Adhiraj Samyama Tower 1C
by Adhiraj Constructions Private Limited · Taloja A.V., RaigarhAlso near Rohinjan, Kharghar
Possession date of Adhiraj Samyama Tower 1C: 31 July 2027, moved from 31 July 2023 (44 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000014859, and currently active. Its completion date has moved from July 2023 to July 2027: 44 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Adhiraj Samyama Tower 1C?
GharKundli’s full report on Adhiraj Samyama Tower 1C
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints and 5 court cases, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Adhiraj Samyama Tower 1AP52000004449 · possession 30 Jun 2025
- Adhiraj Samyama Tower 1BP52000004493 · possession 30 Jun 2025
- Adhiraj Samyama Tower 1DP52000014856 · possession 31 Jul 2027
- Adhiraj Samyama Tower 2AP52000007539 · possession 10 Nov 2023
- Adhiraj Samyama Tower 2BP52000003039 · possession 10 Nov 2023
- Adhiraj Samyama Tower 3BP52000004189 · possession 30 Jun 2025
- MahaRERA registration
- P52000014859
- Status
- Registered and active
- Builder
- Adhiraj Constructions Private Limited
- Location
- Taloja A.V., Raigarh · 410208
- Project type
- Residential / Group Housing
- Registered on
- 8 Jan 2018
- Completion date at registration
- July 2023
- Latest completion date
- July 2027
- Delay so far
- 44 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 262
- Sold or booked
- 87%
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 5
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of Adhiraj Samyama Tower 1C, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 1C | 100% | 22% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 1C: covers Basement 2 + Basement 1+LG+UG+P1+P2+RG/1 to45 floors including 1 Fire check floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Adhiraj Samyama Tower 1C every month.
Adhiraj Samyama Tower 1C: buildings, flats and land, as filed on MahaRERA
- Buildings: 1C (46 floors, 262 units)
- Land: 1,267 sq m (about 0.3 acres) · sanctioned built-up 16,789 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Adhiraj Constructions has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 16 months); 3 still being built, 2 past the promised date (typically 23 months late); 5 lapsed. 110 complaints on MahaRERA across 10 projects.
Read Google reviews of Adhiraj Samyama Tower 1C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Adhiraj Samyama Tower 1C: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Adhiraj Samyama Tower 1C
What is the possession date of Adhiraj Samyama Tower 1C?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Adhiraj Samyama Tower 1C in Taloja A.V., Raigarh is 31 July 2027 — 44 months later than 31 July 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Adhiraj Samyama Tower 1C?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Adhiraj Samyama Tower 1C's builder has filed on MahaRERA, the official one, is 31 July 2027, already 44 months later than the 31 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Adhiraj Samyama Tower 1C?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Adhiraj Samyama Tower 1C in Taloja A.V., Raigarh is P52000014859.
Is Adhiraj Samyama Tower 1C registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Samyama Tower 1C is registered as P52000014859 and its status is "Registered and active".
What is the construction status of Adhiraj Samyama Tower 1C?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Samyama Tower 1C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 1C is 22% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Adhiraj Samyama Tower 1C have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Adhiraj Samyama Tower 1C safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Samyama Tower 1C is registered on MahaRERA as P52000014859, its completion date has moved 44 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Adhiraj Samyama Tower 1C have other wings or phases?
Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: Adhiraj Samyama Tower 1A (P52000004449, possession 30 Jun 2025); Adhiraj Samyama Tower 1B (P52000004493, possession 30 Jun 2025); Adhiraj Samyama Tower 1D (P52000014856, possession 31 Jul 2027); Adhiraj Samyama Tower 2A (P52000007539, possession 10 Nov 2023); Adhiraj Samyama Tower 2B (P52000003039, possession 10 Nov 2023); Adhiraj Samyama Tower 3B (P52000004189, possession 30 Jun 2025). Check that your agreement names the registration of your own wing.
How can I get updates if Adhiraj Samyama Tower 1C's possession date changes?
The latest dates are on Adhiraj Samyama Tower 1C's MahaRERA page (P52000014859). GharKundli's Kundli Watch sends a free WhatsApp update on Adhiraj Samyama Tower 1C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Adhiraj Samyama Tower 1C have?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Samyama Tower 1C has one building filed: 1C with 46 floors and 262 units.
How big is the land of Adhiraj Samyama Tower 1C?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Samyama Tower 1C stands on 1,267 sq m of land (about 0.3 acres), with 16,789 sq m of sanctioned built-up area.
What is the track record of Adhiraj Samyama Tower 1C's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Constructions has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 16 months); 3 still being built, 2 past the promised date (typically 23 months late); 5 lapsed. 110 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Adhiraj Samyama Tower 1C?
Google Maps has reviews of Adhiraj Samyama Tower 1C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Adhiraj Samyama Tower 1C?
Adhiraj Samyama Tower 1C by Adhiraj Constructions Private Limited is in Taloja A.V., Raigarh (pincode 410208), near Rohinjan, Kharghar, Maharashtra, and is registered on MahaRERA as P52000014859, per GharKundli's check of MahaRERA records.
How many homes are in Adhiraj Samyama Tower 1C?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Samyama Tower 1C has 262 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.
When was Adhiraj Samyama Tower 1C registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Adhiraj Samyama Tower 1C was registered on MahaRERA on 8 January 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Adhiraj Samyama Tower 1C?
5 court cases are listed for Adhiraj Samyama Tower 1C on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Adhiraj Samyama Tower 1C?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Adhiraj Constructions Private Limited, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Adhiraj Samyama Tower 1C
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 410208
- Konnark Meadows
- Vrundavan
- K K RESIDENCY
- Rudra Rajendra
- ARKAN CASTLE
- NANASETH RESIDENCY
- Saksham Heights
- GREEN LEAF
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.