by CLUBLIFE REALTORS PRIVATE LIMITED · Bhiwandi, ThaneAlso near Kamatghar, Naupada, Narpoli

Possession date of UTSAV: 30 May 2028, moved from 15 November 2022 (62 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700012319, and currently active. Its completion date has moved from November 2022 to May 2028: 62 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 43 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about UTSAV?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of UTSAV has moved

  1. 15 November 2022

    Completion date given when the project was registered

  2. 14 November 2023

    Extended at the builder's request (MahaRERA application EXT51700011449)

    Reason the builder gave MahaRERA: “Due to lock down the workers and construction work is slow down.”
  3. 30 January 2028

    Extended at the builder's request (MahaRERA application EA16092502612)

    Reason the builder gave MahaRERA: “CHANGE IN MANAGEMENT AND FRAUD COMMITTED BY EARLIER MANAGMENT.”
  4. 30 May 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: UTSAV’s extension records on MahaRERA (P51700012319), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on UTSAV

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 43 complaints, and how it ended
  • Construction pace against the May 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700012319
Status
Registered and active
Builder
CLUBLIFE REALTORS PRIVATE LIMITED
Location
Bhiwandi, Thane · 421302
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
November 2022
Latest completion date
May 2028
Delay so far
62 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
177
Sold or booked
67%
Towers
4
Complaints on MahaRERA
43
Court cases listed
0
Appeals at the tribunal
13
Title report on file
Not found

Construction progress of UTSAV, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Utsav Wing A100%100%85%85%
Utsav Wing B100%100%85%85%
Utsav Wing C100%8%0%0%
Utsav Wing D100%8%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Utsav Wing A: covers 13 floors
  • Utsav Wing B: covers 14 floors
  • Utsav Wing C: covers 3 floors
  • Utsav Wing D: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on UTSAV every month.

UTSAV: buildings, flats and land, as filed on MahaRERA

  • Buildings: Utsav Wing A (13 floors, 71 units) · Utsav Wing B (14 floors, 70 units) · Utsav Wing C (3 floors, 18 units) · Utsav Wing D (3 floors, 18 units)
  • Car parking: 52 covered
  • Land: 5,860 sq m (about 1.4 acres) · sanctioned built-up 6,795 sq m · recreational space 1,578 sq m
  • Boundaries filed include: PIPELINE BHADWAD ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of UTSAV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

UTSAV: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about UTSAV

What is the possession date of UTSAV?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for UTSAV in Bhiwandi, Thane is 30 May 2028 — 62 months later than 15 November 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for UTSAV?

Builders and listing sites often quote an earlier "target" date for handover. The completion date UTSAV's builder has filed on MahaRERA, the official one, is 30 May 2028, already 62 months later than the 15 November 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of UTSAV extended?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV's builder applied to MahaRERA to extend the completion date 2 times: to 14 November 2023, giving the reason "Due to lock down the workers and construction work is slow down."; to 30 January 2028, giving the reason "CHANGE IN MANAGEMENT AND FRAUD COMMITTED BY EARLIER MANAGMENT.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of UTSAV?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of UTSAV in Bhiwandi, Thane is P51700012319.

Is UTSAV registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV is registered as P51700012319 and its status is "Registered and active".

What is the construction status of UTSAV?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 8% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does UTSAV have complaints on MahaRERA?

43 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is UTSAV safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV is registered on MahaRERA as P51700012319, its completion date has moved 62 months since registration and 43 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if UTSAV's possession date changes?

The latest dates are on UTSAV's MahaRERA page (P51700012319). GharKundli's Kundli Watch sends a free WhatsApp update on UTSAV every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does UTSAV have?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV has 4 buildings filed: Utsav Wing A with 13 floors and 71 units; Utsav Wing B with 14 floors and 70 units; Utsav Wing C with 3 floors and 18 units; Utsav Wing D with 3 floors and 18 units.

How much parking does UTSAV have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 52 covered car parking spaces for UTSAV.

How big is the land of UTSAV?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV stands on 5,860 sq m of land (about 1.4 acres), with 6,795 sq m of sanctioned built-up area and 1,578 sq m of recreational open space.

Where can I read reviews of UTSAV?

Google Maps has reviews of UTSAV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 43 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is UTSAV?

UTSAV by CLUBLIFE REALTORS PRIVATE LIMITED is in Bhiwandi, Thane (pincode 421302), near Kamatghar, Naupada, Narpoli, Maharashtra, and is registered on MahaRERA as P51700012319, per GharKundli's check of MahaRERA records. Its boundaries filed there include PIPELINE BHADWAD ROAD.

How many homes are in UTSAV?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV has 177 homes in 4 towers registered on MahaRERA, and 67% of them are sold or booked.

When was UTSAV registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), UTSAV was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on UTSAV?

No court cases are listed for UTSAV on MahaRERA, and 13 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of UTSAV?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CLUBLIFE REALTORS PRIVATE LIMITED.

All projects with possession due in 2028 in Thane →

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.