Veda
by Srujan Development and Construction Division · Gundavli Andheri East, MumbaiAlso near Andheri West, Marol, D.N.Nagar
Possession date of Veda: 31 December 2024, moved from 30 June 2021 (42 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800002383. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about Veda?
How the possession date of Veda has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800009733)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS”
30 June 2023
Extended at the builder's request (MahaRERA application EXT51800013375)
Reason the builder gave MahaRERA:
“DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/06/2023 Building work is completed but Fire OC is pending due to installation of alte…” Read the full reason
“DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/06/2023 Building work is completed but Fire OC is pending due to installation of alternative meter which is pending due to pending Road digging permission from BMC since 4-5 month Therefore we could not make application for occupation Certificate.”31 December 2023
Extended at the builder's request (MahaRERA application EXT51800017143)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51800018224)
Reason the builder gave MahaRERA: “WE HAVE UPLOADED MAHARERA CHAIRPERSON ORDER VIDE CASE NO.79 of 2023 dated 23.11.2023 which grant extension to our Project RERA Registration from 01.07.2023 to 31.12.2024”
Source: Veda’s extension records on MahaRERA (P51800002383), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Veda
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800002383
- Status
- Lapsed (registration period ended)
- Builder
- Srujan Development and Construction Division
- Location
- Gundavli Andheri East, Mumbai · 400069
- Project type
- Others
- Registered on
- 31 Jul 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2024
- Delay so far
- 42 months
- Homes
- 222
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of Veda, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Veda | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Veda every month.
Veda: buildings, flats and land, as filed on MahaRERA
- Buildings: Veda (21 floors)
- Land: 5,413 sq m (about 1.3 acres) · sanctioned built-up 8,812 sq m · recreational space 381 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Veda →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Veda: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Veda
What is the possession date of Veda?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Veda in Gundavli Andheri East, Mumbai is 31 December 2024 — 42 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Veda?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Veda's builder has filed on MahaRERA, the official one, is 31 December 2024, already 42 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Veda extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS"; to 30 June 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/06/2023 Building work is completed but Fire OC is pending due to installation of alternative meter which is pending due to pending Road digging permission from BMC since 4-5 month Therefore we could not make application for occupation Certificate."; to 31 December 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023"; to 31 December 2024, giving the reason "WE HAVE UPLOADED MAHARERA CHAIRPERSON ORDER VIDE CASE NO.79 of 2023 dated 23.11.2023 which grant extension to our Project RERA Registration from 01.07.2023 to 31.12.2024".
What is the RERA number of Veda?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Veda in Gundavli Andheri East, Mumbai is P51800002383.
Is Veda registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda is registered as P51800002383 and its status is "Lapsed (registration period ended)".
What is the construction status of Veda?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Veda is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Veda have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Veda safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda is registered on MahaRERA as P51800002383, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Veda's possession date changes?
The latest dates are on Veda's MahaRERA page (P51800002383). GharKundli's Kundli Watch sends a free WhatsApp update on Veda every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Veda have?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda has one building filed: Veda with 21 floors.
How big is the land of Veda?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda stands on 5,413 sq m of land (about 1.3 acres), with 8,812 sq m of sanctioned built-up area and 381 sq m of recreational open space.
Where can I read reviews of Veda?
Google Maps has reviews of Veda written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Veda?
Veda by Srujan Development and Construction Division is in Gundavli Andheri East, Mumbai (pincode 400069), near Andheri West, Marol, D.N.Nagar, Maharashtra, and is registered on MahaRERA as P51800002383, per GharKundli's check of MahaRERA records.
How many homes are in Veda?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda has 222 homes in 1 tower registered on MahaRERA.
When was Veda registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Veda was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Veda?
No court cases are listed for Veda on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Veda?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Srujan Development and Construction Division.
Check it yourself on MahaRERA
- How to check the possession date of Veda
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400069
- THE KOLLAGE
- AMEY APARTMENTS
- Parleshwar Aangan
- AARHAM
- Sajay Business Hub
- Sankirt Jasmine
- Mass Marquise
- Shri Shankarpuri
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.