CYBER WORKS
by GREENSCAPE VENTURES · T.T.C Industrial Area, ThaneAlso near Sanpada
Possession date of CYBER WORKS: 30 April 2027, moved from 30 June 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700022663, and currently active. Its completion date has moved from June 2025 to April 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about CYBER WORKS?
How the possession date of CYBER WORKS has moved
30 June 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700027821)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and delays in obtaining the Occupanc…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and delays in obtaining the Occupancy Certificate (OC). Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31/12/2026 to complete the project and fulfill all regulatory requirements.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: CYBER WORKS’s extension records on MahaRERA (P51700022663), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CYBER WORKS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700022663
- Status
- Registered and active
- Builder
- GREENSCAPE VENTURES
- Location
- T.T.C Industrial Area, Thane · 400703
- Project type
- Commercial
- Registered on
- 10 Oct 2019
- Completion date at registration
- June 2025
- Latest completion date
- April 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 42%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of CYBER WORKS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CYBER WORKS | 100% | 92% | 45% | 20% |
Commencement certificate (CC), as filed on MahaRERA
- CYBER WORKS: covers 31 (Basement + Ground + 29 Upper Floors)
Latest CC order on MahaRERA: dated 29/05/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CYBER WORKS every month.
CYBER WORKS: buildings, flats and land, as filed on MahaRERA
- Buildings: CYBER WORKS (31 floors, 222 units)
- Car parking: 319 covered
- Land: 6,420 sq m (about 1.6 acres) · sanctioned built-up 28,942 sq m
- Boundaries filed include: MIDC 20M WIDE ROAD, VILLAGE ROAD
The builder’s record and reviews
Greenscape IT Park (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 3 past the promised date. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of CYBER WORKS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CYBER WORKS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CYBER WORKS
What is the possession date of CYBER WORKS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CYBER WORKS in T.T.C Industrial Area, Thane is 30 April 2027 — 18 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for CYBER WORKS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CYBER WORKS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 18 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CYBER WORKS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and delays in obtaining the Occupancy Certificate (OC). Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31/12/2026 to complete the project and fulfill all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of CYBER WORKS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CYBER WORKS in T.T.C Industrial Area, Thane is P51700022663.
Is CYBER WORKS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS is registered as P51700022663 and its status is "Registered and active".
What is the construction status of CYBER WORKS?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CYBER WORKS is 92% done and internal work 45%. GharKundli's full report compares construction progress with the deadline.
Does CYBER WORKS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is CYBER WORKS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS is registered on MahaRERA as P51700022663, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CYBER WORKS's possession date changes?
The latest dates are on CYBER WORKS's MahaRERA page (P51700022663). GharKundli's Kundli Watch sends a free WhatsApp update on CYBER WORKS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CYBER WORKS have?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS has one building filed: CYBER WORKS with 31 floors and 222 units.
How much parking does CYBER WORKS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 319 covered car parking spaces for CYBER WORKS.
How big is the land of CYBER WORKS?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS stands on 6,420 sq m of land (about 1.6 acres), with 28,942 sq m of sanctioned built-up area.
What is the track record of CYBER WORKS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Greenscape IT Park (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 3 past the promised date. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of CYBER WORKS?
Google Maps has reviews of CYBER WORKS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CYBER WORKS?
CYBER WORKS by GREENSCAPE VENTURES is in T.T.C Industrial Area, Thane (pincode 400703), near Sanpada, Maharashtra, and is registered on MahaRERA as P51700022663, per GharKundli's check of MahaRERA records. Its boundaries filed there include MIDC 20M WIDE ROAD, VILLAGE ROAD.
How many homes are in CYBER WORKS?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS has 0 homes in 1 tower registered on MahaRERA, and 42% of them are sold or booked.
When was CYBER WORKS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CYBER WORKS was registered on MahaRERA on 10 October 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on CYBER WORKS?
No court cases are listed for CYBER WORKS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of CYBER WORKS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GREENSCAPE VENTURES.
Check it yourself on MahaRERA
- How to check the possession date of CYBER WORKS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 400703
- ORCHID ARCADE
- AUROUS
- Godrej Bayview
- Gami Ayur
- SHUBHAM ARTESIA
- Kamdhenu Synergy Square
- KAMDHENU SHARAYU
- Satyam Veloura
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.