by Arvind Victory Builder · Vashi, Raigarh

Possession date of Guru Shradha: 31 May 2019, moved from 31 May 2018 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000010290. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (May 2019) has passed.

What do you want to know about Guru Shradha?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Guru Shradha has moved

  1. 31 May 2018

    Completion date given when the project was registered

  2. 31 May 2019

    Extended at the builder's request (MahaRERA application EXT52000000314)

    Reason the builder gave MahaRERA:
    “The Status of Guru Shradha is that we have completed 85% of the construction work which can be seen for Architect Report .We are awaiting the final order from collector office to avail the Balance FSI and 6 Lift's for the approval of revise…” Read the full reason“The Status of Guru Shradha is that we have completed 85% of the construction work which can be seen for Architect Report .We are awaiting the final order from collector office to avail the Balance FSI and 6 Lift's for the approval of revised plans .Which we are expected to get in one months time. The chronological approval status of the same as follows: 1) Revised Plan was submitted to collector office on 10/07/2017. 2) While approval was received by the office of Dy director-Town Planning, Alibaug, vide order no.Token No. 13271/2017 dated 21/12/2017. 3)Thereafter NOC required from Tehsilda…”

Source: Guru Shradha’s extension records on MahaRERA (P52000010290), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Guru Shradha

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the May 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000010290
Status
Lapsed (registration period ended)
Builder
Arvind Victory Builder
Location
Vashi, Raigarh · 410201
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
May 2018
Latest completion date
May 2019
Delay so far
12 months
Homes
94
Towers
6
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Guru Shradha, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%100%50%
Wing B100%100%80%40%
Wing C100%100%60%40%
Wing D100%100%40%20%
Wing E100%100%40%20%
Wing F100%100%60%20%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Guru Shradha every month.

Guru Shradha: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (4 floors) · Wing B (4 floors) · Wing C (4 floors) · Wing D (4 floors) · Wing E (4 floors) · Wing F (4 floors)
  • Land: 3,740 sq m (about 0.9 acres) · sanctioned built-up 3,470 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Guru Shradha →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Guru Shradha: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Guru Shradha

What is the possession date of Guru Shradha?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Guru Shradha in Vashi, Raigarh is 31 May 2019 — 12 months later than 31 May 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Guru Shradha?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Guru Shradha's builder has filed on MahaRERA, the official one, is 31 May 2019, already 12 months later than the 31 May 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Guru Shradha extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha's builder applied to MahaRERA to extend the completion date once: to 31 May 2019, giving the reason "The Status of Guru Shradha is that we have completed 85% of the construction work which can be seen for Architect Report .We are awaiting the final order from collector office to avail the Balance FSI and 6 Lift's for the approval of revised plans .Which we are expected to get in one months time. The chronological approval status of the same as follows: 1) Revised Plan was submitted to collector office on 10/07/2017. 2) While approval was received by the office of Dy director-Town Planning, Alibaug, vide order no.Token No. 13271/2017 dated 21/12/2017. 3)Thereafter NOC required from Tehsilda…".

What is the RERA number of Guru Shradha?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Guru Shradha in Vashi, Raigarh is P52000010290.

Is Guru Shradha registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha is registered as P52000010290 and its status is "Lapsed (registration period ended)".

What is the construction status of Guru Shradha?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.

Does Guru Shradha have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Guru Shradha safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha is registered on MahaRERA as P52000010290, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Guru Shradha's possession date changes?

The latest dates are on Guru Shradha's MahaRERA page (P52000010290). GharKundli's Kundli Watch sends a free WhatsApp update on Guru Shradha every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Guru Shradha have?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha has 6 buildings filed: Wing A with 4 floors; Wing B with 4 floors; Wing C with 4 floors; Wing D with 4 floors; Wing E with 4 floors; Wing F with 4 floors.

How big is the land of Guru Shradha?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha stands on 3,740 sq m of land (about 0.9 acres), with 3,470 sq m of sanctioned built-up area.

Where can I read reviews of Guru Shradha?

Google Maps has reviews of Guru Shradha written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Guru Shradha?

Guru Shradha by Arvind Victory Builder is in Vashi, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000010290, per GharKundli's check of MahaRERA records.

How many homes are in Guru Shradha?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha has 94 homes in 6 towers registered on MahaRERA.

When was Guru Shradha registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Guru Shradha was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Guru Shradha?

No court cases are listed for Guru Shradha on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Guru Shradha?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Arvind Victory Builder.

Other projects in Vashi

All 311 projects in Karjat (410201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.