by Shraddha Prime Projects Limited · Borivali, Mumbai 400092Also near Rajendra Nagar, Magathane, Shimpoli

What’s in the report? →

Possession date of Shraddha Paradise (MahaRERA P51800052244): 30 April 2029. It has 356 homes (1 BHK, 2 BHK and 3 BHK, 453–949 sq ft carpet), 68% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052244, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800052244, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shraddha Paradise?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shraddha Paradise has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shraddha Paradise’s extension records on MahaRERA (P51800052244), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shraddha Paradise

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052244
Status
Registered and active
Builder
Shraddha Prime Projects Limited
Location
Borivali, Mumbai · 400092
Project type
Residential / Group Housing
Registered on
2 Aug 2023
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
356
Sold or booked
68%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of Shraddha Paradise, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A and Wing B100%30%8%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A and Wing B: covers 35 (Ground + 3 Podiums + 31 Upper FLoors)

Latest CC order on MahaRERA: dated 15/07/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shraddha Paradise every 1–2 months.

Shraddha Paradise: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK500 – 713235
3 BHK829 – 949106
1 BHK453 – 56315
  • Buildings: Wing A and Wing B (35 floors, 356 units)
  • Car parking: 350 covered
  • Land: 8,114 sq m (about 2.0 acres) · sanctioned built-up 26,148 sq m
  • Boundaries filed include: Western Railway DT4 Railway Yards-Tracks, Hari Om Nagar
  • Land, as filed: 63/2,3(pt.),4,5,7,10(pt.)
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.

Read Google reviews of Shraddha Paradise →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shraddha Paradise: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shraddha Paradise

What is the possession date of Shraddha Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shraddha Paradise in Borivali, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Shraddha Paradise?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shraddha Paradise's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shraddha Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shraddha Paradise in Borivali, Mumbai is P51800052244.

Is Shraddha Paradise registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise is registered as P51800052244 and its status is "Registered and active".

What is the current construction status of Shraddha Paradise? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A and Wing B is 30% done and internal work 8%. GharKundli's full report compares construction progress with the deadline.

Does Shraddha Paradise have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shraddha Paradise safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise is registered on MahaRERA as P51800052244, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shraddha Paradise?

Shraddha Paradise is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shraddha Paradise are 453 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shraddha Paradise?

For a flat in Shraddha Paradise (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shraddha Paradise received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Shraddha Paradise a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise is a redevelopment: 148 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Shraddha Paradise uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shraddha Paradise was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shraddha Paradise's possession date changes?

The latest dates are on Shraddha Paradise's MahaRERA page (P51800052244). GharKundli's Kundli Watch sends a free WhatsApp update on Shraddha Paradise every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shraddha Paradise have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise has one building filed: Wing A and Wing B with 35 floors and 356 units.

What are the flat sizes (carpet area) in Shraddha Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shraddha Paradise: 2 BHK: 500 to 713 sq ft carpet (235 homes); 3 BHK: 829 to 949 sq ft carpet (106 homes); 1 BHK: 453 to 563 sq ft carpet (15 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Shraddha Paradise have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 350 covered car parking spaces for Shraddha Paradise.

How big is the land of Shraddha Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise stands on 8,114 sq m of land (about 2.0 acres), with 26,148 sq m of sanctioned built-up area.

What is the track record of Shraddha Paradise's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shraddha Paradise?

Google Maps has reviews of Shraddha Paradise written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shraddha Paradise?

Shraddha Paradise by Shraddha Prime Projects Limited is in Borivali, Mumbai, pincode 400092 (near Rajendra Nagar, Magathane, Shimpoli), Maharashtra, and is registered on MahaRERA as P51800052244, per GharKundli's check of MahaRERA records. Its boundaries filed there include Western Railway DT4 Railway Yards-Tracks, Hari Om Nagar. Its land is filed as 63/2,3(pt.),4,5,7,10(pt.). GharKundli lists all 362 MahaRERA projects in Borivali West (400092).

How many flats are in Shraddha Paradise, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise has 356 homes in 1 tower registered on MahaRERA, and 68% of them are sold or booked.

When was Shraddha Paradise registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Paradise was registered on MahaRERA on 2 August 2023. GharKundli did not find a title report on the land on file there.

Does Shraddha Paradise have any legal issues or court cases?

No court cases are listed for Shraddha Paradise on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shraddha Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shraddha Prime Projects Limited, which has 7 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Borivali West (400092)

All 362 projects in Borivali West (400092) →

Other projects by Shraddha Prime Projects Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.