SAI ICON
by Paradise Infra-con Pvt Ltd · Kharghar, RaigarhAlso near Sokhda
Possession: SAI ICON is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000023156. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
Sales frozen by MahaRERA: completion date lapsed
MahaRERA has put this project in abeyance because its completion date has lapsed. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about SAI ICON?
How the possession date of SAI ICON has moved
30 December 2024
Completion date given when the project was registered
14 May 2025
Extended at the builder's request (MahaRERA application EXT52000025662)
Reason the builder gave MahaRERA:
“The Project was registered in December 2019 but due to spread of Pandemic COVID 19 work at site could not be started. The aftermath of COVID 19 continued till end of year 2021. MahaRERA has given suomoto extension of one year time but factu…” Read the full reason
“The Project was registered in December 2019 but due to spread of Pandemic COVID 19 work at site could not be started. The aftermath of COVID 19 continued till end of year 2021. MahaRERA has given suomoto extension of one year time but factually the effect of the pandemic was felt for almost 2 years. The Construction work firstly got delayed due to COVID 19 and Lockdown and Later on due to labour shortage. The Promoter has taken extensive efforts and completed the construction work of the building and obtained the Occupancy Certificate from Authority CIDCO Dated 14-05-2025. The copy of OC is…”
Source: SAI ICON’s extension records on MahaRERA (P52000023156), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI ICON
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the May 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000023156
- Status
- Completed
- Builder
- Paradise Infra-con Pvt Ltd
- Location
- Kharghar, Raigarh · 410210
- Project type
- Residential / Group Housing
- Registered on
- 4 Dec 2019
- Completion date at registration
- December 2024
- Latest completion date
- May 2025
- Delay so far
- 5 months
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SAI ICON, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI ICON | 100% | 100% | 95% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI ICON every month.
SAI ICON: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI ICON (16 floors)
- Land: 3,042 sq m (about 0.8 acres) · sanctioned built-up 4,563 sq m · recreational space 1,353 sq m
The builder’s record and reviews
Paradise Infracon (a group of 10 linked companies) has 30 projects on MahaRERA since 2017, this one included. Of the 30 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 4 months); 22 still being built, 2 past the promised date (typically 15 months late). 18 complaints on MahaRERA across 12 projects.
Read Google reviews of SAI ICON →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI ICON: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI ICON
What is the possession date of SAI ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI ICON in Kharghar, Raigarh is 14 May 2025 — 5 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAI ICON?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI ICON's builder has filed on MahaRERA, the official one, is 14 May 2025, already 5 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI ICON extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI ICON's builder applied to MahaRERA to extend the completion date once: to 14 May 2025, giving the reason "The Project was registered in December 2019 but due to spread of Pandemic COVID 19 work at site could not be started. The aftermath of COVID 19 continued till end of year 2021. MahaRERA has given suomoto extension of one year time but factually the effect of the pandemic was felt for almost 2 years. The Construction work firstly got delayed due to COVID 19 and Lockdown and Later on due to labour shortage. The Promoter has taken extensive efforts and completed the construction work of the building and obtained the Occupancy Certificate from Authority CIDCO Dated 14-05-2025. The copy of OC is…".
What is the RERA number of SAI ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI ICON in Kharghar, Raigarh is P52000023156.
Is SAI ICON registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI ICON is registered as P52000023156 and its status is "Completed". On MahaRERA's own list: Sales frozen by MahaRERA: completion date lapsed. MahaRERA has put this project in abeyance because its completion date has lapsed. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
What is the construction status of SAI ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI ICON's status on MahaRERA is "Completed". As filed by the builder, slab work on SAI ICON is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does SAI ICON have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAI ICON safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI ICON is registered on MahaRERA as P52000023156, its MahaRERA status is "Completed", its completion date has moved 5 months since registration, 1 complaint is listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: completion date lapsed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI ICON's possession date changes?
The latest dates are on SAI ICON's MahaRERA page (P52000023156). GharKundli's Kundli Watch sends a free WhatsApp update on SAI ICON every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI ICON have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI ICON has one building filed: SAI ICON with 16 floors.
How big is the land of SAI ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI ICON stands on 3,042 sq m of land (about 0.8 acres), with 4,563 sq m of sanctioned built-up area and 1,353 sq m of recreational open space.
What is the track record of SAI ICON's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Paradise Infracon (a group of 10 linked companies) has 30 projects on MahaRERA since 2017, this one included. Of the 30 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 4 months); 22 still being built, 2 past the promised date (typically 15 months late). 18 complaints on MahaRERA across 12 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAI ICON?
Google Maps has reviews of SAI ICON written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI ICON?
SAI ICON by Paradise Infra-con Pvt Ltd is in Kharghar, Raigarh (pincode 410210), near Sokhda, Maharashtra, and is registered on MahaRERA as P52000023156, per GharKundli's check of MahaRERA records.
When was SAI ICON registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI ICON was registered on MahaRERA on 4 December 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI ICON?
No court cases are listed for SAI ICON on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAI ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Paradise Infra-con Pvt Ltd.
Check it yourself on MahaRERA
- How to check the possession date of SAI ICON
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410210
- SATYAM VALENCIA
- Nisarg Aura
- Utsav Residency Building No. 1 A and B
- Raya
- THE CRYSTAL PALACE
- Bhagwati Gami Altair
- Gami Bhagwati Orelia
- MADHURAAJ KEDARNATH
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.