AVANTE
by SWARAJ MEGA STRUCTURE PRIVATE LIMITED · Panvel, Raigarh
Possession date of AVANTE: 31 December 2025, moved from 31 December 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000016411. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about AVANTE?
How the possession date of AVANTE has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT52000001516)
Reason the builder gave MahaRERA: “DUE TO DEATH OF ONE KEY DIRECTOR, PROJECT EXTENSION APPLICATION HAS BEEN DONE.”
31 December 2022
Extended at the builder's request (MahaRERA application EXT52000009875)
Reason the builder gave MahaRERA:
“Project was delayed due to death of both the initial directors who were handling the project. Further there is sudden death of one of the newly appointed directors of the company and also there is petition filed by the promoter of the compa…” Read the full reason
“Project was delayed due to death of both the initial directors who were handling the project. Further there is sudden death of one of the newly appointed directors of the company and also there is petition filed by the promoter of the company in court for sale permission of flats as shares of the company was in the name of minor children of the deceased directors. This proceeding is in progress before the court and it will take some time. Afterwards, when things are getting normalised then pandemic situation of COVID-19 arises, so project was delayed because of lockdown and travel restricti…”30 June 2023
Extended at the builder's request (MahaRERA application EXT52000013496)
Reason the builder gave MahaRERA: “AS PER ATTACHED LETTER OF EXTENSION.”
31 July 2023
Extended at the builder's request (MahaRERA application EXT52000017100)
Reason the builder gave MahaRERA: “AS PER FORM-B.”
31 December 2023
Extended at the builder's request (MahaRERA application EXT52000017261)
Reason the builder gave MahaRERA: “AS PER AFFIDAVIT”
30 June 2024
Extended at the builder's request (MahaRERA application EXT52000018757)
Reason the builder gave MahaRERA: “As Per Application For Extension Attached”
31 December 2025
Extended at the builder's request (MahaRERA application EXT52000024312)
Reason the builder gave MahaRERA: “I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52000016411. we have attached the Order for the same from MahaRERA.”
Source: AVANTE’s extension records on MahaRERA (P52000016411), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AVANTE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000016411
- Status
- Lapsed (registration period ended)
- Builder
- SWARAJ MEGA STRUCTURE PRIVATE LIMITED
- Location
- Panvel, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 10 May 2018
- Completion date at registration
- December 2019
- Latest completion date
- December 2025
- Delay so far
- 72 months
- Homes
- 232
- Sold or booked
- 78%
- Towers
- 4
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of AVANTE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 95% | 25% |
| BUILDING B | 100% | 100% | 96% | 30% |
| BUILDING C | 100% | 100% | 100% | 75% |
| BUILDING D | 100% | 100% | 100% | 58% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING A: covers 5 floors
- BUILDING B: covers 5 floors
- BUILDING C: covers 5 floors
- BUILDING D: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AVANTE every month.
AVANTE: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (5 floors, 80 units) · BUILDING B (5 floors, 24 units) · BUILDING C (5 floors, 72 units) · BUILDING D (5 floors, 56 units)
- Land: 14,170 sq m (about 3.5 acres) · sanctioned built-up 13,798 sq m
The builder’s record and reviews
Swaraj Mega Structure (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. 3 complaints on MahaRERA across 2 projects.
Read Google reviews of AVANTE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AVANTE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AVANTE
What is the possession date of AVANTE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AVANTE in Panvel, Raigarh is 31 December 2025 — 72 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for AVANTE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AVANTE's builder has filed on MahaRERA, the official one, is 31 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AVANTE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE's builder applied to MahaRERA to extend the completion date 7 times: to 30 December 2020, giving the reason "DUE TO DEATH OF ONE KEY DIRECTOR, PROJECT EXTENSION APPLICATION HAS BEEN DONE."; to 31 December 2022, giving the reason "Project was delayed due to death of both the initial directors who were handling the project. Further there is sudden death of one of the newly appointed directors of the company and also there is petition filed by the promoter of the company in court for sale permission of flats as shares of the company was in the name of minor children of the deceased directors. This proceeding is in progress before the court and it will take some time. Afterwards, when things are getting normalised then pandemic situation of COVID-19 arises, so project was delayed because of lockdown and travel restricti…"; to 30 June 2023, giving the reason "AS PER ATTACHED LETTER OF EXTENSION."; to 31 July 2023, giving the reason "AS PER FORM-B."; to 31 December 2023, giving the reason "AS PER AFFIDAVIT"; to 30 June 2024, giving the reason "As Per Application For Extension Attached"; to 31 December 2025, giving the reason "I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52000016411. we have attached the Order for the same from MahaRERA.".
What is the RERA number of AVANTE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AVANTE in Panvel, Raigarh is P52000016411.
Is AVANTE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE is registered as P52000016411 and its status is "Lapsed (registration period ended)".
What is the construction status of AVANTE?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does AVANTE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is AVANTE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE is registered on MahaRERA as P52000016411, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AVANTE's possession date changes?
The latest dates are on AVANTE's MahaRERA page (P52000016411). GharKundli's Kundli Watch sends a free WhatsApp update on AVANTE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AVANTE have?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE has 4 buildings filed: BUILDING A with 5 floors and 80 units; BUILDING B with 5 floors and 24 units; BUILDING C with 5 floors and 72 units; BUILDING D with 5 floors and 56 units.
How big is the land of AVANTE?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE stands on 14,170 sq m of land (about 3.5 acres), with 13,798 sq m of sanctioned built-up area.
What is the track record of AVANTE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaraj Mega Structure (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of AVANTE?
Google Maps has reviews of AVANTE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AVANTE?
AVANTE by SWARAJ MEGA STRUCTURE PRIVATE LIMITED is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000016411, per GharKundli's check of MahaRERA records.
How many homes are in AVANTE?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE has 232 homes in 4 towers registered on MahaRERA, and 78% of them are sold or booked.
When was AVANTE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AVANTE was registered on MahaRERA on 10 May 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on AVANTE?
No court cases are listed for AVANTE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AVANTE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SWARAJ MEGA STRUCTURE PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of AVANTE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410206
- Wise City RZ-01 Plotted Development - Phase 3
- Crystal Co-Operative Housing Society Limited
- SAI SIDDHI MADHUBAN
- Pandurang Heights
- Sai Nilay
- MUKTA RESIDENCY
- Shanmukhi Spanda
- Shivesh Mahavir
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.