ARIHANT ADARSH PHASE I

by ARIHANT SUPERSTRUCTURES LIMITED · Panvel, Raigarh

Possession date of ARIHANT ADARSH PHASE I: 30 April 2033, moved from 31 March 2030 (33 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000045699, and currently active. Its completion date has moved from March 2030 to April 2033: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ARIHANT ADARSH PHASE I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ARIHANT ADARSH PHASE I has moved

  1. 31 March 2030

    Completion date given when the project was registered

  2. 31 December 2032

    Extended at the builder's request (MahaRERA application EXT52000019899)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. As we have 0 sold units, we do not require consents.”
  3. 30 April 2033

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ARIHANT ADARSH PHASE I’s extension records on MahaRERA (P52000045699), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ARIHANT ADARSH PHASE I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints and 4 court cases, and how it ended
  • Construction pace against the April 2033 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000045699
Status
Registered and active
Builder
ARIHANT SUPERSTRUCTURES LIMITED
Location
Panvel, Raigarh · 410208
Project type
Others
Registered on
6 Jun 2022
Completion date at registration
March 2030
Latest completion date
April 2033
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
778
Sold or booked
51%
Towers
2
Complaints on MahaRERA
5
Court cases listed
4
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
14

Construction progress of ARIHANT ADARSH PHASE I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%31%10%0%
Wing B50%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A: covers 37 floors
  • Wing B: covers 37 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT ADARSH PHASE I every month.

ARIHANT ADARSH PHASE I: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (37 floors, 353 units) · Wing B (37 floors, 425 units)
  • Car parking: 50 covered
  • Land: 4,041 sq m (about 1.0 acres) · sanctioned built-up 43,347 sq m · recreational space 687 sq m

The builder’s record and reviews

Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects.

Read Google reviews of ARIHANT ADARSH PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ARIHANT ADARSH PHASE I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ARIHANT ADARSH PHASE I

What is the possession date of ARIHANT ADARSH PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT ADARSH PHASE I in Panvel, Raigarh is 30 April 2033 — 33 months later than 31 March 2030, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ARIHANT ADARSH PHASE I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT ADARSH PHASE I's builder has filed on MahaRERA, the official one, is 30 April 2033, already 33 months later than the 31 March 2030 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ARIHANT ADARSH PHASE I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I's builder applied to MahaRERA to extend the completion date once: to 31 December 2032, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. As we have 0 sold units, we do not require consents.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ARIHANT ADARSH PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT ADARSH PHASE I in Panvel, Raigarh is P52000045699.

Is ARIHANT ADARSH PHASE I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I is registered as P52000045699 and its status is "Registered and active".

What is the construction status of ARIHANT ADARSH PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 31% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does ARIHANT ADARSH PHASE I have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ARIHANT ADARSH PHASE I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I is registered on MahaRERA as P52000045699, its completion date has moved 33 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ARIHANT ADARSH PHASE I's possession date changes?

The latest dates are on ARIHANT ADARSH PHASE I's MahaRERA page (P52000045699). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT ADARSH PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ARIHANT ADARSH PHASE I have?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I has 2 buildings filed: Wing A with 37 floors and 353 units; Wing B with 37 floors and 425 units.

How much parking does ARIHANT ADARSH PHASE I have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 50 covered car parking spaces for ARIHANT ADARSH PHASE I.

How big is the land of ARIHANT ADARSH PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I stands on 4,041 sq m of land (about 1.0 acres), with 43,347 sq m of sanctioned built-up area and 687 sq m of recreational open space.

What is the track record of ARIHANT ADARSH PHASE I's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ARIHANT ADARSH PHASE I?

Google Maps has reviews of ARIHANT ADARSH PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ARIHANT ADARSH PHASE I?

ARIHANT ADARSH PHASE I by ARIHANT SUPERSTRUCTURES LIMITED is in Panvel, Raigarh (pincode 410208), Maharashtra, and is registered on MahaRERA as P52000045699, per GharKundli's check of MahaRERA records.

How many homes are in ARIHANT ADARSH PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I has 778 homes in 2 towers registered on MahaRERA, and 51% of them are sold or booked.

When was ARIHANT ADARSH PHASE I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ADARSH PHASE I was registered on MahaRERA on 6 June 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on ARIHANT ADARSH PHASE I?

4 court cases are listed for ARIHANT ADARSH PHASE I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ARIHANT ADARSH PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT SUPERSTRUCTURES LIMITED, which has 14 other projects registered on MahaRERA.

Other projects in Panvel

All 337 projects in Taloja (410208) →

Other projects by ARIHANT SUPERSTRUCTURES LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.