AVAJ RESIDENCY

by AVAJ BUILDERS AND DEVELOPERS PRIVATE LIMITED · Kalamboli, Raigarh

Possession: AVAJ RESIDENCY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000012402. Status: Completed. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about AVAJ RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AVAJ RESIDENCY has moved

  1. 30 June 2018

    Completion date given when the project was registered

  2. 30 June 2019

    Extended at the builder's request (MahaRERA application EXT52000000054)

    Reason the builder gave MahaRERA: “Sanctioning Authority changed from Deputy Collector Alibaug to NAINA (CIDCO) / Grampanchayat Vichumbe. Project Delayed due to Non- Payment from Group of Purchasers.”
  3. 30 June 2019

    Extended at the builder's request (MahaRERA application EXT52000000713)

    Reason the builder gave MahaRERA: “Final touchup work for A,B,C wing only & balance of Infra / Garden & Mandir etc. also procure , OC / CC from Concerned Authority.”

Source: AVAJ RESIDENCY’s extension records on MahaRERA (P52000012402), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AVAJ RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the June 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000012402
Status
Completed
Builder
AVAJ BUILDERS AND DEVELOPERS PRIVATE LIMITED
Location
Kalamboli, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
June 2018
Latest completion date
June 2019
Delay so far
12 months
Homes
126
Towers
2
Complaints on MahaRERA
5
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of AVAJ RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AVAJ RESIDENCY 01100%100%100%0%
AVAJ RESIDENCY 02100%100%100%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AVAJ RESIDENCY every month.

AVAJ RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: AVAJ RESIDENCY 01 (3 floors) · AVAJ RESIDENCY 02 (3 floors)
  • Land: 6,730 sq m (about 1.7 acres)

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AVAJ RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AVAJ RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AVAJ RESIDENCY

What is the possession date of AVAJ RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for AVAJ RESIDENCY in Kalamboli, Raigarh is 30 June 2019 — 12 months later than 30 June 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AVAJ RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AVAJ RESIDENCY's builder has filed on MahaRERA, the official one, is 30 June 2019, already 12 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AVAJ RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2019, giving the reason "Sanctioning Authority changed from Deputy Collector Alibaug to NAINA (CIDCO) / Grampanchayat Vichumbe. Project Delayed due to Non- Payment from Group of Purchasers."; to 30 June 2019, giving the reason "Final touchup work for A,B,C wing only & balance of Infra / Garden & Mandir etc. also procure , OC / CC from Concerned Authority.".

What is the RERA number of AVAJ RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of AVAJ RESIDENCY in Kalamboli, Raigarh is P52000012402.

Is AVAJ RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY is registered as P52000012402 and its status is "Completed".

What is the construction status of AVAJ RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does AVAJ RESIDENCY have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AVAJ RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY is registered on MahaRERA as P52000012402, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AVAJ RESIDENCY's possession date changes?

The latest dates are on AVAJ RESIDENCY's MahaRERA page (P52000012402). GharKundli's Kundli Watch sends a free WhatsApp update on AVAJ RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AVAJ RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY has 2 buildings filed: AVAJ RESIDENCY 01 with 3 floors; AVAJ RESIDENCY 02 with 3 floors.

How big is the land of AVAJ RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY stands on 6,730 sq m of land (about 1.7 acres).

Where can I read reviews of AVAJ RESIDENCY?

Google Maps has reviews of AVAJ RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AVAJ RESIDENCY?

AVAJ RESIDENCY by AVAJ BUILDERS AND DEVELOPERS PRIVATE LIMITED is in Kalamboli, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000012402, per GharKundli's check of MahaRERA records.

How many homes are in AVAJ RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY has 126 homes in 2 towers registered on MahaRERA.

When was AVAJ RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), AVAJ RESIDENCY was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AVAJ RESIDENCY?

No court cases are listed for AVAJ RESIDENCY on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AVAJ RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AVAJ BUILDERS AND DEVELOPERS PRIVATE LIMITED.