Skip to content
GharKundli

SAI KALASH

by KALSHA BUILDERS PRIVATE LIMITED · Ulwe New, RaigarhAlso near Panvel

Possession: SAI KALASH is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000023203. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAI KALASH?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI KALASH has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52000013791)

    Reason the builder gave MahaRERA: “AS PER DOCUMENTS ATTACHED”

Source: SAI KALASH’s extension records on MahaRERA (P52000023203), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI KALASH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000023203
Status
Completed
Builder
KALSHA BUILDERS PRIVATE LIMITED
Location
Ulwe New, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
6 Dec 2019
Completion date at registration
December 2022
Latest completion date
June 2023
Delay so far
6 months
Homes
33
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of SAI KALASH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI-KALASH100%100%95%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI KALASH every month.

SAI KALASH: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI-KALASH (9 floors)
  • Land: 599 sq m (about 0.1 acres) · sanctioned built-up 899 sq m
  • Boundaries filed include: 09 MTS WIDE ROAD

The builder’s record and reviews

SAI Shraddha Enterprises (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of SAI KALASH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI KALASH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI KALASH

What is the possession date of SAI KALASH?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI KALASH in Ulwe New, Raigarh is 30 June 2023 — 6 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI KALASH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI KALASH's builder has filed on MahaRERA, the official one, is 30 June 2023, already 6 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI KALASH extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "AS PER DOCUMENTS ATTACHED".

What is the RERA number of SAI KALASH?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI KALASH in Ulwe New, Raigarh is P52000023203.

Is SAI KALASH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH is registered as P52000023203 and its status is "Completed".

What is the construction status of SAI KALASH?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH's status on MahaRERA is "Completed". As filed by the builder, slab work on SAI-KALASH is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does SAI KALASH have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAI KALASH safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH is registered on MahaRERA as P52000023203, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI KALASH's possession date changes?

The latest dates are on SAI KALASH's MahaRERA page (P52000023203). GharKundli's Kundli Watch sends a free WhatsApp update on SAI KALASH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI KALASH have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH has one building filed: SAI-KALASH with 9 floors.

How big is the land of SAI KALASH?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH stands on 599 sq m of land (about 0.1 acres), with 899 sq m of sanctioned built-up area.

What is the track record of SAI KALASH's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI Shraddha Enterprises (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAI KALASH?

Google Maps has reviews of SAI KALASH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI KALASH?

SAI KALASH by KALSHA BUILDERS PRIVATE LIMITED is in Ulwe New, Raigarh (pincode 410206), near Panvel, Maharashtra, and is registered on MahaRERA as P52000023203, per GharKundli's check of MahaRERA records. Its boundaries filed there include 09 MTS WIDE ROAD.

How many homes are in SAI KALASH?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH has 33 homes in 1 tower registered on MahaRERA.

When was SAI KALASH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KALASH was registered on MahaRERA on 6 December 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI KALASH?

No court cases are listed for SAI KALASH on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI KALASH?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KALSHA BUILDERS PRIVATE LIMITED.

Other projects in pincode 410206

All 2,664 projects in Panvel (410206) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.