PREMIER EXOTICA I
by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD · Kurla West, MumbaiAlso near Bhandup west, Rajawadi, Ghatkopar West
Possession date of PREMIER EXOTICA I: 31 January 2021. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800004431. Status: Lapsed (registration period ended). 10 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (January 2021) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about PREMIER EXOTICA I?
GharKundli’s full report on PREMIER EXOTICA I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 10 complaints, and how it ended
- Construction pace against the January 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- PREMIER EXOTICA IIP51800016598 · possession 31 Dec 2019
- MahaRERA registration
- P51800004431
- Status
- Lapsed (registration period ended)
- Builder
- HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
- Location
- Kurla West, Mumbai · 400070
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- January 2021
- Latest completion date
- January 2021
- Homes
- 519
- Towers
- 6
- Complaints on MahaRERA
- 10
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of PREMIER EXOTICA I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING - A | 100% | 100% | 100% | 90% |
| WING - B | 100% | 100% | 100% | 90% |
| WING - C | 100% | 100% | 70% | 0% |
| WING - D | 100% | 100% | 35% | 0% |
| WING - E | 100% | 100% | 30% | 0% |
| WING - F | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PREMIER EXOTICA I every month.
PREMIER EXOTICA I: buildings, flats and land, as filed on MahaRERA
- Buildings: WING - A (18 floors) · WING - B (18 floors) · WING - C (18 floors) · WING - D (18 floors) · WING - E (18 floors)
- Land: 9,075 sq m (about 2.2 acres) · sanctioned built-up 30,273 sq m · recreational space 16,355 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Housing Development AND Infrastructure has 14 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 7 lapsed. 215 complaints on MahaRERA across 8 projects.
Read Google reviews of PREMIER EXOTICA I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PREMIER EXOTICA I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PREMIER EXOTICA I
What is the possession date of PREMIER EXOTICA I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PREMIER EXOTICA I in Kurla West, Mumbai is 31 January 2021. That date has already passed.
Is the builder's possession date different from the MahaRERA date for PREMIER EXOTICA I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PREMIER EXOTICA I's builder has filed on MahaRERA, the official one, is 31 January 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of PREMIER EXOTICA I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PREMIER EXOTICA I in Kurla West, Mumbai is P51800004431.
Is PREMIER EXOTICA I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PREMIER EXOTICA I is registered as P51800004431 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of PREMIER EXOTICA I?
According to GharKundli's check of MahaRERA records (updated November 2026), PREMIER EXOTICA I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does PREMIER EXOTICA I have complaints on MahaRERA?
10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PREMIER EXOTICA I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PREMIER EXOTICA I is registered on MahaRERA as P51800004431, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder, 10 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does PREMIER EXOTICA I have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: PREMIER EXOTICA II (P51800016598, possession 31 Dec 2019). Check that your agreement names the registration of your own wing.
How can I get updates if PREMIER EXOTICA I's possession date changes?
The latest dates are on PREMIER EXOTICA I's MahaRERA page (P51800004431). GharKundli's Kundli Watch sends a free WhatsApp update on PREMIER EXOTICA I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PREMIER EXOTICA I have?
According to GharKundli's check of MahaRERA records (updated November 2026), PREMIER EXOTICA I has 5 buildings filed: WING - A with 18 floors; WING - B with 18 floors; WING - C with 18 floors; WING - D with 18 floors; WING - E with 18 floors.
How big is the land of PREMIER EXOTICA I?
According to GharKundli's check of MahaRERA records (updated November 2026), PREMIER EXOTICA I stands on 9,075 sq m of land (about 2.2 acres), with 30,273 sq m of sanctioned built-up area and 16,355 sq m of recreational open space.
What is the track record of PREMIER EXOTICA I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Housing Development AND Infrastructure has 14 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 7 lapsed. 215 complaints on MahaRERA across 8 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PREMIER EXOTICA I?
Google Maps has reviews of PREMIER EXOTICA I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PREMIER EXOTICA I?
PREMIER EXOTICA I by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD is in Kurla West, Mumbai (pincode 400070), near Bhandup west, Rajawadi, Ghatkopar West, Maharashtra, and is registered on MahaRERA as P51800004431, per GharKundli's check of MahaRERA records.
How many homes are in PREMIER EXOTICA I?
According to GharKundli's check of MahaRERA records (updated November 2026), PREMIER EXOTICA I has 519 homes in 6 towers registered on MahaRERA.
When was PREMIER EXOTICA I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PREMIER EXOTICA I was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on PREMIER EXOTICA I?
No court cases are listed for PREMIER EXOTICA I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PREMIER EXOTICA I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PREMIER EXOTICA I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400070
- JAI SHREERAM PRASANNA CHSL
- ANUPAM VILLA CHSL
- SAI CHAMUNDA
- Kalyan Kutir Co-operative Housing Society Limited
- SAYBA ARCADIA
- DERAIYA LUXURIO
- Taiba Residency
- Dadamiya’s Man'souza Height
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.