by CHANDRAKANT ANANT MHATRE · Dronagiri, Raigarh

Possession date of SHREE KRUPA CHAHU PRIDE: 30 December 2022, moved from 31 December 2019 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000014847. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2022) has passed.

What do you want to know about SHREE KRUPA CHAHU PRIDE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE KRUPA CHAHU PRIDE has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT52000006133)

    Reason the builder gave MahaRERA: “I REQUEST YOU TO PLEASE EXTEND OUR COMPLETION DATE TO 31ST DEC 2020”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52000009460)

    Reason the builder gave MahaRERA: “Due to Covid 19 pandemic we need to extend our project. we have take the customer approval.”
  4. 30 December 2022

    Revised completion date on MahaRERA

Source: SHREE KRUPA CHAHU PRIDE’s extension records on MahaRERA (P52000014847), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE KRUPA CHAHU PRIDE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000014847
Status
Lapsed (registration period ended)
Builder
CHANDRAKANT ANANT MHATRE
Location
Dronagiri, Raigarh · 400702
Project type
Mixed
Registered on
8 Jan 2018
Completion date at registration
December 2019
Latest completion date
December 2022
Delay so far
36 months
Homes
18
Towers
1
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SHREE KRUPA CHAHU PRIDE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE KRUPA CHAHU PRIDE100%100%100%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE KRUPA CHAHU PRIDE every month.

SHREE KRUPA CHAHU PRIDE: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE KRUPA CHAHU PRIDE (5 floors)
  • Land: 250 sq m (about 0.1 acres) · sanctioned built-up 375 sq m

The builder’s record and reviews

Chandrakant Ananta Mhatre has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 lapsed. 3 complaints on MahaRERA across 1 project.

Read Google reviews of SHREE KRUPA CHAHU PRIDE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE KRUPA CHAHU PRIDE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE KRUPA CHAHU PRIDE

What is the possession date of SHREE KRUPA CHAHU PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREE KRUPA CHAHU PRIDE in Dronagiri, Raigarh is 30 December 2022 — 36 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHREE KRUPA CHAHU PRIDE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE KRUPA CHAHU PRIDE's builder has filed on MahaRERA, the official one, is 30 December 2022, already 36 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE KRUPA CHAHU PRIDE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "I REQUEST YOU TO PLEASE EXTEND OUR COMPLETION DATE TO 31ST DEC 2020"; to 30 June 2022, giving the reason "Due to Covid 19 pandemic we need to extend our project. we have take the customer approval.".

What is the RERA number of SHREE KRUPA CHAHU PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREE KRUPA CHAHU PRIDE in Dronagiri, Raigarh is P52000014847.

Is SHREE KRUPA CHAHU PRIDE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE is registered as P52000014847 and its status is "Lapsed (registration period ended)".

What is the construction status of SHREE KRUPA CHAHU PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE KRUPA CHAHU PRIDE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHREE KRUPA CHAHU PRIDE have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHREE KRUPA CHAHU PRIDE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE is registered on MahaRERA as P52000014847, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE KRUPA CHAHU PRIDE's possession date changes?

The latest dates are on SHREE KRUPA CHAHU PRIDE's MahaRERA page (P52000014847). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE KRUPA CHAHU PRIDE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE KRUPA CHAHU PRIDE have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE has one building filed: SHREE KRUPA CHAHU PRIDE with 5 floors.

How big is the land of SHREE KRUPA CHAHU PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE stands on 250 sq m of land (about 0.1 acres), with 375 sq m of sanctioned built-up area.

What is the track record of SHREE KRUPA CHAHU PRIDE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Chandrakant Ananta Mhatre has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 lapsed. 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHREE KRUPA CHAHU PRIDE?

Google Maps has reviews of SHREE KRUPA CHAHU PRIDE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE KRUPA CHAHU PRIDE?

SHREE KRUPA CHAHU PRIDE by CHANDRAKANT ANANT MHATRE is in Dronagiri, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000014847, per GharKundli's check of MahaRERA records.

How many homes are in SHREE KRUPA CHAHU PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE has 18 homes in 1 tower registered on MahaRERA.

When was SHREE KRUPA CHAHU PRIDE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRUPA CHAHU PRIDE was registered on MahaRERA on 8 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE KRUPA CHAHU PRIDE?

No court cases are listed for SHREE KRUPA CHAHU PRIDE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHREE KRUPA CHAHU PRIDE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is CHANDRAKANT ANANT MHATRE, which has 1 other project registered on MahaRERA.