ARIHANT AARADHYA PHASE II

by ARIHANT SUPERSTRUCTURES LIMITED · Bhiwandi, Thane

Possession date of ARIHANT AARADHYA PHASE II: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700049981, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ARIHANT AARADHYA PHASE II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ARIHANT AARADHYA PHASE II has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ARIHANT AARADHYA PHASE II’s extension records on MahaRERA (P51700049981), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ARIHANT AARADHYA PHASE II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700049981
Status
Registered and active
Builder
ARIHANT SUPERSTRUCTURES LIMITED
Location
Bhiwandi, Thane · 421302
Project type
Residential / Group Housing
Registered on
6 Mar 2023
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
412
Sold or booked
28%
Towers
4
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
14

Construction progress of ARIHANT AARADHYA PHASE II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NALDO100%66%14%0%
PATRACIA100%93%27%0%
QUERIDA100%53%20%0%
OSANE100%66%14%0%

Commencement certificate (CC), as filed on MahaRERA

  • NALDO: covers 15 floors
  • PATRACIA: covers 15 floors
  • QUERIDA: covers 15 floors
  • OSANE: covers 15 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT AARADHYA PHASE II every month.

ARIHANT AARADHYA PHASE II: buildings, flats and land, as filed on MahaRERA

  • Buildings: NALDO (15 floors, 82 units) · PATRACIA (15 floors, 110 units) · QUERIDA (15 floors, 110 units) · OSANE (15 floors, 110 units)
  • Car parking: 83 covered
  • Land: 29,700 sq m (about 7.3 acres) · sanctioned built-up 25,226 sq m · recreational space 6,028 sq m

The builder’s record and reviews

Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects.

Read Google reviews of ARIHANT AARADHYA PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ARIHANT AARADHYA PHASE II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ARIHANT AARADHYA PHASE II

What is the possession date of ARIHANT AARADHYA PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ARIHANT AARADHYA PHASE II in Bhiwandi, Thane is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ARIHANT AARADHYA PHASE II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT AARADHYA PHASE II's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of ARIHANT AARADHYA PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ARIHANT AARADHYA PHASE II in Bhiwandi, Thane is P51700049981.

Is ARIHANT AARADHYA PHASE II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ARIHANT AARADHYA PHASE II is registered as P51700049981 and its status is "Registered and active".

What is the construction status of ARIHANT AARADHYA PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), ARIHANT AARADHYA PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 53% to 93% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does ARIHANT AARADHYA PHASE II have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ARIHANT AARADHYA PHASE II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ARIHANT AARADHYA PHASE II is registered on MahaRERA as P51700049981, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does ARIHANT AARADHYA PHASE II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ARIHANT AARADHYA PHASE I (P51700045430, possession 31 Jul 2029). Check that your agreement names the registration of your own wing.

How can I get updates if ARIHANT AARADHYA PHASE II's possession date changes?

The latest dates are on ARIHANT AARADHYA PHASE II's MahaRERA page (P51700049981). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT AARADHYA PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ARIHANT AARADHYA PHASE II have?

According to GharKundli's check of MahaRERA records (updated November 2026), ARIHANT AARADHYA PHASE II has 4 buildings filed: NALDO with 15 floors and 82 units; PATRACIA with 15 floors and 110 units; QUERIDA with 15 floors and 110 units; OSANE with 15 floors and 110 units.

How much parking does ARIHANT AARADHYA PHASE II have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 83 covered car parking spaces for ARIHANT AARADHYA PHASE II.

How big is the land of ARIHANT AARADHYA PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), ARIHANT AARADHYA PHASE II stands on 29,700 sq m of land (about 7.3 acres), with 25,226 sq m of sanctioned built-up area and 6,028 sq m of recreational open space.

What is the track record of ARIHANT AARADHYA PHASE II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ARIHANT AARADHYA PHASE II?

Google Maps has reviews of ARIHANT AARADHYA PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ARIHANT AARADHYA PHASE II?

ARIHANT AARADHYA PHASE II by ARIHANT SUPERSTRUCTURES LIMITED is in Bhiwandi, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700049981, per GharKundli's check of MahaRERA records.

How many homes are in ARIHANT AARADHYA PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), ARIHANT AARADHYA PHASE II has 412 homes in 4 towers registered on MahaRERA, and 28% of them are sold or booked.

When was ARIHANT AARADHYA PHASE II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ARIHANT AARADHYA PHASE II was registered on MahaRERA on 6 March 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on ARIHANT AARADHYA PHASE II?

No court cases are listed for ARIHANT AARADHYA PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ARIHANT AARADHYA PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ARIHANT SUPERSTRUCTURES LIMITED, which has 14 other projects registered on MahaRERA.

All projects with possession due in 2031 in Thane →

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Other projects by ARIHANT SUPERSTRUCTURES LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.