Possession date of GOLDEN VIEW: 31 December 2026, moved from 28 November 2022 (49 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000024295, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GOLDEN VIEW?
How the possession date of GOLDEN VIEW has moved
28 November 2022
Completion date given when the project was registered
28 November 2023
Extended at the builder's request (MahaRERA application EXT52000013172)
Reason the builder gave MahaRERA: “DUE TO AMENDMENT”
28 November 2024
Extended at the builder's request (MahaRERA application EXT52000022931)
Reason the builder gave MahaRERA: “Due to unforeseen circumstances, we are applying for extension.”
28 November 2025
Extended at the builder's request (MahaRERA application EXT52000027125)
Reason the builder gave MahaRERA: “We have recently received the new Commencement Certificate and the associated plan. As a result, we kindly request an extension of the current deadline. After the extension is granted, we will proceed with the necessary changes as required”
31 December 2026
Extended at the builder's request (MahaRERA application EA17022619880)
Reason the builder gave MahaRERA:
“The Project scope was revised, increasing the number of units and requiring a Revised Commencement Certificate, which is awaited. Construction was delayed due to approval-related procedural delays and labour shortage beyond the Promoter’s c…” Read the full reason
“The Project scope was revised, increasing the number of units and requiring a Revised Commencement Certificate, which is awaited. Construction was delayed due to approval-related procedural delays and labour shortage beyond the Promoter’s control.”
Source: GOLDEN VIEW’s extension records on MahaRERA (P52000024295), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GOLDEN VIEW
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000024295
- Status
- Registered and active
- Builder
- SAMRUDDHI DEVELOPERS
- Location
- Panvel, Raigarh · 410206
- Project type
- Others
- Registered on
- 3 Feb 2020
- Completion date at registration
- November 2022
- Latest completion date
- December 2026
- Delay so far
- 49 months
- Homes
- 40
- Sold or booked
- 75%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 20
Construction progress of GOLDEN VIEW, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GOLDEN VIEW | 100% | 70% | 27.5% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- GOLDEN VIEW: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOLDEN VIEW every month.
GOLDEN VIEW: buildings, flats and land, as filed on MahaRERA
- Buildings: GOLDEN VIEW (6 floors, 46 units)
- Land: 700 sq m (about 0.2 acres) · sanctioned built-up 1,019 sq m
- Boundaries filed include: PROP 18MTR WIDE ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Golden Stone Construction (a group of 2 linked companies) has 7 projects on MahaRERA since 2018, this one included. Of the 7 GharKundli has checked: 2 still being built, 2 past the promised date (typically 33 months late); 5 lapsed. 4 complaints on MahaRERA across 2 projects.
Read Google reviews of GOLDEN VIEW →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GOLDEN VIEW: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GOLDEN VIEW
What is the possession date of GOLDEN VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GOLDEN VIEW in Panvel, Raigarh is 31 December 2026 — 49 months later than 28 November 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for GOLDEN VIEW?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GOLDEN VIEW's builder has filed on MahaRERA, the official one, is 31 December 2026, already 49 months later than the 28 November 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GOLDEN VIEW extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW's builder applied to MahaRERA to extend the completion date 4 times: to 28 November 2023, giving the reason "DUE TO AMENDMENT"; to 28 November 2024, giving the reason "Due to unforeseen circumstances, we are applying for extension."; to 28 November 2025, giving the reason "We have recently received the new Commencement Certificate and the associated plan. As a result, we kindly request an extension of the current deadline. After the extension is granted, we will proceed with the necessary changes as required"; to 31 December 2026, giving the reason "The Project scope was revised, increasing the number of units and requiring a Revised Commencement Certificate, which is awaited. Construction was delayed due to approval-related procedural delays and labour shortage beyond the Promoter’s control.".
What is the RERA number of GOLDEN VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GOLDEN VIEW in Panvel, Raigarh is P52000024295.
Is GOLDEN VIEW registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW is registered as P52000024295 and its status is "Registered and active".
What is the construction status of GOLDEN VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GOLDEN VIEW is 70% done and internal work 27.5%. GharKundli's full report compares construction progress with the deadline.
Does GOLDEN VIEW have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GOLDEN VIEW safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW is registered on MahaRERA as P52000024295, its completion date has moved 49 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GOLDEN VIEW's possession date changes?
The latest dates are on GOLDEN VIEW's MahaRERA page (P52000024295). GharKundli's Kundli Watch sends a free WhatsApp update on GOLDEN VIEW every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GOLDEN VIEW have?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW has one building filed: GOLDEN VIEW with 6 floors and 46 units.
How big is the land of GOLDEN VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW stands on 700 sq m of land (about 0.2 acres), with 1,019 sq m of sanctioned built-up area.
What is the track record of GOLDEN VIEW's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Golden Stone Construction (a group of 2 linked companies) has 7 projects on MahaRERA since 2018, this one included. Of the 7 GharKundli has checked: 2 still being built, 2 past the promised date (typically 33 months late); 5 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of GOLDEN VIEW?
Google Maps has reviews of GOLDEN VIEW written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GOLDEN VIEW?
GOLDEN VIEW by SAMRUDDHI DEVELOPERS is in Panvel, Raigarh (pincode 410206), near Karanjade, Pushpak New, Pushpak- Vadghar, Maharashtra, and is registered on MahaRERA as P52000024295, per GharKundli's check of MahaRERA records. Its boundaries filed there include PROP 18MTR WIDE ROAD.
How many homes are in GOLDEN VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW has 40 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.
When was GOLDEN VIEW registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN VIEW was registered on MahaRERA on 3 February 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on GOLDEN VIEW?
No court cases are listed for GOLDEN VIEW on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of GOLDEN VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMRUDDHI DEVELOPERS, which has 20 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GOLDEN VIEW
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Raigad →
Other projects in pincode 410206
- Wise City RZ-01 Plotted Development - Phase 3
- Crystal Co-Operative Housing Society Limited
- SAI SIDDHI MADHUBAN
- Pandurang Heights
- Sai Nilay
- MUKTA RESIDENCY
- Shanmukhi Spanda
- Shivesh Mahavir
Other projects by SAMRUDDHI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.