SHIV MAJESTIC
by MAJESTIC BUILDERS & DEVELOPERS · Pushpak Node, Raigarh
Possession date of SHIV MAJESTIC: 31 December 2023, moved from 15 August 2021 (28 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000020550. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about SHIV MAJESTIC?
How the possession date of SHIV MAJESTIC has moved
15 August 2021
Completion date given when the project was registered
15 February 2022
Extended at the builder's request (MahaRERA application EXT52000010721)
Reason the builder gave MahaRERA: “Due to Covid-19 pandemic, our construction activity could not be carried out on time and hence could not complete the project on time”
31 December 2023
Extended at the builder's request (MahaRERA application EXT52000015429)
Reason the builder gave MahaRERA: “Work is in progress and there were some Financial constraints due to which construction got delayed during Covid Pandemic.”
Source: SHIV MAJESTIC’s extension records on MahaRERA (P52000020550), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHIV MAJESTIC
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000020550
- Status
- Lapsed (registration period ended)
- Builder
- MAJESTIC BUILDERS & DEVELOPERS
- Location
- Pushpak Node, Raigarh · 410206
- Project type
- Others
- Registered on
- 22 Apr 2019
- Completion date at registration
- August 2021
- Latest completion date
- December 2023
- Delay so far
- 28 months
- Homes
- 36
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of SHIV MAJESTIC, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHIV MAJESTIC | 100% | 100% | 100% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIV MAJESTIC every month.
SHIV MAJESTIC: buildings, flats and land, as filed on MahaRERA
- Buildings: SHIV MAJESTIC (8 floors)
- Land: 700 sq m (about 0.2 acres) · sanctioned built-up 1,050 sq m
The builder’s record and reviews
Majestic Builders & Developers has 3 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of SHIV MAJESTIC →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHIV MAJESTIC: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHIV MAJESTIC
What is the possession date of SHIV MAJESTIC?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHIV MAJESTIC in Pushpak Node, Raigarh is 31 December 2023 — 28 months later than 15 August 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SHIV MAJESTIC?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIV MAJESTIC's builder has filed on MahaRERA, the official one, is 31 December 2023, already 28 months later than the 15 August 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHIV MAJESTIC extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC's builder applied to MahaRERA to extend the completion date 2 times: to 15 February 2022, giving the reason "Due to Covid-19 pandemic, our construction activity could not be carried out on time and hence could not complete the project on time"; to 31 December 2023, giving the reason "Work is in progress and there were some Financial constraints due to which construction got delayed during Covid Pandemic.".
What is the RERA number of SHIV MAJESTIC?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHIV MAJESTIC in Pushpak Node, Raigarh is P52000020550.
Is SHIV MAJESTIC registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC is registered as P52000020550 and its status is "Lapsed (registration period ended)".
What is the construction status of SHIV MAJESTIC?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHIV MAJESTIC is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHIV MAJESTIC have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHIV MAJESTIC safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC is registered on MahaRERA as P52000020550, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 28 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHIV MAJESTIC's possession date changes?
The latest dates are on SHIV MAJESTIC's MahaRERA page (P52000020550). GharKundli's Kundli Watch sends a free WhatsApp update on SHIV MAJESTIC every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHIV MAJESTIC have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC has one building filed: SHIV MAJESTIC with 8 floors.
How big is the land of SHIV MAJESTIC?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC stands on 700 sq m of land (about 0.2 acres), with 1,050 sq m of sanctioned built-up area.
What is the track record of SHIV MAJESTIC's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Majestic Builders & Developers has 3 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHIV MAJESTIC?
Google Maps has reviews of SHIV MAJESTIC written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHIV MAJESTIC?
SHIV MAJESTIC by MAJESTIC BUILDERS & DEVELOPERS is in Pushpak Node, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000020550, per GharKundli's check of MahaRERA records.
How many homes are in SHIV MAJESTIC?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC has 36 homes in 1 tower registered on MahaRERA.
When was SHIV MAJESTIC registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIV MAJESTIC was registered on MahaRERA on 22 April 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SHIV MAJESTIC?
No court cases are listed for SHIV MAJESTIC on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHIV MAJESTIC?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAJESTIC BUILDERS & DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHIV MAJESTIC
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pushpak Node
- SITA RESIDENCY
- BHAVESHWAR RUDRA
- SIDDHIVINAYAK MANGALAM
- KRISHNA HILLS
- SHREEPATI REGALIA
- PRECIOUS MAJESTIC
- DHRITI AURA
- THE BELLAGIO
Other projects by MAJESTIC BUILDERS & DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.