SATRA PARK
by SHREENIVAS DEVELOPERS · Vile Parle East, MumbaiAlso near Borivali West, Borivali East, Shimpoli
Possession date of SATRA PARK: 30 December 2021. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800007235. Status: Lapsed (registration period ended). 12 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2021) has passed.
What do you want to know about SATRA PARK?
GharKundli’s full report on SATRA PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 12 complaints and 1 court case, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007235
- Status
- Lapsed (registration period ended)
- Builder
- SHREENIVAS DEVELOPERS
- Location
- Vile Parle East, Mumbai · 400092
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- December 2021
- Homes
- 248
- Towers
- 3
- Complaints on MahaRERA
- 12
- Court cases listed
- 1
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of SATRA PARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 94% |
| WING B | 100% | 100% | 100% | 94% |
| WING C | 100% | 100% | 100% | 91% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SATRA PARK every month.
SATRA PARK: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (22 floors) · WING B (21 floors) · WING C (22 floors)
- Land: 16,560 sq m (about 4.1 acres) · sanctioned built-up 24,269 sq m · recreational space 1,368 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SATRA PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SATRA PARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SATRA PARK
What is the possession date of SATRA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SATRA PARK in Vile Parle East, Mumbai is 30 December 2021. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SATRA PARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SATRA PARK's builder has filed on MahaRERA, the official one, is 30 December 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SATRA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SATRA PARK in Vile Parle East, Mumbai is P51800007235.
Is SATRA PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SATRA PARK is registered as P51800007235 and its status is "Lapsed (registration period ended)".
What is the construction status of SATRA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), SATRA PARK's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SATRA PARK have complaints on MahaRERA?
12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SATRA PARK safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SATRA PARK is registered on MahaRERA as P51800007235, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 12 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SATRA PARK's possession date changes?
The latest dates are on SATRA PARK's MahaRERA page (P51800007235). GharKundli's Kundli Watch sends a free WhatsApp update on SATRA PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SATRA PARK have?
According to GharKundli's check of MahaRERA records (updated November 2026), SATRA PARK has 3 buildings filed: WING A with 22 floors; WING B with 21 floors; WING C with 22 floors.
How big is the land of SATRA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), SATRA PARK stands on 16,560 sq m of land (about 4.1 acres), with 24,269 sq m of sanctioned built-up area and 1,368 sq m of recreational open space.
Where can I read reviews of SATRA PARK?
Google Maps has reviews of SATRA PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SATRA PARK?
SATRA PARK by SHREENIVAS DEVELOPERS is in Vile Parle East, Mumbai (pincode 400092), near Borivali West, Borivali East, Shimpoli, Maharashtra, and is registered on MahaRERA as P51800007235, per GharKundli's check of MahaRERA records.
How many homes are in SATRA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), SATRA PARK has 248 homes in 3 towers registered on MahaRERA.
When was SATRA PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SATRA PARK was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SATRA PARK?
1 court case is listed for SATRA PARK on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SATRA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREENIVAS DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SATRA PARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects in Borivali West (400092) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.