Om Sakthi Co.op.hsg.soc.ltd
by MAVERICK REALTORS (Titan) · Mulund West, Mumbai 400080Also near Mulund East, Bhandup West, Off Dmart
What’s in the report? →Possession date of Om Sakthi Co.op.hsg.soc.ltd (MahaRERA P51800007273): 30 September 2027, moved from 31 December 2018 (105 months later). It has 32 homes (2 BHK and 3 BHK, 773–871 sq ft carpet), 93% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007273, and currently active.
Source: MahaRERA website — records for P51800007273, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Om Sakthi Co.op.hsg.soc.ltd?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Om Sakthi Co.op.hsg.soc.ltd has moved
31 December 2018
Completion date given when the project was registered
31 December 2019
Extended at the builder's request (MahaRERA application EXT51800001100)
Reason the builder gave MahaRERA:
“On account of low demand & slow down in Real Estate Sector because of Demonetization and GST , there is delay in completion of Project. It is expected that Project would get completed by Sept 2019 and Occupancy Certificate shall be obtained…” Read the full reason
“On account of low demand & slow down in Real Estate Sector because of Demonetization and GST , there is delay in completion of Project. It is expected that Project would get completed by Sept 2019 and Occupancy Certificate shall be obtained before 31st December 2019. Kindly, therefore , grant extension till 31st December , 2019.”31 January 2024
Extended at the builder's request (MahaRERA application EXT51800015209)
Reason the builder gave MahaRERA:
“It’s a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work is going on. We were scheduled to…” Read the full reason
“It’s a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work is going on. We were scheduled to complete the project by 31st December 2019 but on account of increase in FSI & restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project…”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800018273)
Reason the builder gave MahaRERA:
“It's a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work is going on. We were scheduled to…” Read the full reason
“It's a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work is going on. We were scheduled to complete the project by 31st December 2019 but on account of increase in FSI & restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar' 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project…”30 September 2027
Extended at the builder's request (MahaRERA application EA10092622506)
Reason the builder gave MahaRERA:
“Dear Sir/Madam, It's a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work of the entire proj…” Read the full reason
“Dear Sir/Madam, It's a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work of the entire project is complete, but due to the Parking Tower not functioning properly, the appropriate government authority is waiting for it to be rectified for issuance of Occupation Certificate. And due to the same it is expected that the said work would get completed by March' 2027 and Occupancy Certificate shall be obtained on or before 30th September' 2027. Kindly…”
Source: Om Sakthi Co.op.hsg.soc.ltd’s extension records on MahaRERA (P51800007273), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Om Sakthi Co.op.hsg.soc.ltd
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007273
- Status
- Registered and active
- Builder
- MAVERICK REALTORS
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- September 2027
- Delay so far
- 105 months
- Homes
- 32
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of Om Sakthi Co.op.hsg.soc.ltd, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OM SAKTHI CO OP HSG SOC LTD | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- OM SAKTHI CO OP HSG SOC LTD: covers 18 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Om Sakthi Co.op.hsg.soc.ltd every 1–2 months.
Om Sakthi Co.op.hsg.soc.ltd: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 773 | 20 |
| 3 BHK | 871 | 12 |
- Buildings: OM SAKTHI CO OP HSG SOC LTD (18 floors, 32 units)
- Land: 972 sq m (about 0.2 acres) · sanctioned built-up 2,625 sq m
- Land, as filed: 1369
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Maverick Realtors (a group of 9 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 7 finished, 2 within the promised date and 5 needed more time (typically 15 months); 11 still being built, 5 past the promised date (typically 48 months late); 3 lapsed. 8 complaints on MahaRERA across 5 projects.
Read Google reviews of Om Sakthi Co.op.hsg.soc.ltd →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Om Sakthi Co.op.hsg.soc.ltd: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Om Sakthi Co.op.hsg.soc.ltd
What is the possession date of Om Sakthi Co.op.hsg.soc.ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Om Sakthi Co.op.hsg.soc.ltd in Mulund West, Mumbai is 30 September 2027 — 105 months later than 31 December 2018, the date given at registration.
