SERENITY 2

by MAINCO REALTY LLP · Khopoli, RaigarhAlso near Shilphata

Possession date of SERENITY 2: 30 November 2028, moved from 31 July 2024 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000017716, and currently active. Its completion date has moved from July 2024 to November 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SERENITY 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SERENITY 2 has moved

  1. 31 July 2024

    Completion date given when the project was registered

  2. 31 July 2028

    Extended at the builder's request (MahaRERA application EXT52000024468)

    Reason the builder gave MahaRERA:
    “Respected Sir/Madam, We hereby submit our request for an extension of the registration for our project Serenity 2 due to unforeseen and unavoidable circumstances that have significantly impacted project progress. The primary reasons for the…” Read the full reason“Respected Sir/Madam, We hereby submit our request for an extension of the registration for our project Serenity 2 due to unforeseen and unavoidable circumstances that have significantly impacted project progress. The primary reasons for the delay are as follows: 1. Non-Availability of Sand: The unavailability of construction-grade sand due to regulatory restrictions and supply chain disruptions has resulted in delays in critical construction activities. Despite our efforts to source alternative materials and suppliers, procurement challenges have persisted, leading to interruptions in the c…”
  3. 30 November 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SERENITY 2’s extension records on MahaRERA (P52000017716), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SERENITY 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the November 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000017716
Status
Registered and active
Builder
MAINCO REALTY LLP
Location
Khopoli, Raigarh · 410203
Project type
Residential / Group Housing
Registered on
6 Sep 2018
Completion date at registration
July 2024
Latest completion date
November 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
80
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found

Construction progress of SERENITY 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SERENITY 2100%100%85%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SERENITY 2 every month.

SERENITY 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: SERENITY 2 (6 floors)
  • Land: 1,629 sq m (about 0.4 acres) · sanctioned built-up 1,629 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SERENITY 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SERENITY 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SERENITY 2

What is the possession date of SERENITY 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SERENITY 2 in Khopoli, Raigarh is 30 November 2028 — 48 months later than 31 July 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SERENITY 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SERENITY 2's builder has filed on MahaRERA, the official one, is 30 November 2028, already 48 months later than the 31 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SERENITY 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2's builder applied to MahaRERA to extend the completion date once: to 31 July 2028, giving the reason "Respected Sir/Madam, We hereby submit our request for an extension of the registration for our project Serenity 2 due to unforeseen and unavoidable circumstances that have significantly impacted project progress. The primary reasons for the delay are as follows: 1. Non-Availability of Sand: The unavailability of construction-grade sand due to regulatory restrictions and supply chain disruptions has resulted in delays in critical construction activities. Despite our efforts to source alternative materials and suppliers, procurement challenges have persisted, leading to interruptions in the c…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SERENITY 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SERENITY 2 in Khopoli, Raigarh is P52000017716.

Is SERENITY 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2 is registered as P52000017716 and its status is "Registered and active".

What is the construction status of SERENITY 2?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SERENITY 2 is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does SERENITY 2 have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SERENITY 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2 is registered on MahaRERA as P52000017716, its completion date has moved 48 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SERENITY 2's possession date changes?

The latest dates are on SERENITY 2's MahaRERA page (P52000017716). GharKundli's Kundli Watch sends a free WhatsApp update on SERENITY 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SERENITY 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2 has one building filed: SERENITY 2 with 6 floors.

How big is the land of SERENITY 2?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2 stands on 1,629 sq m of land (about 0.4 acres), with 1,629 sq m of sanctioned built-up area.

Where can I read reviews of SERENITY 2?

Google Maps has reviews of SERENITY 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SERENITY 2?

SERENITY 2 by MAINCO REALTY LLP is in Khopoli, Raigarh (pincode 410203), near Shilphata, Maharashtra, and is registered on MahaRERA as P52000017716, per GharKundli's check of MahaRERA records.

How many homes are in SERENITY 2?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2 has 80 homes in 1 tower registered on MahaRERA.

When was SERENITY 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SERENITY 2 was registered on MahaRERA on 6 September 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SERENITY 2?

No court cases are listed for SERENITY 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SERENITY 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAINCO REALTY LLP.

All projects with possession due in 2028 in Raigad →

Other projects in pincode 410203

All 211 projects in Shilphata (410203) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.