Shraddha Panorama
by Shraddha Prime Projects Limited · Mulund, Mumbai 400080Also near Bhandup West, Off Dmart, Wagle I.E
What’s in the report? →Possession date of Shraddha Panorama (MahaRERA P51800053318): 30 April 2028, moved from 31 December 2026 (12 months later). It has 278 homes (1 BHK and 2 BHK, 411–659 sq ft carpet), 22% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800053318, and currently active. Its completion date has moved from December 2026 to April 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800053318, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shraddha Panorama?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shraddha Panorama has moved
31 December 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA12112518314)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shraddha Panorama’s extension records on MahaRERA (P51800053318), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shraddha Panorama
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800053318
- Status
- Registered and active
- Builder
- Shraddha Prime Projects Limited
- Location
- Mulund, Mumbai · 400080
- Project type
- Others
- Registered on
- 27 Oct 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2028
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 278
- Sold or booked
- 22%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of Shraddha Panorama, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sale Building - 1 | 100% | 47.82% | 6.52% | 3.8% |
| Sale Building - 2 | 100% | 12.19% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sale Building - 1: covers 23 (G + 22)
- Sale Building - 2: covers 41 (G + 40)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shraddha Panorama every 1–2 months.
Shraddha Panorama: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 520 – 659 | 158 |
| 1 BHK | 411 – 476 | 120 |
| Shops | 1,070 – 1,098 | 4 |
- Buildings: Sale Building - 1 (23 floors, 40 units) · Sale Building - 2 (41 floors, 242 units)
- Car parking: 138 covered
- Land: 2,850 sq m (about 0.7 acres) · sanctioned built-up 15,363 sq m · recreational space 245 sq m
- Boundaries filed include: Mulund-Goregaon Link Road
- Land, as filed: C.T.S. No. 679 (pt)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.
Read Google reviews of Shraddha Panorama →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shraddha Panorama: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shraddha Panorama
What is the possession date of Shraddha Panorama?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shraddha Panorama in Mulund, Mumbai is 30 April 2028 — 12 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shraddha Panorama?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shraddha Panorama's builder has filed on MahaRERA, the official one, is 30 April 2028, already 12 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shraddha Panorama extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shraddha Panorama?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shraddha Panorama in Mulund, Mumbai is P51800053318.
Is Shraddha Panorama registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama is registered as P51800053318 and its status is "Registered and active".
What is the current construction status of Shraddha Panorama? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 12.19% to 47.82% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Shraddha Panorama have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shraddha Panorama safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama is registered on MahaRERA as P51800053318, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shraddha Panorama?
Shraddha Panorama is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shraddha Panorama are 411 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shraddha Panorama?
For a flat in Shraddha Panorama (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shraddha Panorama received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Shraddha Panorama a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama is a redevelopment: 100 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Shraddha Panorama uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shraddha Panorama was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shraddha Panorama's possession date changes?
The latest dates are on Shraddha Panorama's MahaRERA page (P51800053318). GharKundli's Kundli Watch sends a free WhatsApp update on Shraddha Panorama every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shraddha Panorama have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama has 2 buildings filed: Sale Building - 1 with 23 floors and 40 units; Sale Building - 2 with 41 floors and 242 units.
What are the flat sizes (carpet area) in Shraddha Panorama?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shraddha Panorama: 2 BHK: 520 to 659 sq ft carpet (158 homes); 1 BHK: 411 to 476 sq ft carpet (120 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shraddha Panorama have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 138 covered car parking spaces for Shraddha Panorama.
How big is the land of Shraddha Panorama?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama stands on 2,850 sq m of land (about 0.7 acres), with 15,363 sq m of sanctioned built-up area and 245 sq m of recreational open space.
What is the track record of Shraddha Panorama's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Shraddha Panorama?
Google Maps has reviews of Shraddha Panorama written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shraddha Panorama?
Shraddha Panorama by Shraddha Prime Projects Limited is in Mulund, Mumbai, pincode 400080 (near Bhandup West, Off Dmart, Wagle I.E), Maharashtra, and is registered on MahaRERA as P51800053318, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mulund-Goregaon Link Road. Its land is filed as C.T.S. No. 679 (pt). GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Shraddha Panorama, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama has 278 homes in 2 towers registered on MahaRERA, and 22% of them are sold or booked.
When was Shraddha Panorama registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Panorama was registered on MahaRERA on 27 October 2023. GharKundli did not find a title report on the land on file there.
Does Shraddha Panorama have any legal issues or court cases?
No court cases are listed for Shraddha Panorama on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shraddha Panorama?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shraddha Prime Projects Limited, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shraddha Panorama
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Mulund West (400080)
- Shraddha Paradise Enclave
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Old Hemant Villa Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
Other projects by Shraddha Prime Projects Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.