Sparsh Phase-II

by Shree Enterprises · Shedung, Raigarh

Possession date of Sparsh Phase-II: 31 December 2025, moved from 30 March 2022 (45 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000016230. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Sparsh Phase-II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sparsh Phase-II has moved

  1. 30 March 2022

    Completion date given when the project was registered

  2. 30 March 2023

    Extended at the builder's request (MahaRERA application EXT52000011545)

    Reason the builder gave MahaRERA:
    “That there was delay in approval of UDCPR governing the development of Real Estate projects within the Maharashtra State except the Municipal Corporation of Greater Mumbai issued by Government of Maharashtra due to ongoing pandemic situatio…” Read the full reason“That there was delay in approval of UDCPR governing the development of Real Estate projects within the Maharashtra State except the Municipal Corporation of Greater Mumbai issued by Government of Maharashtra due to ongoing pandemic situation. That there is resultant delay in revised approvals for Proposed but not sanctioned area and therefore the construction work could not be carried out for the additional area declared at the time of registration. That the revised approvals are in process and shall be issued soon. The construction work of building shall be completed accordingly after gett…”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52000015051)

    Reason the builder gave MahaRERA:
    “Dear Sir, That there is delay in getting revised approvals for “Proposed but not sanctioned area” from the Planning Authority on the account of changes in Regulations governing the development of real estate of projects. The Planning Author…” Read the full reason“Dear Sir, That there is delay in getting revised approvals for “Proposed but not sanctioned area” from the Planning Authority on the account of changes in Regulations governing the development of real estate of projects. The Planning Authority took some time to implement the Unified DCPR 2034 and therefore the construction work could not be carried out for the additional area declared at the time of registration. We have completed the construction work of the structure and envelope as well as majority of the finishing work for the building. Photographs showing the completed building and wor…”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52000019819)

    Reason the builder gave MahaRERA:
    “Respected Sir, The structure of the buildings along with the Brickwork and plaster is completed. The internal finishes including gypsum, Floor tiles and Dado, Kitchen Platform and doors have been installed. Currently, the work of electrical…” Read the full reason“Respected Sir, The structure of the buildings along with the Brickwork and plaster is completed. The internal finishes including gypsum, Floor tiles and Dado, Kitchen Platform and doors have been installed. Currently, the work of electrical and plumbing fittings is going on. The external paint work will be started soon. We expect to finish the balance work by 15th November and obtain Occupation Certificate by December end. Accordingly, we are requesting this Hon’ble Authority to allow extension of project registration till 31st December 2024. Thanking you. Yours faithfully, For Shree Enterp…”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52000027378)

    Reason the builder gave MahaRERA: “Required Project extension for project completion purpose.”

Source: Sparsh Phase-II’s extension records on MahaRERA (P52000016230), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sparsh Phase-II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000016230
Status
Lapsed (registration period ended)
Builder
Shree Enterprises
Location
Shedung, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
25 Apr 2018
Completion date at registration
March 2022
Latest completion date
December 2025
Delay so far
45 months
Homes
158
Sold or booked
92%
Towers
5
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
23

Construction progress of Sparsh Phase-II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building no 4100%100%100%90%
Building no 5 Wing A100%100%100%90%
Building no 5 Wing B100%100%100%90%
Building no 6 Wing A100%100%100%90%
Building no 6 Wing B100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • Building no 4: covers 8 floors
  • Building no 5 Wing A: covers 8 floors
  • Building no 5 Wing B: covers 8 floors
  • Building no 6 Wing A: covers 8 floors
  • Building no 6 Wing B: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sparsh Phase-II every month.

