Possession date of Godrej Bayview: 30 April 2029, moved from 31 December 2027 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700031726, and currently active. Its completion date has moved from December 2027 to April 2029: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Godrej Bayview?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Godrej Bayview has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA18072621791)

    Reason the builder gave MahaRERA:
    “1. The project is approximately 45% completed. 2. Form B has been uploaded. 3. The PERT Chart is uploaded. 4. The project was delayed due to the following reasons:- - Post COVID-19 Impact resulting into labour shortages, delays in procureme…” Read the full reason“1. The project is approximately 45% completed. 2. Form B has been uploaded. 3. The PERT Chart is uploaded. 4. The project was delayed due to the following reasons:- - Post COVID-19 Impact resulting into labour shortages, delays in procurement of construction materials, and escalation in construction and labour costs, low sales, flow of revenue and War Situation. totaling the Delay of more than 12 months 5. Application for extension for 12 months, i.e., up to 31/12/2028 u/s. 6 6. The Promoter assures the Hon'ble Authority that the project shall be completed within the extended period and the…”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Godrej Bayview’s extension records on MahaRERA (P51700031726), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Godrej Bayview

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 2 court cases, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700031726
Status
Registered and active
Builder
Suncity Infrastructures (Mumbai) LLP
Location
Vashi, Thane · 400703
Project type
Residential / Group Housing
Registered on
8 Nov 2021
Completion date at registration
December 2027
Latest completion date
April 2029
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
244
Sold or booked
73%
Towers
2
Complaints on MahaRERA
2
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Godrej Bayview, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower 2100%79.16%0%0%
Tower 30%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Tower 2: covers 29 floors
  • Tower 3: covers 29 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Godrej Bayview every month.

Godrej Bayview: buildings, flats and land, as filed on MahaRERA

  • Buildings: Tower 2 (29 floors, 113 units) · Tower 3 (29 floors, 131 units)
  • Car parking: 337 covered
  • Land: 7,750 sq m (about 1.9 acres) · sanctioned built-up 14,161 sq m · recreational space 2,424 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Godrej Properties (a group of 18 linked companies) has 98 projects on MahaRERA since 2017, this one included. Of the 92 GharKundli has checked: 21 finished, 16 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late). 565 complaints on MahaRERA across 59 projects.

Read Google reviews of Godrej Bayview →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Godrej Bayview: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Godrej Bayview

What is the possession date of Godrej Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Godrej Bayview in Vashi, Thane is 30 April 2029 — 12 months later than 31 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Godrej Bayview?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Godrej Bayview's builder has filed on MahaRERA, the official one, is 30 April 2029, already 12 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Godrej Bayview extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "1. The project is approximately 45% completed. 2. Form B has been uploaded. 3. The PERT Chart is uploaded. 4. The project was delayed due to the following reasons:- - Post COVID-19 Impact resulting into labour shortages, delays in procurement of construction materials, and escalation in construction and labour costs, low sales, flow of revenue and War Situation. totaling the Delay of more than 12 months 5. Application for extension for 12 months, i.e., up to 31/12/2028 u/s. 6 6. The Promoter assures the Hon'ble Authority that the project shall be completed within the extended period and the…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Godrej Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Godrej Bayview in Vashi, Thane is P51700031726.

Is Godrej Bayview registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview is registered as P51700031726 and its status is "Registered and active".

What is the construction status of Godrej Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 79.16% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Godrej Bayview have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Godrej Bayview safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview is registered on MahaRERA as P51700031726, its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Godrej Bayview's possession date changes?

The latest dates are on Godrej Bayview's MahaRERA page (P51700031726). GharKundli's Kundli Watch sends a free WhatsApp update on Godrej Bayview every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Godrej Bayview have?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview has 2 buildings filed: Tower 2 with 29 floors and 113 units; Tower 3 with 29 floors and 131 units.

How much parking does Godrej Bayview have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 337 covered car parking spaces for Godrej Bayview.

How big is the land of Godrej Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview stands on 7,750 sq m of land (about 1.9 acres), with 14,161 sq m of sanctioned built-up area and 2,424 sq m of recreational open space.

What is the track record of Godrej Bayview's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Properties (a group of 18 linked companies) has 98 projects on MahaRERA since 2017, this one included. Of the 92 GharKundli has checked: 21 finished, 16 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late). 565 complaints on MahaRERA across 59 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Godrej Bayview?

Google Maps has reviews of Godrej Bayview written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Godrej Bayview?

Godrej Bayview by Suncity Infrastructures (Mumbai) LLP (Godrej) is in Vashi, Thane (pincode 400703), Maharashtra, and is registered on MahaRERA as P51700031726, per GharKundli's check of MahaRERA records.

How many homes are in Godrej Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview has 244 homes in 2 towers registered on MahaRERA, and 73% of them are sold or booked.

When was Godrej Bayview registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Bayview was registered on MahaRERA on 8 November 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Godrej Bayview?

2 court cases are listed for Godrej Bayview on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Godrej Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Suncity Infrastructures (Mumbai) LLP, the company Godrej files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2029 in Thane →

Other projects in pincode 400703

All 58 projects in Vashi (400703) →

Other projects by Suncity Infrastructures (Mumbai) LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.