The date has already moved 105 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Om Sakthi Co.op.hsg.soc.ltd?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Om Sakthi Co.op.hsg.soc.ltd's builder has filed on MahaRERA, the official one, is 30 September 2027, already 105 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Om Sakthi Co.op.hsg.soc.ltd extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2019, giving the reason "On account of low demand & slow down in Real Estate Sector because of Demonetization and GST , there is delay in completion of Project. It is expected that Project would get completed by Sept 2019 and Occupancy Certificate shall be obtained before 31st December 2019. Kindly, therefore , grant extension till 31st December , 2019."; to 31 January 2024, giving the reason "It’s a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work is going on. We were scheduled to complete the project by 31st December 2019 but on account of increase in FSI & restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project…"; to 31 December 2024, giving the reason "It's a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work is going on. We were scheduled to complete the project by 31st December 2019 but on account of increase in FSI & restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar' 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project…"; to 30 September 2027, giving the reason "Dear Sir/Madam, It's a redevelopment project, the Extension is due to increase in FSI, certain allottees / members requested us to amend plans and make this units bigger. The approval for the same has been received & work of the entire project is complete, but due to the Parking Tower not functioning properly, the appropriate government authority is waiting for it to be rectified for issuance of Occupation Certificate. And due to the same it is expected that the said work would get completed by March' 2027 and Occupancy Certificate shall be obtained on or before 30th September' 2027. Kindly…".
What is the RERA number of Om Sakthi Co.op.hsg.soc.ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Om Sakthi Co.op.hsg.soc.ltd in Mulund West, Mumbai is P51800007273.
Is Om Sakthi Co.op.hsg.soc.ltd registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd is registered as P51800007273 and its status is "Registered and active".
What is the current construction status of Om Sakthi Co.op.hsg.soc.ltd? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd's status on MahaRERA is "Registered and active". As filed by the builder, slab work on OM SAKTHI CO OP HSG SOC LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Om Sakthi Co.op.hsg.soc.ltd have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Om Sakthi Co.op.hsg.soc.ltd safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd is registered on MahaRERA as P51800007273, its completion date has moved 105 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Om Sakthi Co.op.hsg.soc.ltd?
Om Sakthi Co.op.hsg.soc.ltd is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Om Sakthi Co.op.hsg.soc.ltd start at 773 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Om Sakthi Co.op.hsg.soc.ltd?
For a flat in Om Sakthi Co.op.hsg.soc.ltd (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Om Sakthi Co.op.hsg.soc.ltd received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd is still under construction, with 30 September 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Om Sakthi Co.op.hsg.soc.ltd a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd is a redevelopment: 18 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Om Sakthi Co.op.hsg.soc.ltd uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Om Sakthi Co.op.hsg.soc.ltd was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Om Sakthi Co.op.hsg.soc.ltd's possession date changes?
The latest dates are on Om Sakthi Co.op.hsg.soc.ltd's MahaRERA page (P51800007273). GharKundli's Kundli Watch sends a free WhatsApp update on Om Sakthi Co.op.hsg.soc.ltd every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Om Sakthi Co.op.hsg.soc.ltd have?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd has one building filed: OM SAKTHI CO OP HSG SOC LTD with 18 floors and 32 units.
What are the flat sizes (carpet area) in Om Sakthi Co.op.hsg.soc.ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Om Sakthi Co.op.hsg.soc.ltd: 2 BHK: 773 sq ft carpet (20 homes); 3 BHK: 871 sq ft carpet (12 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Om Sakthi Co.op.hsg.soc.ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd stands on 972 sq m of land (about 0.2 acres), with 2,625 sq m of sanctioned built-up area.
What is the track record of Om Sakthi Co.op.hsg.soc.ltd's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Maverick Realtors (a group of 9 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 7 finished, 2 within the promised date and 5 needed more time (typically 15 months); 11 still being built, 5 past the promised date (typically 48 months late); 3 lapsed. 8 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Om Sakthi Co.op.hsg.soc.ltd?
Google Maps has reviews of Om Sakthi Co.op.hsg.soc.ltd written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Om Sakthi Co.op.hsg.soc.ltd?
Om Sakthi Co.op.hsg.soc.ltd by MAVERICK REALTORS (Titan) is in Mulund West, Mumbai, pincode 400080 (near Mulund East, Bhandup West, Off Dmart), Maharashtra, and is registered on MahaRERA as P51800007273, per GharKundli's check of MahaRERA records. Its land is filed as 1369. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Om Sakthi Co.op.hsg.soc.ltd, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd has 32 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was Om Sakthi Co.op.hsg.soc.ltd registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sakthi Co.op.hsg.soc.ltd was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Om Sakthi Co.op.hsg.soc.ltd have any legal issues or court cases?
No court cases are listed for Om Sakthi Co.op.hsg.soc.ltd on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Om Sakthi Co.op.hsg.soc.ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAVERICK REALTORS, the company Titan files this project under, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Om Sakthi Co.op.hsg.soc.ltd
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Mulund West (400080)
- Shraddha Paradise Enclave
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Mulund Mahavirdham Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
Other projects by MAVERICK REALTORS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.