Possession date of AUROUS: 31 December 2026, moved from 30 October 2024 (26 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700018167, and currently active. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AUROUS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AUROUS has moved

  1. 30 October 2024

    Completion date given when the project was registered

  2. 29 October 2025

    Extended at the builder's request (MahaRERA application EA26092401831)

    Reason the builder gave MahaRERA: “The project was delayed majorly due to the pandemic as there was immense shortage of labour for a long time. Everything is functioning smoothly and we have also received the amended plans. We expect the Occupancy Certificate shortly.”
  3. 31 January 2026

    Extended at the builder's request (MahaRERA application EA06122518562)

    Reason the builder gave MahaRERA:
    “We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highe…” Read the full reason“We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. We are committed to completing the project efficiently and effectively, and we believe that this extension will enable us to meet all expectations without compromising on quality.”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA30012619641)

    Reason the builder gave MahaRERA:
    “The delay in completion of the Project has occurred on account of revision of the sanctioned plans. Initially, the Project was sanctioned by the Competent Planning Authority with a permissible Floor Space Index (“FSI”) allowing construction…” Read the full reason“The delay in completion of the Project has occurred on account of revision of the sanctioned plans. Initially, the Project was sanctioned by the Competent Planning Authority with a permissible Floor Space Index (“FSI”) allowing construction up to G + 19 floors. Thereafter, in accordance with the applicable Development Control Regulations and planning norms, we applied for revision of the sanctioned plans seeking enhancement of FSI by addition of four (4) floors. The revised plans permitting construction up to G + 23 floors were duly sanctioned by the Competent Authority in April 2024. Pursu…”

Source: AUROUS’s extension records on MahaRERA (P51700018167), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AUROUS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700018167
Status
Registered and active
Builder
ASAYA BUILDERS AND DEVELOPERS LLP
Location
Koperkhairne, Thane · 400703
Project type
Others
Registered on
11 Oct 2018
Completion date at registration
October 2024
Latest completion date
December 2026
Delay so far
26 months
Homes
71
Sold or booked
89%
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of AUROUS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AUROUS100%90%35%10%

Commencement certificate (CC), as filed on MahaRERA

  • AUROUS: covers 24 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AUROUS every month.

AUROUS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Asaya Builders AND Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 10 months late). 19 complaints on MahaRERA across 2 projects.

Read Google reviews of AUROUS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AUROUS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AUROUS

What is the possession date of AUROUS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AUROUS in Koperkhairne, Thane is 31 December 2026 — 26 months later than 30 October 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AUROUS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AUROUS's builder has filed on MahaRERA, the official one, is 31 December 2026, already 26 months later than the 30 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AUROUS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS's builder applied to MahaRERA to extend the completion date 3 times: to 29 October 2025, giving the reason "The project was delayed majorly due to the pandemic as there was immense shortage of labour for a long time. Everything is functioning smoothly and we have also received the amended plans. We expect the Occupancy Certificate shortly."; to 31 January 2026, giving the reason "We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. We are committed to completing the project efficiently and effectively, and we believe that this extension will enable us to meet all expectations without compromising on quality."; to 31 December 2026, giving the reason "The delay in completion of the Project has occurred on account of revision of the sanctioned plans. Initially, the Project was sanctioned by the Competent Planning Authority with a permissible Floor Space Index (“FSI”) allowing construction up to G + 19 floors. Thereafter, in accordance with the applicable Development Control Regulations and planning norms, we applied for revision of the sanctioned plans seeking enhancement of FSI by addition of four (4) floors. The revised plans permitting construction up to G + 23 floors were duly sanctioned by the Competent Authority in April 2024. Pursu…".

What is the RERA number of AUROUS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AUROUS in Koperkhairne, Thane is P51700018167.

Is AUROUS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS is registered as P51700018167 and its status is "Registered and active".

What is the construction status of AUROUS?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AUROUS is 90% done and internal work 35%. GharKundli's full report compares construction progress with the deadline.

Does AUROUS have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AUROUS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS is registered on MahaRERA as P51700018167, its completion date has moved 26 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AUROUS's possession date changes?

The latest dates are on AUROUS's MahaRERA page (P51700018167). GharKundli's Kundli Watch sends a free WhatsApp update on AUROUS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AUROUS have?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS has one building filed: AUROUS with 28 floors and 85 units.

How big is the land of AUROUS?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS stands on 1,657 sq m of land (about 0.4 acres), with 6,409 sq m of sanctioned built-up area and 342 sq m of recreational open space.

What is the track record of AUROUS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Asaya Builders AND Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 10 months late). 19 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AUROUS?

Google Maps has reviews of AUROUS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AUROUS?

AUROUS by ASAYA BUILDERS AND DEVELOPERS LLP is in Koperkhairne, Thane (pincode 400703), near Navi Mumbai, Kopar Khairane, Kopar Khairne, Maharashtra, and is registered on MahaRERA as P51700018167, per GharKundli's check of MahaRERA records.

How many homes are in AUROUS?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS has 71 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.

When was AUROUS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AUROUS was registered on MahaRERA on 11 October 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on AUROUS?

No court cases are listed for AUROUS on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AUROUS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ASAYA BUILDERS AND DEVELOPERS LLP.

All projects with possession due in 2026 in Thane →

Other projects in Thane

All 58 projects in Vashi (400703) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.