on MahaRERA.

When was INAARA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), INAARA was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on INAARA?

No court cases are listed for INAARA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of INAARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARION DEVELOPERS & REALTORS PVT. LTD., the company Living files this project under.