Shraddha Paradise Enclave
by Shraddha Prime Projects Limited · Veena Nagar Phase II, Mumbai
Possession date of Shraddha Paradise Enclave: 31 July 2030, moved from 31 March 2029 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002600018, and currently active. Its completion date has moved from March 2029 to July 2030: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Shraddha Paradise Enclave?
How the possession date of Shraddha Paradise Enclave has moved
31 March 2029
Completion date given when the project was registered
31 March 2030
Extended at the builder's request (MahaRERA application EA27082622407)
Reason the builder gave MahaRERA:
“The delay in completion of project has occurred due to an inadvertent miscalculation of the project completion date at the time of registration. Consequently, the registered completion timeline did not accurately reflect the actual period r…” Read the full reason
“The delay in completion of project has occurred due to an inadvertent miscalculation of the project completion date at the time of registration. Consequently, the registered completion timeline did not accurately reflect the actual period required for completion of the project. We are therefore in the process of applying for a further extension of the project completion date to regularize the timeline and enable us to complete the remaining project activities and necessary formalities within the extended period. Given the circumstances, we kindly request an extension until 31-03-2030, to co…”31 July 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shraddha Paradise Enclave’s extension records on MahaRERA (PR1180002600018), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shraddha Paradise Enclave
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002600018
- Status
- Registered and active
- Builder
- Shraddha Prime Projects Limited
- Location
- Veena Nagar Phase II, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 6 Apr 2026
- Completion date at registration
- March 2029
- Latest completion date
- July 2030
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 197
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of Shraddha Paradise Enclave, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| COMMERCIAL WING | 0% | 0% | 0% | 0% |
| RESIDENTIAL WING | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- COMMERCIAL WING: covers Plinth level
- RESIDENTIAL WING: covers Plinth level
Latest CC order on MahaRERA: dated 01/04/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shraddha Paradise Enclave every month.
Shraddha Paradise Enclave: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 558 – 1,019 | 158 |
| 3 BHK | 754 – 1,019 | 35 |
| Shops | 502 – 746 | 5 |
| Other | 1,821 – 5,075 | 5 |
| 1 Room Kitchen | 393 | 4 |
- Buildings: COMMERCIAL WING (8 floors, 10 units) · RESIDENTIAL WING (37 floors, 197 units)
- Car parking: 256 covered
- Land: 3,997 sq m (about 1.0 acres) · sanctioned built-up 17,392 sq m · recreational space 367 sq m
- Boundaries filed include: Sumangal Society, Internal Road towards hospital, Saptarshi Park
The builder’s record and reviews
Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.
Read Google reviews of Shraddha Paradise Enclave →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shraddha Paradise Enclave: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shraddha Paradise Enclave
What is the possession date of Shraddha Paradise Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shraddha Paradise Enclave in Veena Nagar Phase II, Mumbai is 31 July 2030 — 12 months later than 31 March 2029, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shraddha Paradise Enclave?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shraddha Paradise Enclave's builder has filed on MahaRERA, the official one, is 31 July 2030, already 12 months later than the 31 March 2029 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shraddha Paradise Enclave extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave's builder applied to MahaRERA to extend the completion date once: to 31 March 2030, giving the reason "The delay in completion of project has occurred due to an inadvertent miscalculation of the project completion date at the time of registration. Consequently, the registered completion timeline did not accurately reflect the actual period required for completion of the project. We are therefore in the process of applying for a further extension of the project completion date to regularize the timeline and enable us to complete the remaining project activities and necessary formalities within the extended period. Given the circumstances, we kindly request an extension until 31-03-2030, to co…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shraddha Paradise Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shraddha Paradise Enclave in Veena Nagar Phase II, Mumbai is PR1180002600018.
Is Shraddha Paradise Enclave registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave is registered as PR1180002600018 and its status is "Registered and active".
What is the construction status of Shraddha Paradise Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Shraddha Paradise Enclave have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Shraddha Paradise Enclave safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave is registered on MahaRERA as PR1180002600018, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shraddha Paradise Enclave's possession date changes?
The latest dates are on Shraddha Paradise Enclave's MahaRERA page (PR1180002600018). GharKundli's Kundli Watch sends a free WhatsApp update on Shraddha Paradise Enclave every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shraddha Paradise Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave has 2 buildings filed: COMMERCIAL WING with 8 floors and 10 units; RESIDENTIAL WING with 37 floors and 197 units.
What are the flat sizes (carpet area) in Shraddha Paradise Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shraddha Paradise Enclave: 2 BHK: 558 to 1019 sq ft carpet (158 homes); 3 BHK: 754 to 1019 sq ft carpet (35 homes); 1 Room Kitchen: 393 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shraddha Paradise Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 256 covered car parking spaces for Shraddha Paradise Enclave.
How big is the land of Shraddha Paradise Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave stands on 3,997 sq m of land (about 1.0 acres), with 17,392 sq m of sanctioned built-up area and 367 sq m of recreational open space.
What is the track record of Shraddha Paradise Enclave's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Shraddha Paradise Enclave?
Google Maps has reviews of Shraddha Paradise Enclave written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shraddha Paradise Enclave?
Shraddha Paradise Enclave by Shraddha Prime Projects Limited is in Veena Nagar Phase II, Mumbai (pincode 400080), Maharashtra, and is registered on MahaRERA as PR1180002600018, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sumangal Society, Internal Road towards hospital, Saptarshi Park.
How many homes are in Shraddha Paradise Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave has 197 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Shraddha Paradise Enclave registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise Enclave was registered on MahaRERA on 6 April 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on Shraddha Paradise Enclave?
No court cases are listed for Shraddha Paradise Enclave on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Shraddha Paradise Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shraddha Prime Projects Limited, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shraddha Paradise Enclave
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in Kurla
- Jai Arihant
- Saptashringi
- SUDHANSHU HEIGHTS
- Heritage Lakeside
- Kalyan Kutir Co-operative Housing Society Limited
- Kanakdhara
- Privilon
- Emerald Isle - T16
Other projects by Shraddha Prime Projects Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.