Sparsh Aster
by Shree Enterprises · Kasar Amboli, Pune 412108Also near Paud
What’s in the report? →Possession date of Sparsh Aster (MahaRERA P52100035183): 30 April 2027, moved from 31 December 2025 (12 months later). It has 176 homes, 38% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100035183, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100035183, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sparsh Aster?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sparsh Aster has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA29042620774)
Reason the builder gave MahaRERA:
“Construction of Plinth, Stilt and lower floors is completed. Work on upper floors along with finishes and external services is in progress. We are hopeful of completing the work as per timeline estimated in the CPM Report. We Request this H…” Read the full reason
“Construction of Plinth, Stilt and lower floors is completed. Work on upper floors along with finishes and external services is in progress. We are hopeful of completing the work as per timeline estimated in the CPM Report. We Request this Hon'ble Authority to approve extension of project registration. Thank you”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sparsh Aster’s extension records on MahaRERA (P52100035183), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sparsh Aster
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100035183
- Status
- Registered and active
- Builder
- Shree Enterprises
- Location
- Kasar Amboli, Pune · 412108
- Project type
- Residential / Group Housing
- Registered on
- 10 May 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 176
- Sold or booked
- 38%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 23
Construction progress of Sparsh Aster, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building A Wing A | 100% | 95% | 90% | 0% |
| Building A Wing B | 100% | 100% | 95% | 0% |
| Building A Wing C | 100% | 95% | 90% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building A Wing A: covers 11 floors
- Building A Wing B: covers 8 floors
- Building A Wing C: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sparsh Aster every 1–2 months.
Sparsh Aster: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A Wing A (11 floors, 60 units) · Building A Wing B (8 floors, 56 units) · Building A Wing C (11 floors, 60 units)
- Land: 3,095 sq m (about 0.8 acres) · sanctioned built-up 3,791 sq m
- Boundaries filed include: Pune Poud Road
- Land, as filed: 354, 360, 370
- Map: Get directions
The builder’s record and reviews
Shree Enterprises has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 2 past the promised date (typically 42 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Sparsh Aster →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sparsh Aster: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sparsh Aster
What is the possession date of Sparsh Aster?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sparsh Aster in Kasar Amboli, Pune is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sparsh Aster?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sparsh Aster's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sparsh Aster extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Construction of Plinth, Stilt and lower floors is completed. Work on upper floors along with finishes and external services is in progress. We are hopeful of completing the work as per timeline estimated in the CPM Report. We Request this Hon'ble Authority to approve extension of project registration. Thank you". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sparsh Aster?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sparsh Aster in Kasar Amboli, Pune is P52100035183.
Is Sparsh Aster registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster is registered as P52100035183 and its status is "Registered and active".
What is the current construction status of Sparsh Aster? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 95% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Sparsh Aster have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sparsh Aster safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster is registered on MahaRERA as P52100035183, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sparsh Aster?
Sparsh Aster is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sparsh Aster?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sparsh Aster: gharkundli.com/tools/property-cost-calculator
Has Sparsh Aster received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sparsh Aster uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sparsh Aster was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sparsh Aster's possession date changes?
The latest dates are on Sparsh Aster's MahaRERA page (P52100035183). GharKundli's Kundli Watch sends a free WhatsApp update on Sparsh Aster every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sparsh Aster have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster has 3 buildings filed: Building A Wing A with 11 floors and 60 units; Building A Wing B with 8 floors and 56 units; Building A Wing C with 11 floors and 60 units.
How big is the land of Sparsh Aster?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster stands on 3,095 sq m of land (about 0.8 acres), with 3,791 sq m of sanctioned built-up area.
What is the track record of Sparsh Aster's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Enterprises has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 2 past the promised date (typically 42 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sparsh Aster?
Google Maps has reviews of Sparsh Aster written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sparsh Aster?
Sparsh Aster by Shree Enterprises is in Kasar Amboli, Pune, pincode 412108 (near Paud), Maharashtra, and is registered on MahaRERA as P52100035183, per GharKundli's check of MahaRERA records. Its boundaries filed there include Pune Poud Road. Its land is filed as 354, 360, 370. GharKundli lists all 73 MahaRERA projects in Paud (412108).
How many flats are in Sparsh Aster, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster has 176 homes in 3 towers registered on MahaRERA, and 38% of them are sold or booked.
When was Sparsh Aster registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sparsh Aster was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.
Does Sparsh Aster have any legal issues or court cases?
No court cases are listed for Sparsh Aster on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sparsh Aster?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Enterprises, which has 23 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sparsh Aster
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Paud (412108)
- Aryan Brentwood
- Foresta Phase I
- Satvam Hills C4
- Satvam Hills B7
- Satvam Hills C5
- Satvam Hills A5
- Satvam Hills A6
- Apex Ambar
Other projects by Shree Enterprises
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.