by PRESTIGE MULUND REALTY PRIVATE LIMITED · Mulund West, MumbaiAlso near Wagle I.E

Possession: SIESTA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800005285. Status: Completed. 12 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SIESTA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SIESTA has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800011846)

    Reason the builder gave MahaRERA: “This project is taken over through Resolution Plan passed by NCLT court order dated 23 Mar 2021. Home buyers Association was also a part of the Resolution Plan passed by Majority and approved by NCLT.”

Source: SIESTA’s extension records on MahaRERA (P51800005285), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SIESTA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 12 complaints and 5 court cases, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005285
Status
Completed
Builder
PRESTIGE MULUND REALTY PRIVATE LIMITED
Location
Mulund West, Mumbai · 400080
Project type
Residential / Group Housing
Registered on
11 Aug 2017
Completion date at registration
December 2023
Latest completion date
June 2025
Delay so far
18 months
Towers
1
Complaints on MahaRERA
12
Court cases listed
5
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of SIESTA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SIESTA100%100%90%25%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIESTA every month.

SIESTA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Prestige Mulund Realty (a group of 3 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 8 still being built, none past the promised date yet; 1 lapsed. 36 complaints on MahaRERA across 6 projects.

Read Google reviews of SIESTA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SIESTA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SIESTA

What is the possession date of SIESTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SIESTA in Mulund West, Mumbai is 30 June 2025 — 18 months later than 30 December 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SIESTA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SIESTA's builder has filed on MahaRERA, the official one, is 30 June 2025, already 18 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SIESTA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SIESTA's builder applied to MahaRERA to extend the completion date once: to 30 June 2025, giving the reason "This project is taken over through Resolution Plan passed by NCLT court order dated 23 Mar 2021. Home buyers Association was also a part of the Resolution Plan passed by Majority and approved by NCLT.".

What is the RERA number of SIESTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SIESTA in Mulund West, Mumbai is P51800005285.

Is SIESTA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SIESTA is registered as P51800005285 and its status is "Completed".

What is the construction status of SIESTA?

According to GharKundli's check of MahaRERA records (updated October 2026), SIESTA's status on MahaRERA is "Completed". As filed by the builder, slab work on SIESTA is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does SIESTA have complaints on MahaRERA?

12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SIESTA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SIESTA is registered on MahaRERA as P51800005285, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 12 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SIESTA's possession date changes?

The latest dates are on SIESTA's MahaRERA page (P51800005285). GharKundli's Kundli Watch sends a free WhatsApp update on SIESTA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SIESTA have?

According to GharKundli's check of MahaRERA records (updated October 2026), SIESTA has one building filed: SIESTA with 68 floors.

How big is the land of SIESTA?

According to GharKundli's check of MahaRERA records (updated October 2026), SIESTA stands on 7,250 sq m of land (about 1.8 acres), with 41,230 sq m of sanctioned built-up area.

What is the track record of SIESTA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Prestige Mulund Realty (a group of 3 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 8 still being built, none past the promised date yet; 1 lapsed. 36 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SIESTA?

Google Maps has reviews of SIESTA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SIESTA?

SIESTA by PRESTIGE MULUND REALTY PRIVATE LIMITED is in Mulund West, Mumbai (pincode 400080), near Wagle I.E, Maharashtra, and is registered on MahaRERA as P51800005285, per GharKundli's check of MahaRERA records.

When was SIESTA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SIESTA was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SIESTA?

5 court cases are listed for SIESTA on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SIESTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRESTIGE MULUND REALTY PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.

Other projects in pincode 400080

All 303 projects in Mulund West (400080) →

Other projects by PRESTIGE MULUND REALTY PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.