Anaya Apartment
by Mohammad Azeem Mohiuddin Shaikh · Bhiwandi, Thane 421302
What’s in the report? →Possession date of Anaya Apartment (MahaRERA PR1330002502799): 30 April 2033. It has 28 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1330002502799, and currently active. Its completion date is now April 2033, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1330002502799, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Anaya Apartment?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Anaya Apartment has moved
31 December 2032
Completion date given when the project was registered
30 April 2033
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Anaya Apartment’s extension records on MahaRERA (PR1330002502799), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Anaya Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2033 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1330002502799
- Status
- Registered and active
- Builder
- Mohammad Azeem Mohiuddin Shaikh
- Location
- Bhiwandi, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 16 Mar 2026
- Completion date at registration
- December 2032
- Latest completion date
- April 2033
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 28
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Anaya Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Anaya Apartment | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Anaya Apartment: covers 8 floors
Latest CC order on MahaRERA: dated 10/02/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anaya Apartment every 1–2 months.
Anaya Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: Anaya Apartment (8 floors, 30 units)
- Car parking: 16 covered
- Land: 644 sq m (about 0.2 acres) · sanctioned built-up 2,183 sq m
- Boundaries filed include: 12 mtr Layout Road
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Anaya Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Anaya Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Anaya Apartment
What is the possession date of Anaya Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Anaya Apartment in Bhiwandi, Thane is 30 April 2033, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Anaya Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Anaya Apartment's builder has filed on MahaRERA, the official one, is 30 April 2033, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Anaya Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Anaya Apartment in Bhiwandi, Thane is PR1330002502799.
Is Anaya Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment is registered as PR1330002502799 and its status is "Registered and active".
What is the current construction status of Anaya Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Anaya Apartment is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Anaya Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Anaya Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment is registered on MahaRERA as PR1330002502799, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Anaya Apartment?
Anaya Apartment is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Anaya Apartment?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Anaya Apartment: gharkundli.com/tools/property-cost-calculator
Has Anaya Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment is still under construction, with 30 April 2033 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Anaya Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Anaya Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Anaya Apartment's possession date changes?
The latest dates are on Anaya Apartment's MahaRERA page (PR1330002502799). GharKundli's Kundli Watch sends a free WhatsApp update on Anaya Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Anaya Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment has one building filed: Anaya Apartment with 8 floors and 30 units.
How much parking does Anaya Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 covered car parking spaces for Anaya Apartment.
How big is the land of Anaya Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment stands on 644 sq m of land (about 0.2 acres), with 2,183 sq m of sanctioned built-up area.
What are the reviews of Anaya Apartment?
Google Maps has reviews of Anaya Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Anaya Apartment?
Anaya Apartment by Mohammad Azeem Mohiuddin Shaikh is in Bhiwandi, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as PR1330002502799, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 mtr Layout Road. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Anaya Apartment, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment has 28 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Anaya Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anaya Apartment was registered on MahaRERA on 16 March 2026. GharKundli did not find a title report on the land on file there.
Does Anaya Apartment have any legal issues or court cases?
No court cases are listed for Anaya Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Anaya Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mohammad Azeem Mohiuddin Shaikh.
Check it yourself on MahaRERA
- How to check the possession date of Anaya Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Bhiwandi (421302)
- The Pallazo
- Yuvan Prime
- Omkar Residency A-Wing
- Utsav
- Al Abbas Building No. 06
- Aai Mauli Park Building B
- R N Plaza
- Vistara World
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.