MARATHON NEXZONE CEDAR - 2
by SANVO RESORTS PVT. LTD. (Marathon) · Palaspe Phata, Raigarh
Possession date of MARATHON NEXZONE CEDAR - 2: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000023255, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about MARATHON NEXZONE CEDAR - 2?
GharKundli’s full report on MARATHON NEXZONE CEDAR - 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- MARATHON NEXZONE CEDAR - 1P52000023250 · possession 30 Jun 2026
- MahaRERA registration
- P52000023255
- Status
- Registered and active
- Builder
- SANVO RESORTS PVT. LTD.
- Location
- Palaspe Phata, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 9 Dec 2019
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 98
- Sold or booked
- 53%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 32
Construction progress of MARATHON NEXZONE CEDAR - 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MARATHON NEXZONE CEDAR - 2 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- MARATHON NEXZONE CEDAR - 2: covers 27 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARATHON NEXZONE CEDAR - 2 every month.
MARATHON NEXZONE CEDAR - 2: buildings, flats and land, as filed on MahaRERA
- Buildings: MARATHON NEXZONE CEDAR - 2 (13 floors, 98 units)
- Land: 539 sq m (about 0.1 acres) · sanctioned built-up 700 sq m
- Boundaries filed include: NATIONAL HIGHWAY NH 4B
The builder’s record and reviews
Marathon Realty (a group of 13 linked companies) has 76 projects on MahaRERA since 2017, this one included. Of the 76 GharKundli has checked: 40 finished, 30 within the promised date and 10 needed more time (typically 14 months); 23 still being built, 4 past the promised date (typically 18 months late); 13 lapsed. 214 complaints on MahaRERA across 47 projects.
Read Google reviews of MARATHON NEXZONE CEDAR - 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MARATHON NEXZONE CEDAR - 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MARATHON NEXZONE CEDAR - 2
What is the possession date of MARATHON NEXZONE CEDAR - 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MARATHON NEXZONE CEDAR - 2 in Palaspe Phata, Raigarh is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MARATHON NEXZONE CEDAR - 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MARATHON NEXZONE CEDAR - 2's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of MARATHON NEXZONE CEDAR - 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MARATHON NEXZONE CEDAR - 2 in Palaspe Phata, Raigarh is P52000023255.
Is MARATHON NEXZONE CEDAR - 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXZONE CEDAR - 2 is registered as P52000023255 and its status is "Registered and active".
What is the construction status of MARATHON NEXZONE CEDAR - 2?
According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXZONE CEDAR - 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MARATHON NEXZONE CEDAR - 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MARATHON NEXZONE CEDAR - 2 have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MARATHON NEXZONE CEDAR - 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXZONE CEDAR - 2 is registered on MahaRERA as P52000023255, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does MARATHON NEXZONE CEDAR - 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: MARATHON NEXZONE CEDAR - 1 (P52000023250, possession 30 Jun 2026). Check that your agreement names the registration of your own wing.
How can I get updates if MARATHON NEXZONE CEDAR - 2's possession date changes?
The latest dates are on MARATHON NEXZONE CEDAR - 2's MahaRERA page (P52000023255). GharKundli's Kundli Watch sends a free WhatsApp update on MARATHON NEXZONE CEDAR - 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MARATHON NEXZONE CEDAR - 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXZONE CEDAR - 2 has one building filed: MARATHON NEXZONE CEDAR - 2 with 13 floors and 98 units.
How big is the land of MARATHON NEXZONE CEDAR - 2?
According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXZONE CEDAR - 2 stands on 539 sq m of land (about 0.1 acres), with 700 sq m of sanctioned built-up area.
What is the track record of MARATHON NEXZONE CEDAR - 2's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Marathon Realty (a group of 13 linked companies) has 76 projects on MahaRERA since 2017, this one included. Of the 76 GharKundli has checked: 40 finished, 30 within the promised date and 10 needed more time (typically 14 months); 23 still being built, 4 past the promised date (typically 18 months late); 13 lapsed. 214 complaints on MahaRERA across 47 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MARATHON NEXZONE CEDAR - 2?
Google Maps has reviews of MARATHON NEXZONE CEDAR - 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MARATHON NEXZONE CEDAR - 2?
MARATHON NEXZONE CEDAR - 2 by SANVO RESORTS PVT. LTD. (Marathon) is in Palaspe Phata, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000023255, per GharKundli's check of MahaRERA records. Its boundaries filed there include NATIONAL HIGHWAY NH 4B.
How many homes are in MARATHON NEXZONE CEDAR - 2?
According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXZONE CEDAR - 2 has 98 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.
When was MARATHON NEXZONE CEDAR - 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXZONE CEDAR - 2 was registered on MahaRERA on 9 December 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on MARATHON NEXZONE CEDAR - 2?
No court cases are listed for MARATHON NEXZONE CEDAR - 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of MARATHON NEXZONE CEDAR - 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SANVO RESORTS PVT. LTD., the company Marathon files this project under, which has 32 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MARATHON NEXZONE CEDAR - 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
All projects in Panvel (410206) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.