Sparsh Phase-II: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building no 4 (8 floors, 46 units) · Building no 5 Wing A (8 floors, 28 units) · Building no 5 Wing B (8 floors, 28 units) · Building no 6 Wing A (8 floors, 28 units) · Building no 6 Wing B (8 floors, 28 units)
  • Car parking: 21 covered
  • Land: 1,322 sq m (about 0.3 acres) · sanctioned built-up 2,794 sq m

The builder’s record and reviews

Shree Enterprises has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Sparsh Phase-II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sparsh Phase-II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sparsh Phase-II

What is the possession date of Sparsh Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sparsh Phase-II in Shedung, Raigarh is 31 December 2025 — 45 months later than 30 March 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sparsh Phase-II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sparsh Phase-II's builder has filed on MahaRERA, the official one, is 31 December 2025, already 45 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sparsh Phase-II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II's builder applied to MahaRERA to extend the completion date 4 times: to 30 March 2023, giving the reason "That there was delay in approval of UDCPR governing the development of Real Estate projects within the Maharashtra State except the Municipal Corporation of Greater Mumbai issued by Government of Maharashtra due to ongoing pandemic situation. That there is resultant delay in revised approvals for Proposed but not sanctioned area and therefore the construction work could not be carried out for the additional area declared at the time of registration. That the revised approvals are in process and shall be issued soon. The construction work of building shall be completed accordingly after gett…"; to 31 March 2024, giving the reason "Dear Sir, That there is delay in getting revised approvals for “Proposed but not sanctioned area” from the Planning Authority on the account of changes in Regulations governing the development of real estate of projects. The Planning Authority took some time to implement the Unified DCPR 2034 and therefore the construction work could not be carried out for the additional area declared at the time of registration. We have completed the construction work of the structure and envelope as well as majority of the finishing work for the building. Photographs showing the completed building and wor…"; to 31 December 2024, giving the reason "Respected Sir, The structure of the buildings along with the Brickwork and plaster is completed. The internal finishes including gypsum, Floor tiles and Dado, Kitchen Platform and doors have been installed. Currently, the work of electrical and plumbing fittings is going on. The external paint work will be started soon. We expect to finish the balance work by 15th November and obtain Occupation Certificate by December end. Accordingly, we are requesting this Hon’ble Authority to allow extension of project registration till 31st December 2024. Thanking you. Yours faithfully, For Shree Enterp…"; to 31 December 2025, giving the reason "Required Project extension for project completion purpose.".

What is the RERA number of Sparsh Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sparsh Phase-II in Shedung, Raigarh is P52000016230.

Is Sparsh Phase-II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II is registered as P52000016230 and its status is "Lapsed (registration period ended)".

What is the construction status of Sparsh Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Sparsh Phase-II have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sparsh Phase-II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II is registered on MahaRERA as P52000016230, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 45 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Sparsh Phase-II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Sparsh Phase-III (P52000027334, possession 30 Jun 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Sparsh Phase-II's possession date changes?

The latest dates are on Sparsh Phase-II's MahaRERA page (P52000016230). GharKundli's Kundli Watch sends a free WhatsApp update on Sparsh Phase-II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sparsh Phase-II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II has 5 buildings filed: Building no 4 with 8 floors and 46 units; Building no 5 Wing A with 8 floors and 28 units; Building no 5 Wing B with 8 floors and 28 units; Building no 6 Wing A with 8 floors and 28 units; Building no 6 Wing B with 8 floors and 28 units.

How much parking does Sparsh Phase-II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 21 covered car parking spaces for Sparsh Phase-II.

How big is the land of Sparsh Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II stands on 1,322 sq m of land (about 0.3 acres), with 2,794 sq m of sanctioned built-up area.

What is the track record of Sparsh Phase-II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Enterprises has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sparsh Phase-II?

Google Maps has reviews of Sparsh Phase-II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sparsh Phase-II?

Sparsh Phase-II by Shree Enterprises is in Shedung, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000016230, per GharKundli's check of MahaRERA records.

How many homes are in Sparsh Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II has 158 homes in 5 towers registered on MahaRERA, and 92% of them are sold or booked.

When was Sparsh Phase-II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Phase-II was registered on MahaRERA on 25 April 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Sparsh Phase-II?

No court cases are listed for Sparsh Phase-II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Sparsh Phase-II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Enterprises, which has 23 other projects registered on MahaRERA.

Other projects in Shedung

All 2,664 projects in Panvel (410206) →

Other projects by Shree Enterprises

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.