SIDDHAGIRI RESIDENCY

by SS ENGINEERING · Panvel, Raigarh

Possession date of SIDDHAGIRI RESIDENCY: 31 December 2024, moved from 1 November 2020 (49 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000014294. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about SIDDHAGIRI RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SIDDHAGIRI RESIDENCY has moved

  1. 1 November 2020

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52000012682)

    Reason the builder gave MahaRERA: “covid-19”

Source: SIDDHAGIRI RESIDENCY’s extension records on MahaRERA (P52000014294), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SIDDHAGIRI RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000014294
Status
Lapsed (registration period ended)
Builder
SS ENGINEERING
Location
Panvel, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
20 Nov 2017
Completion date at registration
November 2020
Latest completion date
December 2024
Delay so far
49 months
Homes
17
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of SIDDHAGIRI RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SIDDHAGIRI RESIDENCY100%100%100%60%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIDDHAGIRI RESIDENCY every month.

SIDDHAGIRI RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: SIDDHAGIRI RESIDENCY (5 floors)
  • Land: 299 sq m (about 0.1 acres) · sanctioned built-up 445 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SIDDHAGIRI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SIDDHAGIRI RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SIDDHAGIRI RESIDENCY

What is the possession date of SIDDHAGIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SIDDHAGIRI RESIDENCY in Panvel, Raigarh is 31 December 2024 — 49 months later than 1 November 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SIDDHAGIRI RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SIDDHAGIRI RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2024, already 49 months later than the 1 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SIDDHAGIRI RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 December 2024, giving the reason "covid-19".

What is the RERA number of SIDDHAGIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SIDDHAGIRI RESIDENCY in Panvel, Raigarh is P52000014294.

Is SIDDHAGIRI RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY is registered as P52000014294 and its status is "Lapsed (registration period ended)".

What is the construction status of SIDDHAGIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SIDDHAGIRI RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SIDDHAGIRI RESIDENCY have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SIDDHAGIRI RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY is registered on MahaRERA as P52000014294, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 49 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SIDDHAGIRI RESIDENCY's possession date changes?

The latest dates are on SIDDHAGIRI RESIDENCY's MahaRERA page (P52000014294). GharKundli's Kundli Watch sends a free WhatsApp update on SIDDHAGIRI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SIDDHAGIRI RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY has one building filed: SIDDHAGIRI RESIDENCY with 5 floors.

How big is the land of SIDDHAGIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY stands on 299 sq m of land (about 0.1 acres), with 445 sq m of sanctioned built-up area.

Where can I read reviews of SIDDHAGIRI RESIDENCY?

Google Maps has reviews of SIDDHAGIRI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SIDDHAGIRI RESIDENCY?

SIDDHAGIRI RESIDENCY by SS ENGINEERING is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000014294, per GharKundli's check of MahaRERA records.

How many homes are in SIDDHAGIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY has 17 homes in 1 tower registered on MahaRERA.

When was SIDDHAGIRI RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHAGIRI RESIDENCY was registered on MahaRERA on 20 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SIDDHAGIRI RESIDENCY?

No court cases are listed for SIDDHAGIRI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SIDDHAGIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SS ENGINEERING.