OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
by MAVERICK REALTORS (Tanishq) · Mulund West, MumbaiAlso near Bhandup West, Mulund East, Off Dmart
Possession date of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.: 30 March 2027, moved from 31 December 2019 (83 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008649, and currently active. Its completion date has moved from December 2019 to March 2027: 83 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
How the possession date of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800003830)
Reason the builder gave MahaRERA:
“On account of low demand and slowdown in Real Estate Sector because of Demonetization and GST there is delay in completion of Project. It is expected that Project would get completed by Sep 2020 and Occupancy Certificate shall be obtained be…” Read the full reason
“On account of low demand and slowdown in Real Estate Sector because of Demonetization and GST there is delay in completion of Project. It is expected that Project would get completed by Sep 2020 and Occupancy Certificate shall be obtained before 30th December 2020. Kindly therefore grant extension till 30th December 2020.”30 June 2022
Extended at the builder's request (MahaRERA application EXT51800010289)
Reason the builder gave MahaRERA:
“On account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Proje…” Read the full reason
“On account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Sep 2021 and Occupancy Certificate shall be obtained on or before 31st May 2022. Kindly, therefore, grant extension till 30th June, 2022.”31 October 2023
Extended at the builder's request (MahaRERA application EXT51800012933)
Reason the builder gave MahaRERA:
“It’s a redevelopment project on account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a…” Read the full reason
“It’s a redevelopment project on account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Aug’ 2023 and Occupancy Certificate shall be obtained on or before 30th Sep’ 2023. Kindly, therefore, grant extension till 31st Oct, 2023.”30 November 2026
Extended at the builder's request (MahaRERA application EA07082622047)
Reason the builder gave MahaRERA:
“Dear Sir/Madam, We have received Occupancy Certificate/Completion Certificate of the project, the same was uploaded on Rera Portal along with Form 4, which came to be rejected as Occupancy Certificate date was post Rera completion date, so…” Read the full reason
“Dear Sir/Madam, We have received Occupancy Certificate/Completion Certificate of the project, the same was uploaded on Rera Portal along with Form 4, which came to be rejected as Occupancy Certificate date was post Rera completion date, so we request your goodself to please allow us extension till 30.11.2026”30 March 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.’s extension records on MahaRERA (P51800008649), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008649
- Status
- Registered and active
- Builder
- MAVERICK REALTORS
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- March 2027
- Delay so far
- 83 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 31
- Sold or booked
- 94%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD., as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OLD HEMANT VILLA CHS LTD | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- OLD HEMANT VILLA CHS LTD: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. every month.
OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 461 – 688 | 20 |
| 2 BHK | 669 – 746 | 10 |
| 3 BHK | 982 | 1 |
- Buildings: OLD HEMANT VILLA CHS LTD (21 floors, 31 units)
- Land: 572 sq m (about 0.1 acres) · sanctioned built-up 1,780 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Maverick Realtors (a group of 9 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 7 finished, 2 within the promised date and 5 needed more time (typically 15 months); 11 still being built, 5 past the promised date (typically 48 months late); 3 lapsed. 8 complaints on MahaRERA across 5 projects.
Read Google reviews of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
What is the possession date of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. in Mulund West, Mumbai is 30 March 2027 — 83 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
Builders and listing sites often quote an earlier "target" date for handover. The completion date OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.'s builder has filed on MahaRERA, the official one, is 30 March 2027, already 83 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. extended?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.'s builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2020, giving the reason "On account of low demand and slowdown in Real Estate Sector because of Demonetization and GST there is delay in completion of Project. It is expected that Project would get completed by Sep 2020 and Occupancy Certificate shall be obtained before 30th December 2020. Kindly therefore grant extension till 30th December 2020."; to 30 June 2022, giving the reason "On account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Sep 2021 and Occupancy Certificate shall be obtained on or before 31st May 2022. Kindly, therefore, grant extension till 30th June, 2022."; to 31 October 2023, giving the reason "It’s a redevelopment project on account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Aug’ 2023 and Occupancy Certificate shall be obtained on or before 30th Sep’ 2023. Kindly, therefore, grant extension till 31st Oct, 2023."; to 30 November 2026, giving the reason "Dear Sir/Madam, We have received Occupancy Certificate/Completion Certificate of the project, the same was uploaded on Rera Portal along with Form 4, which came to be rejected as Occupancy Certificate date was post Rera completion date, so we request your goodself to please allow us extension till 30.11.2026". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. in Mulund West, Mumbai is P51800008649.
Is OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. is registered as P51800008649 and its status is "Registered and active".
What is the construction status of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work on OLD HEMANT VILLA CHS LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. is registered on MahaRERA as P51800008649, its completion date has moved 83 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.'s possession date changes?
The latest dates are on OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.'s MahaRERA page (P51800008649). GharKundli's Kundli Watch sends a free WhatsApp update on OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. have?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. has one building filed: OLD HEMANT VILLA CHS LTD with 21 floors and 31 units.
What are the flat sizes (carpet area) in OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.: 1 BHK: 461 to 688 sq ft carpet (20 homes); 2 BHK: 669 to 746 sq ft carpet (10 homes); 3 BHK: 982 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. stands on 572 sq m of land (about 0.1 acres), with 1,780 sq m of sanctioned built-up area.
What is the track record of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.'s builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Maverick Realtors (a group of 9 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 7 finished, 2 within the promised date and 5 needed more time (typically 15 months); 11 still being built, 5 past the promised date (typically 48 months late); 3 lapsed. 8 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
Google Maps has reviews of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. by MAVERICK REALTORS (Tanishq) is in Mulund West, Mumbai (pincode 400080), near Bhandup West, Mulund East, Off Dmart, Maharashtra, and is registered on MahaRERA as P51800008649, per GharKundli's check of MahaRERA records.
How many homes are in OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. has 31 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.
When was OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
No court cases are listed for OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAVERICK REALTORS, the company Tanishq files this project under, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400080
- MULUND MAHAVIRDHAM CO. OP. HOUSING SOC. LTD.
- Keshavpada
- ARIHANT ROYALE
- THE SANCTUARY - TOWER 5
- Dhanraj Tower
- Madhuvan Nivanta
- Shraddha Paradise Enclave
- Malhar Guide
Other projects by MAVERICK REALTORS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.