EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3

by Xrbia Developers Ltd · Madap, Raigarh

Possession date of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3: 30 December 2021, moved from 31 December 2019 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000007610. Status: Lapsed (registration period ended). 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT52000005056)

    Reason the builder gave MahaRERA: “As per Attached Application for Extension”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3’s extension records on MahaRERA (P52000007610), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000007610
Status
Lapsed (registration period ended)
Builder
Xrbia Developers Ltd
Location
Madap, Raigarh · 410203
Project type
Others
Registered on
17 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
102
Towers
102
Complaints on MahaRERA
7
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
R-0010%0%0%0%
R-0020%0%0%0%
R-0030%0%0%0%
R-0050%0%0%0%
R-0080%0%0%0%
R-0100%0%0%0%
R-0110%0%0%0%
R-0120%0%0%0%
R-0240%0%0%0%
R-0270%0%0%0%
R-0280%0%0%0%
R-0300%0%0%0%
R-0390%0%0%0%
R-0470%0%0%0%
R-0540%0%0%0%
R-0570%0%0%0%
R-0580%0%0%0%
R-0620%0%0%0%
R-004100%13%0%0%
R-007100%100%100%0%
R-009100%33%0%0%
R-013100%100%60%0%
R-014100%100%53%0%
R-015100%100%47%0%
R-016100%100%47%0%
R-019100%100%60%0%
R-022100%100%27%0%
R-023100%100%40%0%
R-025100%100%53%0%
R-026100%100%53%0%

Showing 30 of 102 towers.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 every month.

EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3: buildings, flats and land, as filed on MahaRERA

  • Buildings: R-004 (3 floors) · R-007 (3 floors) · R-009 (3 floors) · R-013 (3 floors) · R-014 (3 floors) · R-015 (3 floors) · R-016 (3 floors) · R-019 (3 floors) · and 22 more
  • Land: 10,332 sq m (about 2.6 acres) · sanctioned built-up 15,183 sq m · recreational space 11,084 sq m

The builder’s record and reviews

Xrbia Developers has 10 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 lapsed. 26 complaints on MahaRERA across 4 projects.

Read Google reviews of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3

What is the possession date of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 in Madap, Raigarh is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "As per Attached Application for Extension".

What is the RERA number of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 in Madap, Raigarh is P52000007610.

Is EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 is registered as P52000007610 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 is registered on MahaRERA as P52000007610, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration, 7 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1 (P52000007138, possession 30 Mar 2023); EXPRESS CITY /KHOPOLI WOODS/NEW LONAVALA - PH 2 (P52000011789, possession 30 Mar 2023); EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA - PH -4 (P52000008195, possession 30 Mar 2023). Check that your agreement names the registration of your own wing.

How can I get updates if EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3's possession date changes?

The latest dates are on EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3's MahaRERA page (P52000007610). GharKundli's Kundli Watch sends a free WhatsApp update on EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 has 30 buildings filed: R-004 with 3 floors; R-007 with 3 floors; R-009 with 3 floors; R-013 with 3 floors; R-014 with 3 floors; R-015 with 3 floors; and 24 more.

How big is the land of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 stands on 10,332 sq m of land (about 2.6 acres), with 15,183 sq m of sanctioned built-up area and 11,084 sq m of recreational open space.

What is the track record of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Developers has 10 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 lapsed. 26 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

Google Maps has reviews of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 by Xrbia Developers Ltd is in Madap, Raigarh (pincode 410203), Maharashtra, and is registered on MahaRERA as P52000007610, per GharKundli's check of MahaRERA records.

How many homes are in EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 has 102 homes in 102 towers registered on MahaRERA.

When was EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

No court cases are listed for EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Xrbia Developers Ltd, which has 9 other projects registered on MahaRERA.

Other projects in Khalapur

All 211 projects in Shilphata (410203) →

Other projects by Xrbia Developers Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.