TARUN PLANTATIONS COMPANY
by TARUN PLANTATIONS COMPANY · Pen, Raigarh
Possession date of TARUN PLANTATIONS COMPANY: 31 July 2027, moved from 30 March 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000014149, and currently active. Its completion date has moved from March 2022 to July 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about TARUN PLANTATIONS COMPANY?
How the possession date of TARUN PLANTATIONS COMPANY has moved
30 March 2022
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA22052621062)
Reason the builder gave MahaRERA:
“1. The project stands at 80% completion. 2. The consent of 82.76% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The…” Read the full reason
“1. The project stands at 80% completion. 2. The consent of 82.76% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- a. Unfavourable Market Conditions b. Financial Constraints c. Shortage of Skilled Labour and Construction Materials d. Increased Construction Cost e. Unfavourable Weather Conditions 6. The revised date of completion is now 31/03/2027. 7. We hereby assure the Hon’ble Authority that the project shall be fully c…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: TARUN PLANTATIONS COMPANY’s extension records on MahaRERA (P52000014149), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on TARUN PLANTATIONS COMPANY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000014149
- Status
- Registered and active
- Builder
- TARUN PLANTATIONS COMPANY
- Location
- Pen, Raigarh · 402107
- Project type
- Plotted
- Registered on
- 9 Nov 2017
- Completion date at registration
- March 2022
- Latest completion date
- July 2027
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
TARUN PLANTATIONS COMPANY: buildings, flats and land, as filed on MahaRERA
- Land: 93,284 sq m (about 23.1 acres) · recreational space 35,885 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of TARUN PLANTATIONS COMPANY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TARUN PLANTATIONS COMPANY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TARUN PLANTATIONS COMPANY
What is the possession date of TARUN PLANTATIONS COMPANY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TARUN PLANTATIONS COMPANY in Pen, Raigarh is 31 July 2027 — 60 months later than 30 March 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for TARUN PLANTATIONS COMPANY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TARUN PLANTATIONS COMPANY's builder has filed on MahaRERA, the official one, is 31 July 2027, already 60 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of TARUN PLANTATIONS COMPANY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), TARUN PLANTATIONS COMPANY's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "1. The project stands at 80% completion. 2. The consent of 82.76% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- a. Unfavourable Market Conditions b. Financial Constraints c. Shortage of Skilled Labour and Construction Materials d. Increased Construction Cost e. Unfavourable Weather Conditions 6. The revised date of completion is now 31/03/2027. 7. We hereby assure the Hon’ble Authority that the project shall be fully c…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of TARUN PLANTATIONS COMPANY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TARUN PLANTATIONS COMPANY in Pen, Raigarh is P52000014149.
Is TARUN PLANTATIONS COMPANY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TARUN PLANTATIONS COMPANY is registered as P52000014149 and its status is "Registered and active".
What is the construction status of TARUN PLANTATIONS COMPANY?
According to GharKundli's check of MahaRERA records (updated October 2026), TARUN PLANTATIONS COMPANY's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does TARUN PLANTATIONS COMPANY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is TARUN PLANTATIONS COMPANY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), TARUN PLANTATIONS COMPANY is registered on MahaRERA as P52000014149, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TARUN PLANTATIONS COMPANY's possession date changes?
The latest dates are on TARUN PLANTATIONS COMPANY's MahaRERA page (P52000014149). GharKundli's Kundli Watch sends a free WhatsApp update on TARUN PLANTATIONS COMPANY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of TARUN PLANTATIONS COMPANY?
According to GharKundli's check of MahaRERA records (updated October 2026), TARUN PLANTATIONS COMPANY stands on 93,284 sq m of land (about 23.1 acres) and 35,885 sq m of recreational open space.
Where can I read reviews of TARUN PLANTATIONS COMPANY?
Google Maps has reviews of TARUN PLANTATIONS COMPANY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TARUN PLANTATIONS COMPANY?
TARUN PLANTATIONS COMPANY by TARUN PLANTATIONS COMPANY is in Pen, Raigarh (pincode 402107), Maharashtra, and is registered on MahaRERA as P52000014149, per GharKundli's check of MahaRERA records.
When was TARUN PLANTATIONS COMPANY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TARUN PLANTATIONS COMPANY was registered on MahaRERA on 9 November 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on TARUN PLANTATIONS COMPANY?
No court cases are listed for TARUN PLANTATIONS COMPANY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of TARUN PLANTATIONS COMPANY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TARUN PLANTATIONS COMPANY.
Check it yourself on MahaRERA
- How to check the possession date of TARUN PLANTATIONS COMPANY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 402107
- Wing B Shivam Prajapati Complex
- Nakshatra Heights
- SHREE VASANTI RESIDENCY
- PENDSE PARK
- GURUDARSHAN PRIDE
- YUVARNA RESIDENCY
- HAWARE GRANDE
- SHREE SAMARTH KRUPA APARTMENT
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.